Permit Information
Permit NumberBLD05-03391
StatusFinaled
Name MORNING STAR PENTECOSTAL CHURCH
Site Address 3080 N WILDWOOD ST
Project Name 
Customer Number 
ePlanReviewNo
Description
RCE 8288 - Shelubay construction (MORNING STAR PENTECOSTAL CHURCH) This building is NOT fire sprinklered. To remodel an existing 10,673 square foot church building (5,802 square foot 1st story and 4,871 square foot basement). Work is to include a wheelchair lift, 3 restrooms accessible to the disabled, a new exterior exit stairway from the basement, suspended ceilings, and finishes. In addition, a 40 square foot building addition will be provided at the top of an existing basement stairway to accommodate the stairway landing. Structural work includes additional floor joists, beams, headers, columns, concrete footings, and a masonry wall. The work is required to comply with the approved drawings, the plan review report, and all applicable codes. CZC05-00239 **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/21/20109/22/20109/22/2010APASS
DetailsJim Sly
All required signatures done. OK for Occ.
DOC - Permit Finaled9/22/20109/22/20109/22/2010PPASS
DetailsJim Sly
BLD-Final9/21/20109/21/20109/21/2010PCANC
DetailsJim Sly
Vlad phone
BLD-Aging Inspection7/27/20097/27/20097/27/2009 PASS
DetailsTom Arcoraci
BLD-Final4/7/20084/8/20084/8/2008APASS
DetailsJim Sly
boris Phone #: ###-####
OK for Perm Occ........Checked HVAC and Fire......Both OK for Perm Occ. :)
BLD-Final3/27/20083/28/20083/28/2008ANR
DetailsJim Sly
Boris...###-####
Still firestopping penitrations in Mech and storage room ceilings.
BLD-Final3/26/20083/27/20083/27/2008PCANC
DetailsJim Sly
Boris = ); Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
Re-scheduled
FIRE-Final Inspection3/26/20083/26/20083/26/2008PPASS
DetailsTroy Cobbley
Life safety passed.
FIRE-Final Inspection3/18/20083/19/20083/19/2008AFAIL
DetailsTroy Cobbley
Four exit signs and two exit discharge lights still need to be added. See the electrical sheets of the approved basement plans for the locations with astericks.
BLD-Final3/11/20083/11/20083/11/2008PNR
DetailsJim Sly
borus Phone #: ###-####
Need Fire final
FIRE-Final Inspection3/3/20083/4/20083/4/2008PFAIL
DetailsTroy Cobbley
The upper level life safety is passed. The lower level is failed. There are missing exit discharge lights, emergency lights and exit signs.
BLD-Energy code compliance10/8/200710/10/200710/9/2007PPASS
DetailsJim Sly
forest Phone #: ###-####
BLD-Framing/Rough-in10/3/200710/3/200710/4/2007PPART
DetailsJim Sly
doris Note: please call 1/2 hr prior Phone #: ###-####
E. third of basement....OK
FIRE-Final Inspection9/18/20079/24/20079/24/2007AFAIL
DetailsTroy Cobbley
Boris just needed occupancy for the upstairs area which was going to be alowed per a previous agreement with dave hanniman. Life safety items are ok upstairs except for the exit signs and emergency lights that need to be installed and or repaired. I told boris I could not give him a sign off on the upstairs portion until these items were done.
BLD-Framing/Rough-in9/17/20079/18/20079/18/2007ACANC
DetailsMike Jordan
Basement area only please--boris
BLD-Final9/17/20079/18/20079/18/2007ACANC
DetailsJim Sly
upstairs and 1/2 of basement please--Boris
Talked to Boris........Need Plumb...Electr..... and Mech finals......Need Occ Req card......Need Fire final....Prior to calling for struct final Boris...###-####
BLD-Final12/13/200612/14/200612/14/2006PNR
DetailsJim Sly
Scheduled by a contractor via Hello! on 12/13/2006 at 10:11:08 AM. Contact: ###-####.
Need all req signatures.
FIRE-Conference11/30/200612/1/200612/1/2006ADONE
DetailsTroy Cobbley
I went over fire extinguisher, exit lights and emergency light placement with Bill. Also discussed was door hardware issues and exit discharge light issues. Per Carl Westfalls and I's discussion exit discharge lights will be required at both of the stairways from the basement.
BLD-Framing/Rough-in5/22/20065/23/20065/23/2006APASS
DetailsJim Sly
vlad - call 1/2 hour prior to insp; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
BLD-Framing/Rough-in5/16/20065/18/20065/18/2006APART
DetailsJim Sly
vlad//please call 30 min prior to inspection; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
Framing OK on 1st phase.......1st phase includes 1st and 2nd story.......West 2/3 of building. OK to insulate this area only.
BLD-Foundation5/17/20065/18/20065/18/2006APASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 5/17/2006 at 5:15:19 PM. Contact: ###-####.
Wall for Ext. stairway at S. side of Bldg. OK
BLD-Footing5/16/20065/17/20065/17/2006APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 5/16/2006 at 7:08:44 PM. Contact: ###-####. footing for new stairway from basement.
BLD-Framing/Rough-in5/11/20065/15/20065/15/2006ANR
DetailsMike Jordan
vlad; Phone #: ###-#### Note: please call 1/2 hr prior Internet Inspection Request from: Cathy Chiles. No access to interior of bldg.
FIRE-Conference5/4/20065/4/20065/4/2006PDONE
DetailsTroy Cobbley
Contractor requested the use of the finished areas of the church while construction continued in the recreation area. Dave Hanneman agreed as long as all life safety items had been completed in the areas to be occupied. At this point the project is not ready for inspection.
BLD-Conference5/3/20065/3/20065/3/2006PDONE
DetailsJim Sly
Vlad - please call 1/2 hr before; Phone #: ###-#### Internet Inspection Request from: Ione Coleman
Met with Vlad....walk thru. Wants to phase Constr. and Temp part of Bldg. Need to OK with fire Dept then OK with me.
BLD-Conference3/15/20063/15/20063/15/2006PDONE
DetailsJim Sly
vlad; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Met with Plumb Contr. Talked about where he can bore holes in floor joists. Looked at footing for CMU wall near elevator lift.
BLD-Conference3/10/20063/10/20063/10/2006PDONE
DetailsJim Sly
Vlad; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong and John Cook (Arch) to discuss plans.
Met with Vlad