Permit Information
Permit NumberBLD05-03413
StatusFinaled
Name VERTICAL CONSTRUCTION
Site Address 417 S 6TH ST
Project NameADA COUNTY JUSTICE CENTER
Customer Number 
ePlanReviewNo
Description
(ADA COUNTY JUSTICE CENTER) This building is fire sprinklered for area increase. To remodel the 1st story (18,080 square feet) and the basement (25,500 square feet) of an existing 50,900 square foot building for a new office and storage tenant. Except for new exterior windows, a new exterior door, and a fire sprinkler system, an existing 7,320 square foot tenant space located on the 1st story is NOT within the scope of work allowed under this permit. Work is to include interior nonbearing walls, several restrooms accessible to the disabled, suspended ceilings, new exterior windows and doors, new single ply roof membrane and insulation, millwork, and finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes. The fire sprinkler system shall comply with NFPA 13 as regulated by the Fire Code. Site work including parking was done under permit BLD05-02914. Interior demolition was done under permit BLD05-03470. (DRH05-00230, CVA05-00019, and CUP05-00073) **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/11/200610/12/200610/12/2006APASS
DetailsDave Hannah
joe; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok for perm occ
BLD-Final10/10/200610/11/200610/12/2006ADEFR
DetailsDave Hannah
joe; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Permanent Occupancy 10/12/200610/12/2006 DONE
Details
Code Occupancy Approval10/10/200610/10/200610/10/2006PPASS
DetailsWm. Michael Meloy
Compliance met.
BLD-Final7/7/20067/7/20067/7/2006PPART
DetailsDave Hannah
JOE; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok for temp occ needs other trades to go perm needs to install fright elev needs to finish installing glass needs to fix ada rest rooms
FIRE-Final Inspection7/7/20067/7/20067/7/2006PPASS
DetailsForrest France
Fire life safety correction notice items have been completed, inspection passed.
FIRE-Final Inspection7/6/20067/7/20067/7/2006ACANC
DetailsForrest France
Joe; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
BLD-Final7/5/20067/6/20067/6/2006PNR
DetailsDave Hannah
joe; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley still needs fire sign offs
FIRE-Final Inspection7/5/20067/6/20067/6/2006AFAIL
DetailsForrest France
Need to install exit signs per red line notes on approved plan set and as discussed on site, provide key box for FD use, provide sheetrock at the basement soffit where separation between fire sprinklers was designed, provide paint for flooring at the basement path of egress as indicated on approved plans, need to test emergency lighting at next inspection.
BLD-Final6/30/20067/3/20067/3/2006PCANC
DetailsDave Hannah
not ready per raylene-joe; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
FIRE-Final Inspection6/30/20067/3/20067/3/2006ACANC
DetailsForrest France
not ready per raylene -joe; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
BLD-Conference6/30/20066/30/20066/30/2006 FAIL
DetailsWm. Michael Meloy
Exterior Siding not on. OK to Bond for $4.000 for completion of of decorative siding.
BLD-Other6/15/20066/15/20066/15/2006PPART
DetailsDave Hannah
Joe, ceiling grid; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt ceiling grid rest of rooms ok to cover after elec and fire r/is are completed
BLD-Framing/Rough-in5/24/20065/24/20065/24/2006PPART
DetailsDave Hannah
Joe; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ceiling grid center area ok to cover after elec r/i is approved
BLD-Framing/Rough-in5/9/20065/9/20065/9/2006PPASS
DetailsDave Hannah
joe Note: at loading dock; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles 6th street side and basement restrooms ok to cover
BLD-Energy code compliance4/19/20064/19/20064/19/2006PPASS
DetailsDave Hannah
joe; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
BLD-Framing/Rough-in4/14/20064/17/20064/17/2006APASS
DetailsDave Hannah
Joe; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esongok to cover int walls
BLD-Energy code compliance4/11/20064/12/20064/12/2006APART
DetailsDave Hannah
Joe -- prefer late insp; call 1st before insp; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong west wall ok
BLD-Energy code compliance4/11/20064/11/20064/11/2006PPART
DetailsDave Hannah
Joe -- prefer late insp; call 1st before insp; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong ext walls south and east ok
BLD-Framing/Rough-in4/7/20064/10/20064/10/2006APART
DetailsDave Hannah
###-#### joe ext only wall framing not per plan need arch ok ok to insulate if ok with arch also needs to remover osb out of ext walls
BLD-Energy code compliance4/7/20064/10/20064/10/2006ANR
DetailsDave Hannah
###-#### joe