Permit Information
Permit NumberBLD05-03461
StatusFinaled
Name BODO DEVELOPMENT INC
Site Address 314 S 9TH ST
Project NameBODO BLDG #4-Foster Bldg
Customer Number 
ePlanReviewNo
Description
(FOSTER BUILDING SEISMIC UPGRADE) This building will be fire sprinklered for story increase and for future code trade-offs. To upgrade an existing 8,665 square foot, 4 story with basement historic building (5 stories total). Each story has a floor area of about 1,733 square feet. Work is to include concrete footings, concrete shear walls, concrete beams, wood floor infills, floor and roof sheathing, bolted connections between the diaphragms (i.e. floors and roof) and the perimeter walls, steel headers and trimmers at new wall openings in masonry walls, an interior basement stairway, new roof insulation and roof covering, seismic joints between this building and the adjacent buildings, 3 hour fire doors, and new steel beam hangers. The work is required to comply with the approved drawings, the structural design, the plan review report, and all applicable codes. The fire sprinkler system shall comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Conference6/6/20066/7/20066/7/2006PPASS
DetailsDave Hannah
Please call Paul to inspect. Thank you. ###-####
DOC - Permit Finaled6/7/20066/7/20066/7/2006PPASS
DetailsDave Hannah
BLD-Final6/7/20066/7/20066/7/2006PPASS
DetailsDave Hannah
Please call Paul to inspect. Thank you. ###-####
FIRE-Final Inspection4/21/20064/21/20064/21/2006PPASS
DetailsForrest France
The building fire alarm and sprinkler permits have been finaled, life safety for the permitted seismic upgrade work is acceptable.
BLD-Final4/20/20064/20/20064/20/2006PNR
DetailsDave Hannah
Frrest is scheduled to sign-off on the fire-life safety this afternoon. Please check with Forrest to ensure that you arrive after he has reviewed. We may have to schedule you for Friday morning...I hope not. Alex.
BLD-Final4/13/20064/14/20064/17/2006PNR
DetailsDave Hannah
Dave: We would like to do the final walk through for Foster in the after noon, around 2-3 so we still have time to get the letter of compliance from the city. Call me when you get here. needs fire sign off
BLD-Framing/Rough-in4/12/20064/13/20064/13/2006APART
DetailsDave Hannah
If possible first thing in the morning. Call Paul to review the entry stair and basement stair framing prior to drywall/cover-up. Thanks.front stairs ok but stairs into basement need to be rebuilt
BLD-Conference4/5/20064/5/20064/5/2006PPASS
DetailsDave Hannah
Please come to the office and call Alex and Paul. Thanks.