BLD-Final | 2/29/2008 | 2/29/2008 | 2/29/2008 | P | PASS |
Dave Hannah
|
|
|
mel Phone #: ###-#### ok for perm occ
|
FIRE-Final Inspection | 2/28/2008 | 2/28/2008 | 2/28/2008 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection passed, signage at the door to the FACP and riser room to be provided- verified at next visit for the adjacent building permits.
|
BLD-Final | 2/28/2008 | 2/28/2008 | 2/28/2008 | P | CANC |
Dave Hannah
|
|
|
mel Phone #: ###-####
|
Code Occupancy Approval Temp | 2/27/2008 | 2/27/2008 | 2/27/2008 | P | DONE |
Michael Garner
|
|
|
site inspection done - this is for a temporary approval - bike racks are not emplaced - but are on site - landscaping is not complete - though, the sprinklers are in place - I spoke w/onsite foreman - we agreed to a bond amount of 24K plus 10%
|
BLD-Framing/Rough-in | 7/10/2007 | 7/10/2007 | 7/10/2007 | P | PASS |
Dave Hannah
|
|
|
mel; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang
|
BLD-Framing/Rough-in | 7/9/2007 | 7/9/2007 | 7/9/2007 | P | PART |
Mike Jordan
|
|
|
mel; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang. Needs to complete firestop at 1hr. walls. Interior shearwalls not attached as per plan. Rock behind mech. chases on 2nd floor not atteched correctly. Gave ok to start rock on lid at carport. Insul installed, double rock around beams and between floor joist ok. All for bldg. 1.
|
BLD-Framing/Rough-in | 6/29/2007 | 7/2/2007 | 7/2/2007 | A | PART |
Dave Hannah
|
|
|
mel; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang ok to shear int walls
|
BLD-Conference | 4/27/2007 | 4/27/2007 | 4/27/2007 | P | PART |
Dave Hannah
|
|
|
Mel; Phone #: ###-#### Internet Inspection Request from: Victoria Beall went over fire walls ect and fire proofing
|
BLD-Other | 3/21/2007 | 3/22/2007 | 3/22/2007 | A | PART |
Dave Hannah
|
|
|
Harvey sheer wall; Phone #: ###-#### Internet Inspection Request from: Stacie Backus shear ext ok need to install flr to flr strapes
|
BLD-Foundation | 3/8/2007 | 3/9/2007 | 3/9/2007 | A | PART |
Dave Hannah
|
|
|
Harvey; Phone #: ###-#### Internet Inspection Request from: Stacie Backus columns ok to pour
|
BLD-Foundation | 3/1/2007 | 3/2/2007 | 3/2/2007 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/1/2007 at 10:21:34 AM. Contact: ###-####. columns above footing pads
|
BLD-Footing | 2/23/2007 | 2/26/2007 | 2/26/2007 | A | PART |
Dave Hannah
|
|
|
harvey ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith colunm ftgs ok to place concrete
|
BLD-Footing | 2/22/2007 | 2/23/2007 | 2/23/2007 | A | CANC |
Dave Hannah
|
|
|
harvey; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
BLD-Foundation | 1/11/2007 | 1/12/2007 | 1/12/2007 | A | PART |
Jim Storey
|
|
|
harvey - stemwall ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith rebar ok wip
|
BLD-Foundation | 1/10/2007 | 1/11/2007 | 1/11/2007 | A | NR |
Dave Hannah
|
|
|
harvey; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
BLD-Footing | 1/8/2007 | 1/9/2007 | 1/9/2007 | A | PART |
Jim Sly
|
|
|
harvey - rebar ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith Footing OK pending special inspection, tests, and approvals from MTI......3500 psi concrete design strength.
|