BLD-Final | 6/6/2006 | 6/6/2006 | 6/6/2006 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/6/2006 at 7:11:20 AM. Contact: ###-####. ok for perm occ
|
Permanent Occupancy | | 6/6/2006 | 6/6/2006 | | DONE |
|
|
|
|
BLD-Final | 5/25/2006 | 5/26/2006 | 5/26/2006 | P | PART |
Dave Hannah
|
|
|
mike - call prior to insp; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok for temp occ need to finish checking doors and glassing after its installed
|
FIRE-Final Inspection | 5/25/2006 | 5/26/2006 | 5/26/2006 | A | PASS |
Forrest France
|
|
|
Items on correction notice have been completed, fire life safety inspection passed. Note: door hardware at some locations is not installed-verified hardware on site and per door schedule is okay, final approval at structural inspection.
|
BLD-Final | 5/24/2006 | 5/24/2006 | 5/24/2006 | P | CANC |
Dave Hannah
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
FIRE-Final Inspection | 5/24/2006 | 5/24/2006 | 5/24/2006 | A | FAIL |
Forrest France
|
|
|
Three locations are missing emergency lights for the path of egress, need to provide and install fire extinguishers as discussed, provide suite address, doors are not installed at this time for verification of hardware requirements.
|
BLD-Other | 5/17/2006 | 5/17/2006 | 5/17/2006 | P | PART |
Dave Hannah
|
|
|
MIKE NOTE: GRID; Phone #: ###-#### nOTE; 3RD FLOOR Internet Inspection Request from: Cathy Chiles ceiling grid ok to cover
|
BLD-Framing/Rough-in | 4/4/2006 | 4/4/2006 | 4/4/2006 | P | PASS |
Dave Hannah
|
|
|
Mike; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong ok to cover int walls
|
BLD-Framing/Rough-in | 3/30/2006 | 3/31/2006 | 3/31/2006 | A | PART |
Dave Hannah
|
|
|
Mike; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong ok to rock one side of walls
|