Code Occupancy Approval | 4/17/2007 | 4/17/2007 | 4/18/2007 | P | PASS |
Scott M.Brown
|
|
|
ALL IN WILL SIGN FINAL AT CITY HALL
|
Permanent Occupancy | | 4/18/2007 | 4/18/2007 | | DONE |
|
|
|
|
BLD-Final | 2/28/2007 | 2/28/2007 | 2/28/2007 | | DONE |
|
|
|
Final approved for perm. occ.
|
FIRE-Final Inspection | 2/12/2007 | 2/12/2007 | 2/12/2007 | P | PASS |
Troy Cobbley
|
|
|
LIfe safety passed
|
FIRE-Final Inspection | 12/28/2006 | 12/29/2006 | 12/29/2006 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with dave hannimans permission until the sprinkler design/aisle widths are figured out. Also need curbing painted and the racking permit finaled.
|
BLD-Final | 12/28/2006 | 12/29/2006 | 12/29/2006 | P | PART |
Mike Jordan
|
|
|
greg; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. ok for temp occ. Needs fire to go perm and needs to add landing on exterior door and provide final aff. letter from special inspection agengcy.
|
BLD-Other | 12/15/2006 | 12/18/2006 | 12/18/2006 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/15/2006 at 4:22:17 PM. Contact: ###-####. grid ok
|
BLD-Framing/Rough-in | 11/14/2006 | 11/14/2006 | 11/14/2006 | P | PASS |
Jim Sly
|
|
|
greg ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith Welding report .....OK
|
BLD-Framing/Rough-in | 11/10/2006 | 11/13/2006 | 11/13/2006 | A | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 11/10/2006 at 1:27:19 PM. Contact: ###-####. Plumbing ri not completed.
|
BLD-Footing | 7/17/2006 | 7/17/2006 | 7/17/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/17/2006 at 11:14:11 AM. Contact: ###-####.
|
BLD-Footing | 7/10/2006 | 7/11/2006 | 7/11/2006 | A | DEFR |
Mike Jordan
|
|
|
craig - pouring concrete between 7 and 8 am; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley. conc. placed prior to 8:00am
|