Code Occupancy Approval | 5/1/2008 | 5/1/2008 | 5/1/2008 | A | PASS |
Carol Montgomery
|
|
|
Meets compliance with CUP05-00165
|
BLD-Final | 5/1/2008 | 5/1/2008 | 5/1/2008 | P | PASS |
Jim Sly
|
|
|
tom Phone #: ###-#### OK for Perm Occ.......Pending Zoning approval.
|
FIRE-Final Inspection | 4/29/2008 | 4/30/2008 | 4/30/2008 | A | PASS |
Troy Cobbley
|
|
|
life safety passed. A gate has been added out of the south side fenced yard with lever hardware and sign to the area of refuge have been provided on the fence.
|
BLD-Final | 4/29/2008 | 4/30/2008 | 4/29/2008 | P | CANC |
Jim Sly
|
|
|
tom Phone #: ###-#### Canc by Contr.....
|
BLD-Final | 4/1/2008 | 4/2/2008 | 4/2/2008 | A | PEND |
Jim Sly
|
|
|
Mcalvain... Talked to Tom.....Finishing up Fire/Life issues and roof.......Need fire finals.
|
BLD-Final | 3/17/2008 | 3/17/2008 | 3/17/2008 | P | DONE |
Jim Sly
|
|
|
###-####........Tom
|
BLD-Conference | 3/13/2008 | 3/13/2008 | 3/13/2008 | A | DONE |
Jim Sly
|
|
|
WIP
|
FIRE-Conference | 2/26/2008 | 2/26/2008 | 2/28/2008 | P | DONE |
Troy Cobbley
|
|
|
The conference was to address exiting issues from the south exit into the fenced tower yard. Jim Sly and myself told the contractor to either provide a gate so that employees could exit all the way out to the "area of refuge" or resubmit to plan review for approval to use the fenced tower yard as a gathering point.
|
BLD-Conference | 2/25/2008 | 2/26/2008 | 2/26/2008 | P | DONE |
Jim Sly
|
|
|
tom Phone #: ###-####
|
FIRE-Final Inspection | 12/10/2007 | 12/12/2007 | 12/13/2007 | P | CANC |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 12/10/2007 at 9:56:35 AM.
|
BLD-Final | 12/10/2007 | 12/10/2007 | 12/10/2007 | P | PART |
Jim Sly
|
|
|
tom Phone #: ###-#### Temp Occ.OK on selected part of the bldg...(offices). See notes on previous fire inspection.
|
FIRE-Final Inspection | 12/10/2007 | 12/10/2007 | 12/10/2007 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Mark Senteno's permission. The owner/building stated that only the offices were going to be occupied and that a full time fire watch was being used. The sprinkler system was to be active and this was verified by me with greg patrick with treasure valley fire protection.
|
BLD-Other | 10/23/2007 | 10/24/2007 | 10/24/2007 | A | PASS |
Jim Sly
|
|
|
tom - ceiling grid Phone #: ###-####
|
BLD-Framing/Rough-in | 9/12/2007 | 9/13/2007 | 9/13/2007 | A | PART |
Jim Sly
|
|
|
tom Phone #: ###-####
|
BLD-Framing/Rough-in | 7/17/2007 | 7/17/2007 | 7/17/2007 | P | FAIL |
Jim Sly
|
|
|
tom - also for fire caulking; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang C/N Provide ul listings for all penitrations in rated walls and wall/ceiling
|
BLD-Conference | 5/21/2007 | 5/21/2007 | 5/21/2007 | P | DONE |
Jim Sly
|
|
|
tom; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
BLD-Footing | 5/10/2007 | 5/10/2007 | 5/10/2007 | P | PASS |
Mike Jordan
|
|
|
tom; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. Interior grade beam footings.
|
BLD-Framing/Rough-in | 5/10/2007 | 5/10/2007 | 5/10/2007 | P | PASS |
Mike Jordan
|
|
|
tom; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. Interior framing. Pending elec.
|
BLD-Framing/Rough-in | 4/30/2007 | 5/1/2007 | 5/1/2007 | A | PART |
Jim Sly
|
|
|
Tom; Phone #: ###-#### Internet Inspection Request from: Andrea Whiteman OK to cover select walls
|
BLD-Other | 4/11/2007 | 4/12/2007 | 4/12/2007 | A | DONE |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 4/11/2007 at 7:21:36 AM. Walked job with Tom Crowell
|
BLD-Concrete | 2/27/2007 | 2/28/2007 | 2/28/2007 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/27/2007 at 1:31:03 PM. Contact: ###-####. Concrete pad....... OK pend special insp (strata) tests and approvals
|
BLD-Footing | 12/8/2006 | 12/12/2006 | 12/11/2006 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/8/2006 at 1:47:26 PM. Contact: ###-####. Footings OK pending special insp (STRATA) tests, and approvals.
|