Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD06-00895
StatusFinaled
Name US MODULAR GROUP
Site Address 303 N ALLUMBAUGH ST
Project NameINTERMOUNTAIN HOSPITAL
Customer Number 
ePlanReviewNo
Description
(RCE-5895, US Modular Group Inc.) Intermountain Hospital (Modular Addition) - To place a thirteen unit Modular Building System of 11,136 sq. ft. for use as a medical treatment unit on the Intermountain Hospital Campus. This building will attach to the east end of existing modular system done under BLD02-00567. A two hour fire wall is required between the two modular units. The wall shall extend 18" beyond the exterior walls on the north & south and extend from concrete foundation to bottom of the roof deck per Sec. 705.6, exception #2 on existing building side and exception #4 on new building side per State of Idaho plan review correction, 3/2/06 (modified from 30" parapet above roof 8/9/06). All openings & penetrations in the wall shall be protected. This permit scope includes installation of the foundation, piers, tie downs, landings, ramps, skirting, concrete sidewalks, electrical, plumbing & mechanical utility connections for the facility. All per approved plans. The premanufactured, 13 modular building units, to be assembled on this foundation, were reviewed and approved by the State of Idaho Division of Building Safety Building Bureau as a medical facility under Tag # 10057FB and Plan Approval # PA13398FB. NOTE: A Letter of Completion is required for this scope of work. Separate fire supression & alarm permits are required through fire department. DRH05-00347, CUP05-00130 drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/16/200611/17/200611/17/2006APASS
DetailsTom Arcoraci
kay; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
Permanent Occupancy 11/17/200611/17/2006 DONE
Details
Code Occupancy Approval  11/15/2006 PASS
ALL IN FINAL OK
BLD-Final11/9/200611/9/200611/9/2006PNR
DetailsTom Arcoraci
kay; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
FIRE-Final Inspection11/8/200611/9/200611/9/2006APASS
DetailsForrest France
Final fire life safety inspeciton passed, contractor to replace missing ceiling tile and sprinkler escutcheon at the data closet prior to occupancy as agreed.
BLD-Aging Inspection9/29/20069/29/20069/29/2006 NR
DetailsTom Arcoraci
BLD-Framing/Rough-in6/16/20066/19/20066/19/2006ADEFR
DetailsMike Jordan
Scheduled by a contractor via Hello! on 6/15/2006 at 4:26:27 PM. Contact: ###-####. State of Idaho has inspected the 2hr. wall seperating the new unit from the old unit. State will also be inspecting 1hr corridors. Modular units are already assembeled when on site. noted to contractor that copies of inspections and tags will be required at bldg. final. Did note that 2hr wall is not yet extended the min 18" horizintally or the 30" inches vertically as noted on permit and approved plans. Could not verify if 2hr. wall extetnds to footing.
BLD-Framing/Rough-in6/15/20066/16/20066/16/2006PDEFR
DetailsJim Storey
Scheduled by a contractor via Hello! on 6/15/2006 at 4:26:27 PM. Contact: ###-####. out of time rolled to monday am.
BLD-Foundation6/8/20066/9/20066/9/2006ADONE
DetailsMike Jordan
Scheduled by a contractor via Hello! on 6/8/2006 at 1:29:40 PM. interior footings, ne end, already placed when arrived on site. NO INSPECTION WAS PERFORMED.
BLD-Footing6/6/20066/6/20066/6/2006PPART
DetailsDave Hannah
bill - call prior to insp; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley ok to pour ext ftgs