Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD06-00981
StatusFinaled
Name NO TENANT (VANILLA FINISH)
Site Address 121 N 9TH ST Unit: 400
Project NamePLAZA 121-Suite 400
Customer NumberSEE COMMENTS
ePlanReviewNo
Description
(PLAZA 121-SUITE 400)(Vanilla Finish) To remodel a 2481 sq ft portion of the fourth floor for a future office tenant. NO OCCUPANCY allowed under this permit. A separate permit will be required to obtain a certificate of occupancy prior to occuping this space. Work to include, construction of interior noncombustible partitions to create reception area, office areas, installation of suspended ceiling system and related lighting, Miscellaneous related finishes. This permit also includes the extension of an existing exit stair enclosure from the third floor to the rooftop that will serve as a required exit for the roof top patio area and fourth floor tenant spaces, This building is fully fire sprinklered any alterations or modifications to the sprinkler system shall be per NFPA #13 as regulated by the fire department. RMH
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/8/200612/11/200612/11/2006APASS
DetailsDave Hannah
Dan or Jim; Phone #: ###-#### or ###-#### Internet Inspection Request from: Cathy Weisshaupt
DOC - Permit Finaled12/11/200612/11/200612/11/2006PPASS
DetailsDave Hannah
FIRE-Final Inspection12/7/200612/8/200612/8/2006PPASS
DetailsForrest France
Fire life safety final inspection passed.
BLD-Final12/1/200612/5/200612/6/2006PFAIL
DetailsDave Hannah
dan; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles needs to remove exit sign from inside and install it on the ext of the door fix ext landing at stair tower
FIRE-Final Inspection12/1/200612/5/200612/5/2006AFAIL
DetailsForrest France
Door hardware as installed at the second exit to the roof from the common corridor is not approved.
BLD-Final11/30/200612/1/200612/1/2006ACANC
DetailsDave Hannah
randy; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Conference11/29/200611/30/200611/30/2006PDONE
DetailsDave Hannah
jim - stairway advice ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
FIRE-Final Inspection11/29/200611/30/200611/30/2006PFAIL
DetailsTroy Cobbley
I tried to do inspection this morning but no approved plans are on site and the secondary exit across the roof has not been completed. Inspection will be rescheduled for tomorrow.
BLD-Conference10/30/200610/31/200610/31/2006APART
DetailsDave Hannah
Jim, early a.m. if possible; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt ceiling grid ok
BLD-Other8/23/20068/23/20068/23/2006PPART
DetailsDave Hannah
Dan, stairwell inspection; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt ok to put second layer on stair tower area
BLD-Framing/Rough-in7/18/20067/19/20067/19/2006APASS
DetailsDave Hannah
Dan; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt