BLD-Final | 12/8/2006 | 12/11/2006 | 12/11/2006 | A | PASS |
Dave Hannah
|
|
|
Dan or Jim; Phone #: ###-#### or ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
DOC - Permit Finaled | 12/11/2006 | 12/11/2006 | 12/11/2006 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 12/7/2006 | 12/8/2006 | 12/8/2006 | P | PASS |
Forrest France
|
|
|
Fire life safety final inspection passed.
|
BLD-Final | 12/1/2006 | 12/5/2006 | 12/6/2006 | P | FAIL |
Dave Hannah
|
|
|
dan; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles needs to remove exit sign from inside and install it on the ext of the door fix ext landing at stair tower
|
FIRE-Final Inspection | 12/1/2006 | 12/5/2006 | 12/5/2006 | A | FAIL |
Forrest France
|
|
|
Door hardware as installed at the second exit to the roof from the common corridor is not approved.
|
BLD-Final | 11/30/2006 | 12/1/2006 | 12/1/2006 | A | CANC |
Dave Hannah
|
|
|
randy; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Conference | 11/29/2006 | 11/30/2006 | 11/30/2006 | P | DONE |
Dave Hannah
|
|
|
jim - stairway advice ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
FIRE-Final Inspection | 11/29/2006 | 11/30/2006 | 11/30/2006 | P | FAIL |
Troy Cobbley
|
|
|
I tried to do inspection this morning but no approved plans are on site and the secondary exit across the roof has not been completed. Inspection will be rescheduled for tomorrow.
|
BLD-Conference | 10/30/2006 | 10/31/2006 | 10/31/2006 | A | PART |
Dave Hannah
|
|
|
Jim, early a.m. if possible; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt ceiling grid ok
|
BLD-Other | 8/23/2006 | 8/23/2006 | 8/23/2006 | P | PART |
Dave Hannah
|
|
|
Dan, stairwell inspection; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt ok to put second layer on stair tower area
|
BLD-Framing/Rough-in | 7/18/2006 | 7/19/2006 | 7/19/2006 | A | PASS |
Dave Hannah
|
|
|
Dan; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|