BLD-Final | 1/25/2007 | 1/25/2007 | 1/25/2007 | P | PASS |
Mike Jordan
|
|
|
Gary; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt. Final ok.
|
Code Occupancy Approval | | | 1/25/2007 | | PASS |
|
|
|
OK PER REQUIREMENTS FINAL SIGNED OFF
|
FIRE-Final Inspection | 1/23/2007 | 1/24/2007 | 1/24/2007 | A | PASS |
Forrest France
|
|
|
Door hardware corrections verified, fire life safety inspection passed.
|
Permanent Occupancy | | 1/24/2007 | 1/24/2007 | | DONE |
|
|
|
|
FIRE-Final Inspection | 1/18/2007 | 1/19/2007 | 1/19/2007 | A | FAIL |
Troy Cobbley
|
|
|
Need approved door hardware. Other items are ok.
|
BLD-Framing/Rough-in | 1/18/2007 | 1/18/2007 | 1/18/2007 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/18/2007 at 5:35:59 AM. Contact: ###-####. Wanted final insp. Still needs finals from others. Also needs special insp. on high strength bolting.
|
BLD-Footing | 10/6/2006 | 10/6/2006 | 10/6/2006 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/6/2006 at 5:26:43 AM. Contact: ###-####. Footings and column pad footings. Notified cntractor that conc. testing is required.
|