Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD06-01450
StatusFinaled
Name CM INVESTMENTS LLC
Site Address 323 W JEFFERSON ST
Project NameTHE JEFFERSON BLDG
Customer Number 
ePlanReviewNo
Description
(The Jefferson Building Parking Garage, Grading, Drainage, Underground Utilities & Landscaping) - To construct a new 35,040 square feet, single story, shell only building, with a multi-level (4 teared) basement parking garage, below a three hour horizontal assembly per IBC Section 508.2. The first floor is 11,680 square feet, will be finished with three dwelling units, along with the entry lobby and accessory storage area for the dwelling units. The basements area is 23,360 square feet and will be used as a private parking garage. This building is requried to be fire sprinklered with a NFPA 13 fire sprinkler system. Refer to BLD 06-01451 for the construction of the upper five floors, the completition of the interior of the dwelling units, the entry lobby, the parking garage and the accessory storage area. NOTE: This permit is for a shell only. The minimum ceiling height in vehicle and pedestrian areas is 7 feet. All construction per the approved plans and attached comment list. DRH05-00396 CUP05-00150 (7/24/07: Plan modification for structural slab and wall changes approved.) MJP
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection7/13/20097/14/20097/14/2009APASS
DetailsTroy Cobbley
Life safety passed.
BLD-Final2/27/20092/27/20093/2/2009ACANC
DetailsDave Hannah
BLD-Final2/26/20092/26/20092/26/2009APART
DetailsDave Hannah
Dave; We have all the signatures for this permit. Can we get the Temp.Oc. today?

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok for temp occ ok for perm occ after fire gos perm
FIRE-Final Inspection2/25/20092/26/20092/26/2009APART
DetailsTroy Cobbley
A temporary occupancy was given until the project related fire alarm permit is finaled. Life safety items will be ok to pass at that time.
FIRE-Final Inspection2/23/20092/24/20092/25/2009AFAIL
DetailsTroy Cobbley
Life safety items are ok. Just waiting for the fire alarm resubmittals which were required due to changes/additional devices.
FIRE-Final Inspection2/24/20092/24/20092/24/2009ADONE
DetailsScott Arellano
Emergency egress lighting and generator satisfactory.
BLD-Framing/Rough-in11/20/200811/21/200811/22/2008APART
DetailsDave Hannah
Dave; Could we get a re-inspect for the lower units( C3,4,5)?
Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to cover lids c3,4,5 level 1 ok to cover drops level 6 ok to start insulating roof /ceiling level7
BLD-Framing/Rough-in10/10/200810/10/200810/13/2008APART
DetailsDave Hannah
Dave; Could you do a framing inspection for the trash room, generator room, pump room, and mechanical rooms on levels P1,2,3.

Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to cover
BLD-Framing/Rough-in8/20/20088/20/20088/21/2008APART
DetailsDave Hannah
Dave; I would like to cover one side of the Trash Room wall;metal studs in garage.Two of the walls are shaft liner,no rough-in in them. Other walls have rough-in,will do one side only. Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to cover this area
BLD-Framing/Rough-in8/20/20088/20/20088/21/2008PCANC
DetailsDave Hannah
Dave; I would like to cover one side of the Trash Room wall;metal studs in garage.Two of the walls are shaft liner,no rough-in in them. Other walls have rough-in,will do one side only. Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to cover this area
BLD-Concrete2/12/20082/13/20082/13/2008PPART
DetailsDave Hannah
Rebar,tendon inspection for L3 PT slab. Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Conference2/8/20082/11/20082/12/2008PPASS
DetailsDave Hannah
Dave; Have you had a chance to check on the
framing detail where the 1hr floor meets the
2hr shaft. You were going to run it by George
and/or Marlene, I think. Let me know.
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Conference2/5/20082/5/20082/5/2008PDONE
DetailsDave Hannah
Dave; If possible,could you stop by the job
between 1-2:45pm and look over a couple
details the arch. was needing OKed.If this
time frame is good today,we could get
together tomorrow. Thanks, Bob
Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Conference1/23/20081/23/20081/23/2008PDONE
DetailsJim Storey
Dave; I have a couple quick questions on
framing I need to run by you. Could
we meet at job trailer some time
today? Bob Phone #: ###-####
Internet Inspection Request from: bob austin
Architect to provide new wall details for approval.......or Call Dave
BLD-Conference12/28/20071/3/20081/3/2008ADONE
DetailsDave Hannah
Owner,Arch.,framer,myself would like to meet to
go over some possible question/problem areas with reguard to framing.If possible,10:30 at
420 Main St.,suite 202(Veltex Bldg.)Let me know
if this time is a problem. Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Foundation12/26/200712/27/200712/28/2007APART
DetailsDave Hannah
Wall rebar for L2.MTI will inspect.

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Foundation12/12/200712/12/200712/13/2007PPART
DetailsDave Hannah
Rebar for L1 walls. MTI will inspect.

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Foundation12/4/200712/4/200712/4/2007PPART
DetailsDave Hannah
Rebar for L1 walls; MTI will inspect also.

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Conference11/28/200711/29/200711/29/2007APASS
DetailsDave Hannah
Conference with subs on floor/wall
penetrations at 10:00 am. Have confirmed
with Dave Hannah.
Thanks, Bob fire protection

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Foundation11/19/200711/19/200711/19/2007PPART
DetailsJim Storey
P1 wall rebar-MTI will inspect. pending reports

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Foundation11/1/200711/1/200711/2/2007PPART
DetailsDave Hannah
Rebar for walls at P2 level.MTI will inspect.

Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Concrete10/25/200710/26/200710/26/2007PPASS
DetailsDave Hannah
This is for post-tensioned(PT)slab P1.All rebar
and tendons have been inspected by MTI.

Thanks Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Foundation10/12/200710/12/200710/12/2007PPART
DetailsDave Hannah
Level 2 wall rebar. My appologies;I failed to notify you of a floor pour on Oct.5th.I was out of town from Oct.3rd-8th.It was inspected by MTI and structural engineer from Seatle. Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Foundation8/31/20079/4/20079/4/2007APART
DetailsDave Hannah
Rebar for walls - special inspection will do also. Phone #: ###-#### Internet Inspection Request from: bob austin
BLD-Foundation8/14/20078/15/20078/15/2007APART
DetailsDave Hannah
Wall rebar Phone #: ###-#### Internet Inspection Request from: bob austin rebar ok crew still setting forms spec inspection will final befor pour
BLD-Footing8/2/20078/3/20078/3/2007APART
DetailsTony Young
Phone #: ###-#### Internet Inspection Request from: bob austin
pending S.I. report
BLD-Other7/24/20077/25/20077/25/2007PPART
DetailsDave Hannah
around 2 if possible please---Re-bar walls and 4 column footings only please--###-####spec inpection on site
BLD-Foundation7/12/20077/17/20077/17/2007APART
DetailsDave Hannah
Rebar please @ Gridline 1 & M & A- ###-#### Bob Austin spec inspection on site
BLD-Footing7/12/20077/17/20077/17/2007APART
DetailsDave Hannah
Footing @ area D & H around 10 if possible ###-#### Bob Austin spec inspection on site
BLD-Footing6/29/20077/3/20077/3/2007PPART
DetailsDave Hannah
Around 1:30 if possible please--###-#### Bob ok to pour first section of basement wall ftg