FIRE-Final Inspection | 7/13/2009 | 7/14/2009 | 7/14/2009 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
BLD-Final | 2/27/2009 | 2/27/2009 | 3/2/2009 | A | CANC |
Dave Hannah
|
|
|
|
BLD-Final | 2/26/2009 | 2/26/2009 | 2/26/2009 | A | PART |
Dave Hannah
|
|
|
Dave; We have all the signatures for this permit. Can we get the Temp.Oc. today?
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok for temp occ ok for perm occ after fire gos perm
|
FIRE-Final Inspection | 2/25/2009 | 2/26/2009 | 2/26/2009 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given until the project related fire alarm permit is finaled. Life safety items will be ok to pass at that time.
|
FIRE-Final Inspection | 2/23/2009 | 2/24/2009 | 2/25/2009 | A | FAIL |
Troy Cobbley
|
|
|
Life safety items are ok. Just waiting for the fire alarm resubmittals which were required due to changes/additional devices.
|
FIRE-Final Inspection | 2/24/2009 | 2/24/2009 | 2/24/2009 | A | DONE |
Scott Arellano
|
|
|
Emergency egress lighting and generator satisfactory.
|
BLD-Framing/Rough-in | 11/20/2008 | 11/21/2008 | 11/22/2008 | A | PART |
Dave Hannah
|
|
|
Dave; Could we get a re-inspect for the lower units( C3,4,5)? Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to cover lids c3,4,5 level 1 ok to cover drops level 6 ok to start insulating roof /ceiling level7
|
BLD-Framing/Rough-in | 10/10/2008 | 10/10/2008 | 10/13/2008 | A | PART |
Dave Hannah
|
|
|
Dave; Could you do a framing inspection for the trash room, generator room, pump room, and mechanical rooms on levels P1,2,3.
Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to cover
|
BLD-Framing/Rough-in | 8/20/2008 | 8/20/2008 | 8/21/2008 | A | PART |
Dave Hannah
|
|
|
Dave; I would like to cover one side of the Trash Room wall;metal studs in garage.Two of the walls are shaft liner,no rough-in in them. Other walls have rough-in,will do one side only. Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to cover this area
|
BLD-Framing/Rough-in | 8/20/2008 | 8/20/2008 | 8/21/2008 | P | CANC |
Dave Hannah
|
|
|
Dave; I would like to cover one side of the Trash Room wall;metal studs in garage.Two of the walls are shaft liner,no rough-in in them. Other walls have rough-in,will do one side only. Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin ok to cover this area
|
BLD-Concrete | 2/12/2008 | 2/13/2008 | 2/13/2008 | P | PART |
Dave Hannah
|
|
|
Rebar,tendon inspection for L3 PT slab. Phone #: ###-#### Internet Inspection Request from: bob austin
|
BLD-Conference | 2/8/2008 | 2/11/2008 | 2/12/2008 | P | PASS |
Dave Hannah
|
|
|
Dave; Have you had a chance to check on the framing detail where the 1hr floor meets the 2hr shaft. You were going to run it by George and/or Marlene, I think. Let me know. Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
|
BLD-Conference | 2/5/2008 | 2/5/2008 | 2/5/2008 | P | DONE |
Dave Hannah
|
|
|
Dave; If possible,could you stop by the job between 1-2:45pm and look over a couple details the arch. was needing OKed.If this time frame is good today,we could get together tomorrow. Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
|
BLD-Conference | 1/23/2008 | 1/23/2008 | 1/23/2008 | P | DONE |
Jim Storey
|
|
|
Dave; I have a couple quick questions on framing I need to run by you. Could we meet at job trailer some time today? Bob Phone #: ###-#### Internet Inspection Request from: bob austin Architect to provide new wall details for approval.......or Call Dave
|
BLD-Conference | 12/28/2007 | 1/3/2008 | 1/3/2008 | A | DONE |
Dave Hannah
|
|
|
Owner,Arch.,framer,myself would like to meet to go over some possible question/problem areas with reguard to framing.If possible,10:30 at 420 Main St.,suite 202(Veltex Bldg.)Let me know if this time is a problem. Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
|
BLD-Foundation | 12/26/2007 | 12/27/2007 | 12/28/2007 | A | PART |
Dave Hannah
|
|
|
Wall rebar for L2.MTI will inspect.
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
|
BLD-Foundation | 12/12/2007 | 12/12/2007 | 12/13/2007 | P | PART |
Dave Hannah
|
|
|
Rebar for L1 walls. MTI will inspect.
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
|
BLD-Foundation | 12/4/2007 | 12/4/2007 | 12/4/2007 | P | PART |
Dave Hannah
|
|
|
Rebar for L1 walls; MTI will inspect also.
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
|
BLD-Conference | 11/28/2007 | 11/29/2007 | 11/29/2007 | A | PASS |
Dave Hannah
|
|
|
Conference with subs on floor/wall penetrations at 10:00 am. Have confirmed with Dave Hannah. Thanks, Bob fire protection Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
|
BLD-Foundation | 11/19/2007 | 11/19/2007 | 11/19/2007 | P | PART |
Jim Storey
|
|
|
P1 wall rebar-MTI will inspect. pending reports
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
|
BLD-Foundation | 11/1/2007 | 11/1/2007 | 11/2/2007 | P | PART |
Dave Hannah
|
|
|
Rebar for walls at P2 level.MTI will inspect.
Thanks, Bob Phone #: ###-#### Internet Inspection Request from: bob austin
|
BLD-Concrete | 10/25/2007 | 10/26/2007 | 10/26/2007 | P | PASS |
Dave Hannah
|
|
|
This is for post-tensioned(PT)slab P1.All rebar and tendons have been inspected by MTI.
Thanks Phone #: ###-#### Internet Inspection Request from: bob austin
|
BLD-Foundation | 10/12/2007 | 10/12/2007 | 10/12/2007 | P | PART |
Dave Hannah
|
|
|
Level 2 wall rebar. My appologies;I failed to notify you of a floor pour on Oct.5th.I was out of town from Oct.3rd-8th.It was inspected by MTI and structural engineer from Seatle. Phone #: ###-#### Internet Inspection Request from: bob austin
|
BLD-Foundation | 8/31/2007 | 9/4/2007 | 9/4/2007 | A | PART |
Dave Hannah
|
|
|
Rebar for walls - special inspection will do also. Phone #: ###-#### Internet Inspection Request from: bob austin
|
BLD-Foundation | 8/14/2007 | 8/15/2007 | 8/15/2007 | A | PART |
Dave Hannah
|
|
|
Wall rebar Phone #: ###-#### Internet Inspection Request from: bob austin rebar ok crew still setting forms spec inspection will final befor pour
|
BLD-Footing | 8/2/2007 | 8/3/2007 | 8/3/2007 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: bob austin pending S.I. report
|
BLD-Other | 7/24/2007 | 7/25/2007 | 7/25/2007 | P | PART |
Dave Hannah
|
|
|
around 2 if possible please---Re-bar walls and 4 column footings only please--###-####spec inpection on site
|
BLD-Foundation | 7/12/2007 | 7/17/2007 | 7/17/2007 | A | PART |
Dave Hannah
|
|
|
Rebar please @ Gridline 1 & M & A- ###-#### Bob Austin spec inspection on site
|
BLD-Footing | 7/12/2007 | 7/17/2007 | 7/17/2007 | A | PART |
Dave Hannah
|
|
|
Footing @ area D & H around 10 if possible ###-#### Bob Austin spec inspection on site
|
BLD-Footing | 6/29/2007 | 7/3/2007 | 7/3/2007 | P | PART |
Dave Hannah
|
|
|
Around 1:30 if possible please--###-#### Bob ok to pour first section of basement wall ftg
|