BLD-Final | 1/2/2007 | 1/3/2007 | 1/3/2007 | A | PASS |
Dave Hannah
|
|
|
Jan; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt ok for perm occ
|
FIRE-Final Inspection | 9/28/2006 | 10/2/2006 | 10/2/2006 | A | PASS |
Forrest France
|
|
|
Fire life safety passed final inspection.
|
BLD-Final | 9/22/2006 | 9/25/2006 | 9/26/2006 | P | PART |
Dave Hannah
|
|
|
jan; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok for temp occ need to relock front door
|
FIRE-Final Inspection | 9/25/2006 | 9/25/2006 | 9/25/2006 | P | PART |
Forrest France
|
|
|
Fire life safety is satisfactory pending final of project related alarm permit including completion of smoke and heat detectors at the top of the elevator hoistway. Temporary occupancy has been granted for the second floor portion of this tenant.
|
FIRE-Final Inspection | 9/22/2006 | 9/25/2006 | 9/25/2006 | A | FAIL |
Forrest France
|
|
|
Project related fire alarm permit must be finaled prior to life safety final, need to relocate two and add one exit sign as discussed, need to install visual indicators at the main entry/exit door locks per review notes.
|
BLD-Final | 9/21/2006 | 9/22/2006 | 9/25/2006 | P | NR |
Dave Hannah
|
|
|
jan ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley needs other trades finaled
|
FIRE-Final Inspection | 9/21/2006 | 9/22/2006 | 9/22/2006 | P | NR |
Forrest France
|
|
|
Project related alarm permit must be finaled prior to BLD life safety final.
|
BLD-Framing/Rough-in | 9/14/2006 | 9/15/2006 | 9/15/2006 | A | PART |
Dave Hannah
|
|
|
jan -ceiling cover; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley ok to cover ceiling
|
FIRE-Final Inspection | 8/18/2006 | 8/21/2006 | 8/21/2006 | A | PART |
Forrest France
|
|
|
c/n items related to the 2nd floor life safety have been completed. No inspections for the 1st floor have been done at this time regarding alarm, sprinkler, or life safety.
|
BLD-Final | 8/17/2006 | 8/18/2006 | 8/18/2006 | A | PART |
Dave Hannah
|
|
|
Jan; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt ok to occ second floor after fire oks
|
FIRE-Final Inspection | 8/17/2006 | 8/18/2006 | 8/18/2006 | A | FAIL |
Forrest France
|
|
|
Provide addressing for the second floor, hardware at the boardroom must meet code requirements, 2nd floor only life safety inspection completed today.
|
BLD-Final | 8/16/2006 | 8/17/2006 | 8/17/2006 | P | CANC |
Dave Hannah
|
|
|
jan - temp occupancy insp; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
FIRE-Final Inspection | 8/17/2006 | 8/17/2006 | 8/17/2006 | P | NR |
Forrest France
|
|
|
Project is not ready for life safety inspection at this time, advised contractor of remaining issues.
|
BLD-Final | 8/14/2006 | 8/15/2006 | 8/15/2006 | P | NR |
Dave Hannah
|
|
|
jan; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Other | 8/15/2006 | 8/15/2006 | 8/15/2006 | P | PART |
Dave Hannah
|
|
|
jan; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ceiling grid ok drop in pannels after elec and fire r/is are completed
|
BLD-Concrete | 8/14/2006 | 8/15/2006 | 8/15/2006 | A | PART |
Dave Hannah
|
|
|
slab inspection; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt slab for mezz. ok to pour
|
BLD-Wall cover | 8/2/2006 | 8/3/2006 | 8/3/2006 | P | PART |
Dave Hannah
|
|
|
jan Note: if possible right after lunch or before ; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ground floor ext walls
|
BLD-Energy code compliance | 8/2/2006 | 8/3/2006 | 8/3/2006 | P | PART |
Dave Hannah
|
|
|
jan Note: if possible right after lunch or before ; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ground floor ext wall around columns ok to cover
|
BLD-Energy code compliance | 7/20/2006 | 7/21/2006 | 7/21/2006 | A | PART |
Dave Hannah
|
|
|
jan ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley needs to finish vapor barr
|
BLD-Energy code compliance | 7/19/2006 | 7/20/2006 | 7/20/2006 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/19/2006 at 3:49:22 PM. Contact: ###-####. needs a class a vis queen
|
BLD-Wall cover | 7/18/2006 | 7/19/2006 | 7/19/2006 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/18/2006 at 3:09:00 PM. Contact: ###-####. ok to insulate ext walls on second floor ok to cover perimeter walls on second floor
|
BLD-Foundation | 7/17/2006 | 7/18/2006 | 7/18/2006 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/17/2006 at 2:12:37 PM. Contact: ###-####.
|
BLD-Footing | 7/14/2006 | 7/17/2006 | 7/17/2006 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/14/2006 at 10:19:31 AM. Contact: ###-####. rebar not per plan
|