BLD-Final | 3/20/2007 | 3/20/2007 | 3/20/2007 | P | PASS |
Mike Jordan
|
|
|
Ok for perm occ. Issue on final aff. letter has been resolved.
|
Permanent Occupancy | | 3/20/2007 | 3/20/2007 | | DONE |
|
|
|
|
Code Occupancy Approval | 3/9/2007 | 3/9/2007 | 3/19/2007 | P | PASS |
Scott M.Brown
|
|
|
FINAL SIGNED AND BOND RELEASED
|
BLD-Final | 3/9/2007 | 3/12/2007 | 3/12/2007 | A | PEND |
Mike Jordan
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. Received final aff letter from special insp. agency. There is one issue that must be resolved prior to perm occ.
|
BLD-Final | 3/8/2007 | 3/8/2007 | 3/8/2007 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/8/2007 at 9:09:43 AM. Contact: ###-####. Needs to supply final aff. letter from special insp. agency prio to perm occ.
|
FIRE-Final Inspection | 3/5/2007 | 3/6/2007 | 3/6/2007 | A | PASS |
Troy Cobbley
|
|
|
LIfe safety passed.
|
BLD-Final | 1/18/2007 | 1/19/2007 | 1/19/2007 | P | PASS |
Mike Jordan
|
|
|
MIKE; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. ok for temp occ. Need final aff. letter from special insp. agency.
|
FIRE-Final Inspection | 1/18/2007 | 1/19/2007 | 1/19/2007 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given until the fire dept. access curb painting is complete. All other life safety items are ok.
|
Code Occupancy Approval Temp | | | 1/19/2007 | | PASS |
|
|
|
BOND HAS BEEN POSTED FOR $20,752 FOR INCOMPLETED ITEMS SO I SIGNED TEMP OCCUPANCY
|
FIRE-Final Inspection | 1/17/2007 | 1/18/2007 | 1/18/2007 | A | CANC |
Troy Cobbley
|
|
|
Per the contractor they are not ready for a final just yet
|
BLD-Final | 1/18/2007 | 1/18/2007 | 1/18/2007 | P | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/18/2007 at 7:04:41 AM. Contact: ###-####.
|
BLD-Other | 12/28/2006 | 12/29/2006 | 12/29/2006 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 12/28/2006 at 11:28:01 AM. Contact: ###-####.
|
BLD-Conference | 12/18/2006 | 12/19/2006 | 12/19/2006 | A | DONE |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 12/18/2006 at 1:05:07 PM. Contact: ###-####.
|
BLD-Wall cover | 11/17/2006 | 11/17/2006 | 11/17/2006 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 11/17/2006 at 7:37:30 AM. Contact: ###-####. interior walls ok to cover
|
BLD-Framing/Rough-in | 11/9/2006 | 11/13/2006 | 11/13/2006 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 11/9/2006 at 3:15:00 PM. Contact: ###-####. shearwall nailing. ok to cover.
|
BLD-Conference | 11/6/2006 | 11/7/2006 | 11/7/2006 | A | DONE |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 11/6/2006 at 1:46:50 PM. Contact: ###-####. Change in job super. Wanted to know what still needed to be inspected.
|
BLD-Framing/Rough-in | 10/16/2006 | 10/17/2006 | 10/17/2006 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/16/2006 at 10:37:15 AM. Contact: ###-####. Exterior steel stud framing, box headers and dragstruts.
|
BLD-Foundation | 8/16/2006 | 8/16/2006 | 8/16/2006 | P | PASS |
Jim Storey
|
|
|
steve ; Phone #: ###-#### Note: pouring concrete at 2:00 pm Internet Inspection Request from: Marsha Smylie
|
BLD-Footing | 8/11/2006 | 8/14/2006 | 8/14/2006 | A | PASS |
Jim Storey
|
|
|
steve; Phone #: ###-#### Internet Ins rebar ok si pending.pection Request from: Cathy Chiles
|