BLD-Final | 10/12/2007 | 10/12/2007 | 10/12/2007 | P | PASS |
Tom Arcoraci
|
|
|
rob Phone #: ###-####
|
FIRE-Final Inspection | 10/12/2007 | 10/12/2007 | 10/12/2007 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
BLD-Wall cover | 9/26/2007 | 9/27/2007 | 9/27/2007 | A | CANC |
Tom Arcoraci
|
|
|
call rob
|
BLD-Final | 9/21/2007 | 9/24/2007 | 9/24/2007 | A | PART |
Tom Arcoraci
|
|
|
rob Phone #: ###-####
|
BLD-Final | 9/21/2007 | 9/21/2007 | 9/21/2007 | P | PART |
Tom Arcoraci
|
|
|
ok for temp
|
FIRE-Final Inspection | | 9/21/2007 | 9/21/2007 | | PART |
|
|
|
Partial Fire final inspection; Approved for TOC; remaining items for Permanent CO are: 1) provide FD access roadway signs at the entrance of both FD roadways on the north side of the bldg (NW and NE corners); 2) post 4" or larger address numbers on the front of the building, or on the front (street) side of the Candlewood sign); 3) verify proper FA monitoring of the 120v shunt trip power monitoring, (to be done jointly by our fire alarm inspector and the State elevator inspector); 4) Provide sprinkler valve monitoring of the two anti-freeze sprinkler control valves (handles temporarily removed); 5) Provide permanent labels on the antifreeze system to indicate the type of antifreeze solution, quantity, and freeze point in accordance with NFPA (16.5). Upon completion of these items the Spk and FA permits can be finaled, whereupon the Bldg permit can be Passed by Fire.
|
Code Occupancy Approval Temp | 9/20/2007 | 9/20/2007 | 9/20/2007 | P | DONE |
Scott M.Brown
|
|
|
SMALL AREA IN REAR NEEDS GRASS BUT I WILLNOT MAKE THEM BOND. THEY HAD TO WORK WITH MERIDIAN NAMPA CANAL COMPANY SO REQUIRMENTS ARE THEIRS. OK FOR TEMP OCCUPANCY ONLY
|
FIRE-Final Inspection | 9/20/2007 | 9/20/2007 | 9/20/2007 | P | FAIL |
Troy Cobbley
|
|
|
Provide building address, provide fire dept access signage, repair the exit discharge light at the first floor north center exit, repair the third floor center exit light, provide emergency lighting in both of the stairwells as per plan, provide annual inspection tags for the fire extinguishers, final fire alarm permit and fire sprinkler permits.
|
BLD-Other | 8/24/2007 | 8/24/2007 | 8/24/2007 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Other | 8/17/2007 | 8/20/2007 | 8/20/2007 | A | PASS |
Tom Arcoraci
|
|
|
grid ok 3 2 floor
|
BLD-Conference | 8/13/2007 | 8/14/2007 | 8/14/2007 | A | PASS |
Jim Storey
|
|
|
rob - drywall -as soon as possible Phone #: ###-#### floor ceilling at storage rm 2 and 3 rd floors fire stopped and gyp ok to cover fur out.
|
BLD-Framing/Rough-in | 8/13/2007 | 8/13/2007 | 8/13/2007 | P | DEFR |
Jim Storey
|
|
|
rob - drywall -as soon as possible Phone #: ###-#### no one at site/ am rolled over.
|
BLD-Other | 8/3/2007 | 8/3/2007 | 8/3/2007 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 7/23/2007 | 7/24/2007 | 7/24/2007 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 7/18/2007 | 7/19/2007 | 7/19/2007 | A | FAIL |
Tom Arcoraci
|
|
|
rob - ###-#### needs to resubmit for elevator lobby change
|
BLD-Wall cover | 7/13/2007 | 7/13/2007 | 7/13/2007 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 6/11/2007 | 6/11/2007 | 6/11/2007 | P | PART |
Jim Storey
|
|
|
rob; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang first floor rms septration and ceilling only ok to hang
|
BLD-Conference | 6/7/2007 | 6/7/2007 | 6/7/2007 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Other | 6/7/2007 | 6/7/2007 | 6/7/2007 | A | PASS |
Tom Arcoraci
|
|
|
wip ok 1st floor
|
BLD-Framing/Rough-in | 5/30/2007 | 5/30/2007 | 5/30/2007 | P | PASS |
Tom Arcoraci
|
|
|
2nd floor
|
BLD-Framing/Rough-in | 5/29/2007 | 5/30/2007 | 5/30/2007 | A | CANC |
Tom Arcoraci
|
|
|
rob ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Conference | 5/24/2007 | 5/25/2007 | 5/25/2007 | P | PASS |
Tom Arcoraci
|
|
|
rob
|
BLD-Framing/Rough-in | 5/18/2007 | 5/18/2007 | 5/18/2007 | P | PASS |
Tom Arcoraci
|
|
|
rob; Phone #: ###-#### Internet Inspection Request from: Victoria Beall 2nd floor east side
|
BLD-Framing/Rough-in | 5/16/2007 | 5/18/2007 | 5/18/2007 | A | CANC |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 5/16/2007 | 5/16/2007 | 5/16/2007 | P | PART |
Tom Arcoraci
|
|
|
2nd floor only please--rob; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt ok to insulate walls east side
|
BLD-Framing/Rough-in | 5/9/2007 | 5/10/2007 | 5/10/2007 | A | PART |
Tom Arcoraci
|
|
|
rob; Phone #: ###-#### Internet Inspection Request from: Victoria Beall THRID FLOOR OK
|
BLD-Other | 5/4/2007 | 5/4/2007 | 5/4/2007 | P | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Conference | 5/3/2007 | 5/3/2007 | 5/3/2007 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Other | 4/25/2007 | 4/26/2007 | 4/26/2007 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 4/18/2007 | 4/20/2007 | 4/19/2007 | A | CANC |
Tom Arcoraci
|
|
|
rob or bruce at ###-#### ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Other | 4/5/2007 | 4/12/2007 | 4/12/2007 | P | PASS |
Tom Arcoraci
|
|
|
ok to rock cor lid per plan
|
BLD-Other | 4/3/2007 | 4/5/2007 | 4/5/2007 | P | PASS |
Tom Arcoraci
|
|
|
wip per plan
|
BLD-Conference | 3/30/2007 | 3/30/2007 | 3/30/2007 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 3/23/2007 | 3/23/2007 | 3/30/2007 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Other | 3/22/2007 | 3/23/2007 | 3/23/2007 | A | CANC |
Tom Arcoraci
|
|
|
|
BLD-Conference | 3/15/2007 | 3/21/2007 | 3/21/2007 | P | CANC |
Tom Arcoraci
|
|
|
see rob 3 pm
|
BLD-Conference | 3/21/2007 | 3/21/2007 | 3/21/2007 | P | PASS |
Tom Arcoraci
|
|
|
per plan
|
BLD-Wall cover | 3/9/2007 | 3/12/2007 | 3/12/2007 | A | PASS |
Tom Arcoraci
|
|
|
1st floor ext nail ok also
|
BLD-Other | 3/8/2007 | 3/8/2007 | 3/8/2007 | P | PASS |
Tom Arcoraci
|
|
|
meet with mike on resub issues
|
BLD-Other | 3/1/2007 | 3/2/2007 | 3/5/2007 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Other | 3/1/2007 | 3/1/2007 | 3/1/2007 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 3/1/2007 | 3/1/2007 | 3/1/2007 | A | PASS |
Tom Arcoraci
|
|
|
on plan changes
|