BLD-Final | 2/28/2007 | 2/28/2007 | 2/28/2007 | P | PASS |
Dave Hannah
|
|
|
Rob; Phone #: ###-#### Internet Inspection Request from: Victoria Beall ok for perm occ
|
BLD-Final | 2/27/2007 | 2/28/2007 | 2/28/2007 | A | CANC |
Dave Hannah
|
|
|
Rob; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
Permanent Occupancy | | 2/28/2007 | 2/28/2007 | | DONE |
|
|
|
|
FIRE-Final Inspection | 1/10/2007 | 1/11/2007 | 1/11/2007 | A | PASS |
Forrest France
|
|
|
Required corrections have been verified for completion, fire life safety final inspection passed.
|
BLD-Final | 1/4/2007 | 1/5/2007 | 1/8/2007 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/4/2007 at 10:29:00 AM. Contact: ###-####. ok for temp occ needs to fix ada shower and hl oles in floor
|
FIRE-Final Inspection | 1/4/2007 | 1/5/2007 | 1/5/2007 | A | PART |
Forrest France
|
|
|
Agreed in conjunction with the structural inspector to allow temporary occupancy pending the replacement of four light fixtures with defective emergency ballasts. Corrections are to be made and verified for completion early next week as discussed.
|
FIRE-Final Inspection | 1/4/2007 | 1/5/2007 | 1/5/2007 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/4/2007 at 10:28:20 AM. Contact: ###-####. wrong inspector
|
BLD-Framing/Rough-in | 12/22/2006 | 12/22/2006 | 12/22/2006 | P | PART |
Jim Storey
|
|
|
rich judy///ceiling grid inspection please; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt floor firestopping not done/ pvc plm in return air plenm/needs spreader bars.hole in stair encloser. ok to start but leave access for reinsp.
|
BLD-Framing/Rough-in | 11/29/2006 | 11/30/2006 | 11/30/2006 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/29/2006 at 5:57:22 PM. Contact: ###-####.ok to cover restroom plumbing wall
|
BLD-Framing/Rough-in | 11/28/2006 | 11/29/2006 | 11/29/2006 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/28/2006 at 3:50:35 PM. Contact: ###-####.ok to cover all but restroom plumbing wall
|
BLD-Energy code compliance | 11/15/2006 | 11/16/2006 | 11/16/2006 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/15/2006 at 4:47:01 PM. Contact: ###-####.
|
BLD-Energy code compliance | 11/14/2006 | 11/16/2006 | 11/15/2006 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/14/2006 at 4:15:51 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Nov 15 2006 4:51PM.
|
FIRE-Conference | 11/14/2006 | 11/15/2006 | 11/15/2006 | P | PASS |
Troy Cobbley
|
|
|
The contractor had a question about a pipe penatration through a rated wall
|
BLD-Framing/Rough-in | 11/14/2006 | 11/15/2006 | 11/15/2006 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/14/2006 at 4:13:44 PM. Contact: ###-####. ok to insulate ext walls
|
BLD-Conference | 6/27/2006 | 6/27/2006 | 6/28/2006 | P | DONE |
Forrest France
|
|
|
Phone conversation with contractor regarding duct smoke detection requirements for HVAC shutdown in a proposed common plenum.
|
BLD-Conference | 6/27/2006 | 6/27/2006 | 6/27/2006 | A | PASS |
Dixie Fellows
|
|
|
per dixie..referred richard kartchner to sam rogers regarding outside fresh air not being ducted to r/a on all units..they are using the ceiling as a plenum and the units will all have duct detectors in the r/a's.
|