Permit Information
Permit NumberBLD06-01860
StatusFinaled
Name LEVI STRAUSS AND COMPANY
Site Address 321 S 8TH ST
Project NameBODO BLDG #4
Customer Number 
ePlanReviewNo
Description
Contractor reg # RCE-10862 DEVCON CONSTRUCTION (LEVI STRAUSS & CO - BODO BLDG #4) This building is fire sprinklered for area increase. To construct a 2,635 square foot retail sales tenant space on the 1st story of "BoDo Building #4" (Northeast corner). Work is to include 2 restrooms accessible to the disabled, a fitting room accessible to the disabled, interior nonbearing walls, interior doors, millwork, and finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/31/200611/1/200611/1/2006APASS
DetailsDave Hannah
Phone #: ###-#### ok for perm occ
Permanent Occupancy 11/1/200611/1/2006 DONE
Details
BLD-Final10/24/200610/25/200610/26/2006PPART
DetailsDave Hannah
michael; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok for temp occ needs lav in mens restroom moved
FIRE-Final Inspection10/24/200610/25/200610/25/2006APASS
DetailsForrest France
Required corrections have been made, fire life safety finaled.
FIRE-Final Inspection10/23/200610/24/200610/24/2006AFAIL
DetailsTroy Cobbley
Provide suite number, exit discharge lighting at the front exit (rear exit is covered) and provide an indicator at the front exit.
BLD-Final10/19/200610/20/200610/20/2006PNR
DetailsDave Hannah
Dave I will be heading out of town around 2:00 PM. Please call Michael Jones with # above for inspection. Thanks Paul; Phone #: ###-####
FIRE-Final Inspection10/19/200610/20/200610/20/2006PFAIL
DetailsForrest France
The project related fire sprinkler permit must be finaled prior to life safety final, also missing PFE, project is not in a condition for final life safety inspection at this time.
BLD-Wall cover9/20/20069/21/20069/21/2006APASS
DetailsDave Hannah
Dave: I will need you to have look of vapor barrier and if things go ok with electrical / sprinkler inspections I'd like to cover ceilings. Thanks Paul
BLD-Wall cover9/13/20069/14/20069/15/2006PFAIL
DetailsDave Hannah
vapor barreir not class a
BLD-Framing/Rough-in9/12/20069/13/20069/13/2006APART
DetailsDave Hannah
see you tomorrow. ok to cover int walls