BLD-Final | 6/23/2008 | 6/23/2008 | 6/23/2008 | P | PASS |
Mike Jordan
|
|
|
Keith Phone #: ###-####
|
DOC - Permit Finaled | 6/23/2008 | 6/23/2008 | 6/23/2008 | P | PASS |
Mike Jordan
|
|
|
Letter of completion issued. Verified all other finals.
|
BLD-Conference | 6/23/2008 | 6/23/2008 | 6/23/2008 | A | PASS |
Mike Jordan
|
|
|
Will do final this afternoon.
|
FIRE-Final Inspection | 5/7/2008 | 5/7/2008 | 5/7/2008 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Conference | 4/10/2008 | 4/10/2008 | 4/10/2008 | P | PASS |
Mike Jordan
|
|
|
Called and spoke with Keith of T2 developement about bldg. C. All finals are complete and partial from life safety. Kieth Noted that knox boxes have been installed. Kieth noted that he would call in for life/safety final and bldg. final by end of this week or start of next week.
|
FIRE-Final Inspection | 11/16/2007 | 11/19/2007 | 11/19/2007 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with dave hannimans permission until the knox key box, which is on back order, is received and installed.
|
FIRE-Final Inspection | 11/15/2007 | 11/16/2007 | 11/16/2007 | A | CANC |
Troy Cobbley
|
|
|
The fire alarm testing was canceled by the fire alarm contractor
|
FIRE-Final Inspection | 11/9/2007 | 11/13/2007 | 11/13/2007 | A | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm and fire alarm permits finaled first. The emergency lights and exit signs tested ok.
|
FIRE-Conference | 11/8/2007 | 11/9/2007 | 11/9/2007 | A | CANC |
Troy Cobbley
|
|
|
To be rescheduled for tuesday since the fire alarm contractor could not make the 8:00am meeting time.
|
Code Occupancy Approval | 9/19/2007 | 9/19/2007 | 9/19/2007 | A | PASS |
Scott M.Brown
|
|
|
OK FOR FINAL
|
BLD-Energy code compliance | 7/11/2007 | 7/11/2007 | 7/11/2007 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 7/10/2007 | 7/11/2007 | 7/11/2007 | P | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/10/2007 at 6:11:19 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 7/10/2007 | 7/10/2007 | 7/10/2007 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/10/2007 at 8:16:10 AM. Contact: ###-####.
|
FIRE-Conference | 6/27/2007 | 6/28/2007 | 6/29/2007 | A | PASS |
Troy Cobbley
|
|
|
The outside front canopy has been filled with insulation.
|
BLD-Framing/Rough-in | 5/16/2007 | 5/17/2007 | 5/17/2007 | A | PASS |
Mike Jordan
|
|
|
KEITH; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. roof framing and diaphram only.
|
BLD-Footing | 5/8/2007 | 5/8/2007 | 5/8/2007 | P | PASS |
Mike Jordan
|
|
|
keith; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. Column pad footings for exterior canopy, south side.
|
BLD-Foundation | 3/12/2007 | 3/12/2007 | 3/12/2007 | P | PASS |
Mike Jordan
|
|
|
brian; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. loading dock wall.
|
BLD-Foundation | 3/7/2007 | 3/8/2007 | 3/8/2007 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/7/2007 at 8:30:33 PM. Contact: ###-####.
|
BLD-Footing | 3/5/2007 | 3/6/2007 | 3/6/2007 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/5/2007 at 3:24:05 PM. Contact: ###-####. Exterior and interior footings. Will recieve special insp.
|
BLD-Footing | 3/2/2007 | 3/5/2007 | 3/5/2007 | A | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/2/2007 at 10:56:56 AM. Contact: ###-####. Contractor to reschedule for tomorrow morning.
|