Permit Information
Permit NumberBLD06-02211
StatusFinaled
Name KEYSER DAVID SCOTT
Site Address 11560 W PRESIDENT DR
Project NameRAYCO OFFICE BUILDING
Customer Number 
ePlanReviewNo
Description
(K2 Construction RCE-1824) Rayco Office Building - To construct a new 5,150 square foot, one story, wood framed office building and related site improvements. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Code Occupancy Approval3/19/20073/19/20073/19/2007PPASS
DetailsScott M.Brown
OK FOR FINAL & RELEASE OF BOND.
Permanent Occupancy 3/19/20073/19/2007 DONE
Details
BLD-Final12/28/200612/29/200612/29/2006PPART
DetailsMike Jordan
Julio; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt. Temp occ given. Noted bond has been received. Will be ok for perm occ once others have finaled.
FIRE-Final Inspection12/28/200612/29/200612/29/2006APASS
DetailsTroy Cobbley
Life safety finaled
FIRE-Final Inspection12/27/200612/28/200612/28/2006AFAIL
DetailsTroy Cobbley
Lower and tag fire extinguishers. Provide correct sample tubes and remote annunciators for the duct smoke detectors.
BLD-Final12/27/200612/28/200612/28/2006PNR
DetailsMike Jordan
julo; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Needs life/safety and public works.
Code Occupancy Approval Temp  12/26/2006 FAIL
NEEDS TO BOND FOR $28,000, LANDSCAPE. BLACK TOP, PARKING LOT MARKING, STONE WORK ALL TO BE DONE FOR THIS BOND AMOUNT. WILL RECALL TURSDAY FOR TEMP AND PLACE BOND WITH CATHY.
BLD-Conference12/19/200612/21/200612/21/2006ADONE
DetailsMike Jordan
Julio; Phone #: ###-#### Internet Inspection Request from: Sherri Bennett
BLD-Conference12/18/200612/19/200612/19/2006ADONE
DetailsMike Jordan
Julio; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
BLD-Other12/7/200612/8/200612/8/2006APART
DetailsMike Jordan
julio - note: ceiling grid ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. Needs to repair some wires, exceed 1 in 8 as noted on approved plans. insp. pending other ri prior to cover.
BLD-Energy code compliance12/8/200612/8/200612/8/2006APASS
DetailsMike Jordan
julio - note: ceiling grid ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. Attic insul.
BLD-Framing/Rough-in12/8/200612/8/200612/8/2006APASS
DetailsMike Jordan
julio - note: ceiling grid ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
BLD-Wall cover11/6/200611/6/200611/6/2006PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 11/6/2006 at 10:26:52 AM. Contact: ###-####.
BLD-Framing/Rough-in10/20/200610/23/200610/23/2006APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 10/20/2006 at 1:44:29 PM. Contact: ###-####. Ok to cover soffitt. All hardware installed as per plan.
BLD-Framing/Rough-in10/11/200610/12/200610/12/2006APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 10/11/2006 at 2:01:40 PM. Contact: ###-####. Roof shear nailing, interior holdowns for panel system. Needs to have welds on strapping inspected by special insp.
BLD-Energy code compliance9/19/20069/19/20069/19/2006PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 9/19/2006 at 10:29:25 AM. Contact: ###-####.
BLD-Footing9/11/20069/12/20069/12/2006APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 9/11/2006 at 10:36:45 AM. Contact: ###-####. wip. perimeter footings. Project will have special insp. on conc. and vrebar.