Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD06-02401
StatusFinaled
Name CM COMPANY
Site Address 4719 S MARKET ST Unit: 102
Project NameAssociated Foods Warehouse
Customer Number 
ePlanReviewNo
Description
(P.O.D.S. - ASSOCIATED FOODS WAREHOUSE - NE CORNER TENANT SPACE 102) To create a 35,159 sq.ft. secure tenant space within an existing 250,000 sq ft building for storage of high pile steel storage containers of assorted household goods per approved plans. Work to include, erection of 18 ft high metal stud and gypboard partitions, construction of a new restroom, installation of new exterior 18' overhead door & two 3' x 6' 8" man doors to be installed on the east side of the building, relocate an existing interior modular office space too within this space, This building is fully fire sprinkled any alterations or modifications to the sprinkler system shall be per NFPA #13 as regulated by the fire department. Solid partitions are constructed to separate storage areas to less than 50,000 sq ft so heat & smoke vents are NOT Required. RMH **(PLAN MODIFICATION 1)**(3/8/07)** Plan modification to add a ramp and sand oil interceptor at new overhead door opening per approved plans and engineering.**(2ND PLAN MODIFICATION)**(4/13/07)** To expand an existing fire sprinkler pump room on the north side of building to install larger fire pump per approved plans and attached engineering. Work to include, construction of new CMU walls, concrete slab, and noncombustible roof deck. **(3RD PLAN MODIFICATION)** TO CONSTRUCT A 24' WIDE BY 810 FT LONG ACCESS ROAD TO THE EXISTING WAREHOUSE. ***(FOURTH PLAN MODIFICATION 3-14-07)*** TO CONSTRUCT NEW 134' X 20' ASPHALT FIRE ACCESS ROAD ON THE NORTH SIDE OF THE EXISTING WAREHOUSE TO PROVIDE ACCESS BY THE FIRE DEPARTMENT TO THE NEW PUMP ROOM. CONSTRUCT NEW DRAINAGE POND FOR STORM WATER RUN OFF. TO INSTALL TWO NEW FIRE HYDRANTS ALL PER FIRE DEPEPARTMENTS APPROVAL. RmH
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/12/20086/12/20086/12/2008PPASS
DetailsJim Storey
dan Phone #: ###-####
DOC - Permit Finaled6/12/20086/12/20086/12/2008PPASS
DetailsJim Storey
BLD-Aging Inspection5/8/20085/8/20085/8/2008 NR
DetailsJim Storey
sprinkler and access road isues pending/
BLD-Aging Inspection2/7/20082/7/20082/7/2008 PASS
DetailsJim Storey
fire lane to be resolved with sam rogers fir/ dan stuart plan review and cm co./ steed co. meetting to be on 2/7/08.
BLD-Aging Inspection12/4/200712/4/200712/6/2007 FAIL
DetailsJim Storey
no call to insp 3dr phase
BLD-Other5/7/20075/8/20075/8/2007PPASS
DetailsJim Storey
rob Note: steel rebar in the block; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Framing/Rough-in5/3/20075/3/20075/3/2007PPASS
DetailsJim Storey
Rob; Phone #: ###-#### Internet Inspection Request from: Andrea Whiteman
DOC - Permit Finaled5/3/20075/3/20075/3/2007PPASS
DetailsJim Storey
BLD-Footing4/23/20074/24/20074/24/2007APASS
DetailsJim Storey
rob - call 30 min prior ; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
BLD-Footing3/15/20073/15/20073/15/2007PPASS
DetailsJim Storey
Rob pls call 30min prior; Phone #: ###-#### Internet Inspection Request from: Stacie Backus
FIRE-Final Inspection3/8/20073/9/20073/12/2007PPART
DetailsForrest France
Items on correction notice issued at the previous inspection on 3/7 have been verified for compliance. Agreed to proceed with the terms of the agreements outlined at the on site meeting on 2/16 for temp. storage of the PODS.
FIRE-Final Inspection3/6/20073/7/20073/7/2007AFAIL
DetailsTroy Cobbley
Inspection was for a temporary for the placement of the POD's within the building. Inspection was done per the meeting minutes. Items that still need correcting are fire extinguishers need to be placed in all spaces, the items stored in the left hand of the "Y" intersection at the west end of the building need remove for fire dept. access, remove the concrete parking curbs from the access way to the east overhead door and remove the POD's that have already been stored in the building until all items have been satified.
BLD-Final3/6/20073/6/20073/6/2007PCANC
DetailsJim Storey
rob; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Framing/Rough-in2/20/20072/21/20072/21/2007APASS
DetailsJim Storey
rob; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
BLD-Framing/Rough-in2/20/20072/20/20072/20/2007PDEFR
DetailsJim Storey
rob; Phone #: ###-#### Internet Inspection Request from: Victoria Beall out of time defr to am.
FIRE-Conference2/8/20072/9/20072/12/2007ADONE
DetailsTroy Cobbley
Rob wanted to know if the owner could begin storing the containers in the building. After speaking to sam about the situation I informed him that the answer is no.
BLD-Foundation1/29/20071/30/20071/30/2007APASS
DetailsJim Storey
ROB PLEASE CALL 45 MIN BEFORE GOING OUT ; Phone #: ###-####; Phone #: ###-#### Internet Inspection Request from: Darla Downs
BLD-Foundation1/29/20071/29/20071/29/2007PCANC
DetailsJim Storey
ROB PLEASE CALL 45 MIN BEFORE GOING OUT ; Phone #: ###-#### Internet Inspection Request from: Darla Downs Rob called to cancel this inspection not ready///dld
BLD-Footing12/29/20061/2/20071/2/2007APASS
DetailsJim Storey
rob; Phone #: ###-#### Internet Inspection Request from: Sherri Bennett epoxy performed by mti rebar ok ft ok
BLD-Final5/29/20085/29/2008 P 
DetailsJim Storey
dan Phone #: ###-####