Code Occupancy Approval Temp | | | 3/31/2008 | | DONE |
|
|
|
Cathy received the bond today from Heathstone; it does cover the costs for the remaining landscaping which needs to be done.
|
BLD-Final | 3/20/2008 | 3/20/2008 | 3/20/2008 | P | PART |
Jim Storey
|
|
|
craig Phone #: ###-#### final ok pending p&z bond and plan review letter for unbuildabe lot to be on file.
|
FIRE-Final Inspection | 3/19/2008 | 3/20/2008 | 3/20/2008 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 3/18/2008 | 3/19/2008 | 3/19/2008 | P | FAIL |
Troy Cobbley
|
|
|
Life safety completed except for missing knox box's. Will call in permit for final when knox box is installed.KR
|
FIRE-Final Inspection | 3/17/2008 | 3/18/2008 | 3/18/2008 | P | FAIL |
Forrest France
|
|
|
Provide knox box, need to final fire sprinkler and alarm permits, need closures at doors, not all items reviewed at this time.
|
BLD-Final | 3/14/2008 | 3/17/2008 | 3/18/2008 | A | NR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 3/14/2008 at 2:32:42 PM. Contact: ###-####.
|
Code Occupancy Approval Temp | | | 3/18/2008 | | DONE |
|
|
|
Contractor has submitted a bid for the remaining bark work. Temp granted as all other conditions have been met. He anticipates work to be done within the next two weeks, so the bond can be released.
|
BLD-Aging Inspection | 2/18/2008 | 2/18/2008 | 2/20/2008 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Energy code compliance | 12/18/2007 | 12/19/2007 | 12/20/2007 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/18/2007 at 10:10:53 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 12/12/2007 | 12/14/2007 | 12/14/2007 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/12/2007 at 3:38:08 PM. Contact: ###-####.
|
BLD-Conference | 10/19/2007 | 10/22/2007 | 10/22/2007 | A | PASS |
Jim Storey
|
|
|
vern
|
BLD-Conference | 10/19/2007 | 10/19/2007 | 10/19/2007 | P | CANC |
Jim Storey
|
|
|
vern Phone #: ###-#### rolled am mon
|
BLD-Framing/Rough-in | 10/11/2007 | 10/12/2007 | 10/12/2007 | A | PASS |
Jim Storey
|
|
|
late am if possible please--fern Phone #: ###-#### 2nd floor wall gyp ok
|
BLD-Framing/Rough-in | 10/3/2007 | 10/4/2007 | 10/4/2007 | A | PASS |
Jim Storey
|
|
|
vern - around 11:00 if possible Phone #: ###-####gyp nailling ok
|
BLD-Framing/Rough-in | 10/3/2007 | 10/3/2007 | 10/3/2007 | P | PASS |
Jim Storey
|
|
|
vern - around 3:00 if possible Phone #: ###-#### gyp nailling ok
|
BLD-Conference | 10/2/2007 | 10/2/2007 | 10/2/2007 | P | PASS |
Jim Storey
|
|
|
vern Phone #: ###-####
|
BLD-Foundation | 9/11/2007 | 9/11/2007 | 9/11/2007 | P | PASS |
Tom Arcoraci
|
|
|
ben; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt
|
BLD-Footing | 9/5/2007 | 9/6/2007 | 9/6/2007 | A | FAIL |
Mike Jordan
|
|
|
Ben; Phone #: ###-#### Internet Inspection Request from: Hattie James. See detail 10 on sheet S2.02, verts need to be @ 10" oc. Needs to double check spacing on verts, many areas at front is 22"oc, needs toi be 18"oc. Check special insp. start up sheet, is required. c/n posted. Also left meesage with Ben.
|