Permit Information
Permit NumberBLD06-02655
StatusFinaled
Name FALASH & ROSS CONSTRUCTION
Site Address 1010 W JEFFERSON ST (BASEMENT)
Project Name1010 JEFFERSON LLC BLDG
Customer Number 
ePlanReviewNo
Description
(RCE-2502 FALASH & ROSS CONSTRUCTION) (BASEMENT REMODEL) The basement is fire sprinklered. To create a common reception/lobby area (718 square feet), hallway (646 square feet), conference room (560 square feet), and break room (295 square feet) within the 7,863 square foot basement of an existing 2 story with basement building. Fire sprinkler heads in the basement will be changed to quick-response sprinklers in conjunction with this project. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/28/20073/1/20073/1/2007PPASS
DetailsDave Hannah
greg; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
DOC - Permit Finaled3/1/20073/1/20073/1/2007PPASS
DetailsDave Hannah
FIRE-Final Inspection3/1/20073/1/20073/1/2007PPASS
DetailsForrest France
Duplicate entry, inspection passed.
FIRE-Final Inspection2/23/20072/26/20073/1/2007APASS
DetailsForrest France
Fire life safety passed inspection, noted two covers at SD to be removed after const. cleaning is finished and prior to occupancy, contractor also agreed to remove locking hasp at the door to the mech. room while on site.
BLD-Final2/23/20072/26/20072/26/2007APART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 2/23/2007 at 7:31:19 PM. Contact: ###-####.ok for perm occ after other trades go perm
BLD-Other1/18/20071/18/20071/19/2007PPASS
DetailsDave Hannah
This is for a ceiling inspection. Please contact Greg Bolton @ ###-####. Thank you Phone #: ###-####
BLD-Framing/Rough-in12/13/200612/14/200612/14/2006ADONE
DetailsDave Hannah
Please contact Greg Bolton prior to going out at ###-####. Thanks; Phone #: ###-#### Internet Inspection Request from: Jennifer Jenson
BLD-Framing/Rough-in12/14/200612/14/200612/14/2006PPASS
DetailsDave Hannah
Please contact Greg Bolton prior to going out at ###-####. Thanks; Phone #: ###-#### Internet Inspection Request from: Jennifer Jenson
BLD-Framing/Rough-in12/6/200612/7/200612/7/2006APART
DetailsJim Sly
Please contact Greg Bolton at ###-####, prior to going out. Thank You; Phone #: ###-#### Internet Inspection Request from: Jennifer Jenson
Walls not per appr plan........Resubmitted plan in plan check for approval.....Contr wants to 1side walls.....OK , but on his own..... do not proceed beyond this until plans appr, and frame insp completed.