BLD-Final | 7/20/2007 | 7/20/2007 | 7/20/2007 | P | PASS |
Dave Hannah
|
|
|
barak - please call 1/2 hr prior to inspection Phone #: ###-####
|
DOC - Permit Finaled | 7/20/2007 | 7/20/2007 | 7/20/2007 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 7/19/2007 | 7/20/2007 | 7/20/2007 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 7/5/2007 | 7/5/2007 | 7/5/2007 | P | FAIL |
Forrest France
|
|
|
Emergency light at the elevator lobby 5th floor failed to function, one fire door at the 3rd floor west side atrium pair failed to close on general alarm, exit sign at the 2nd floor east side does not illuminate on power fail.
|
FIRE-Sprinkler Rough-in | 7/5/2007 | 7/5/2007 | 7/5/2007 | P | PASS |
Forrest France
|
|
|
Required corrections for the corridor fire sprinklers on the 2nd, 3rd, 4th, and 5th levels completed satisfactory.
|
FIRE-Final Inspection | 5/23/2007 | 5/23/2007 | 5/23/2007 | P | FAIL |
Forrest France
|
|
|
Missing escutcheons at fire sprinkler heads at various locations in the corridors, some heads are in need of adjustment as the deflector is above or even with the ceiling tile, need to repair emergency lighting at several locations, missing a/v fire alarm notification for ADA room 516.
|
FIRE-Sprinkler Rough-in | 5/22/2007 | 5/23/2007 | 5/23/2007 | P | CANC |
Forrest France
|
|
|
barak ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Framing/Rough-in | 4/17/2007 | 4/18/2007 | 4/18/2007 | P | PASS |
Dave Hannah
|
|
|
gordon; Phone #: ###-#### Internet Inspection Request from: Victoria Beall ok to cover bathroom
|
BLD-Framing/Rough-in | 4/12/2007 | 4/13/2007 | 4/13/2007 | A | FAIL |
Dave Hannah
|
|
|
gordon ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith remove sheet rock from ceiling fire stop all pent in walls and floor criling
|
BLD-Other | 2/8/2007 | 2/8/2007 | 2/8/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/8/2007 at 7:26:06 AM. Contact: ###-####. 4th floor ceiling
|
BLD-Other | 1/17/2007 | 1/18/2007 | 1/18/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/15/2007 at 6:37:35 AM. Contact: ###-####.grid ok but need to patch up holes in corr wall
|
BLD-Other | 1/16/2007 | 1/17/2007 | 1/17/2007 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/15/2007 at 6:37:35 AM. Contact: ###-####.
|
BLD-Other | 1/15/2007 | 1/16/2007 | 1/16/2007 | A | DEFR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/15/2007 at 6:37:35 AM. Contact: ###-####.
|
BLD-Other | 12/1/2006 | 12/4/2006 | 12/4/2006 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/1/2006 at 10:48:05 AM. Contact: ###-####. third floor ceiling grid ok tocover after all other trades ok
|
BLD-Other | 11/20/2006 | 11/20/2006 | 11/20/2006 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/20/2006 at 9:07:29 AM. Contact: ###-####.second flr ceiling grid souyh half ok
|