Permit Information
Permit NumberBLD06-03160
StatusFinaled
Name MATERIAL TESTING & INSPECTION
Site Address 2791 S VICTORY VIEW WAY
Project NameC2 ENTERPRISES
Customer Number 
ePlanReviewNo
Description
NO CONTRACTOR REGISTRATION PROVIDED. (MATERIAL TESTING & INSPECTION - EXPANSION) To expand an existing 9,053 sq.ft. office into a vacant new shell 1,944 sq.ft. area and finish per approved plans. Fire sprinklers per Boise Fire.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/25/20083/26/20083/26/2008APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 3/25/2008 at 9:09:06 AM. Contact: ###-####. ok for perm occ.
FIRE-Conference2/12/20082/19/20082/21/2008PPASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection2/11/20082/12/20082/12/2008PFAIL
DetailsTroy Cobbley
A sprinkler head is installed in the storage room in an area where no ceiling is present. Per my conversation with Zane, I will follow up next week to see if the ceiling has been completed. If it is the fire life safety can be passed.
FIRE-Final Inspection2/8/20082/11/20082/11/2008AFAIL
DetailsTroy Cobbley
zane was not here and nobody else knew anything about the inspection. No inspection performed. - fire life safety Phone #: ###-####
FIRE-Final Inspection1/23/20081/23/20081/23/2008PFAIL
DetailsTroy Cobbley
Fire sprinkler protection has to be added in the storage room or the ceiling needs to be permanantly removed as discussed. Also no approved plan/notes were on site for review.
BLD-Wall cover11/14/200711/15/200711/15/2007PNR
DetailsMike Jordan
Scheduled by a contractor via Hello! on 11/14/2007 at 2:34:44 PM.
BLD-Aging Inspection2/27/20072/27/20072/27/2007 PASS
DetailsMike Jordan
wip. Needs to pull mech permit, get finals from elec. and fire.