BLD-Final | 4/25/2007 | 4/26/2007 | 4/26/2007 | A | PASS |
Mike Jordan
|
|
|
zach; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
DOC - Permit Finaled | 4/26/2007 | 4/26/2007 | 4/26/2007 | P | PASS |
Mike Jordan
|
|
|
|
Code Occupancy Approval | 4/25/2007 | 4/25/2007 | 4/25/2007 | P | PASS |
Scott M.Brown
|
|
|
all in as required final ok
|
Code Occupancy Approval | 4/24/2007 | 4/25/2007 | 4/25/2007 | P | CANC |
Wm. Michael Meloy
|
|
|
zach; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Reassigned to Scott Brown
|
FIRE-Final Inspection | 4/24/2007 | 4/24/2007 | 4/24/2007 | P | PASS |
Troy Cobbley
|
|
|
life safety passed.
|
BLD-Framing/Rough-in | 3/5/2007 | 3/6/2007 | 3/6/2007 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/5/2007 at 11:37:26 AM. Correct truss engineering on job site. Framing ok.
|
BLD-Framing/Rough-in | 3/2/2007 | 3/5/2007 | 3/5/2007 | A | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/2/2007 at 1:03:48 PM. Contact: ###-####. Incorrect Truss enginnering on job site. No insp. done. Contractor was notified.
|
BLD-Framing/Rough-in | 3/1/2007 | 3/2/2007 | 3/2/2007 | A | PART |
Mike Jordan
|
|
|
zac; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. ok to insul. Need truss engineering to complete framing inspection. Verified double layer 5/8 type x at soffit and can lights boxed out with double layer 5/8 typex. All penetrations were fire caulked.
|
BLD-Framing/Rough-in | 2/28/2007 | 3/1/2007 | 3/1/2007 | P | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/28/2007 at 2:05:47 PM. Contact: ###-####. Inspection cancelled from web by: Victoria Beall
|
BLD-Framing/Rough-in | 2/26/2007 | 2/27/2007 | 2/27/2007 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/26/2007 at 4:07:01 PM. Contact: ###-####. Shear nailing ok. ok to cover exterior walls.
|
BLD-Framing/Rough-in | 2/25/2007 | 2/26/2007 | 2/26/2007 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/25/2007 at 1:35:44 PM. Contact: ###-####. Roof sheating ok to cover. Engineer noted staples to be at 2" oc.
|
BLD-Framing/Rough-in | 2/22/2007 | 2/23/2007 | 2/23/2007 | P | PART |
Mike Jordan
|
|
|
zack - shear wall ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. wip. 95% complete. Contractor used 1/2" x 1 1/2 " 16 gauge nails for attachment rather than the 10d nails listed on approved plans. Contractor to get conversion from engineer and restaple if neccessay. Everything at 3 and 6, east wall at 2 and 6.
|
BLD-Other | 2/21/2007 | 2/22/2007 | 2/22/2007 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/21/2007 at 11:52:46 AM. Contact: ###-####. shear nail insp. not ready. wip. Contractor to reschedule for tommorrow.
|
BLD-Foundation | 1/30/2007 | 1/30/2007 | 1/30/2007 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/30/2007 at 10:05:21 AM. Contact: ###-####.
|
BLD-Footing | 1/29/2007 | 1/29/2007 | 1/29/2007 | P | PASS |
Mike Jordan
|
|
|
STEVE; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Footing | 1/25/2007 | 1/26/2007 | 1/26/2007 | P | NR |
Jim Storey
|
|
|
steve; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|