BLD-Final | 6/19/2008 | 6/19/2008 | 6/19/2008 | P | PASS |
Dave Hannah
|
|
|
cory - as early as possible please Phone #: ###-#### ok for c.c
|
BLD-Final | 6/17/2008 | 6/18/2008 | 6/19/2008 | P | NR |
Dave Hannah
|
|
|
cory Phone #: ###-####
|
DOC - Permit Finaled | | | 6/19/2008 | | DONE |
Barbara Stitt
|
|
|
Letter of compliance issued 6-19-08 see scanned documents
|
FIRE-Final Inspection | 6/11/2008 | 6/12/2008 | 6/12/2008 | A | PASS |
Forrest France
|
|
|
Correction notice items verified for compliance, shell life safety finaled.
|
FIRE-Final Inspection | 6/10/2008 | 6/11/2008 | 6/11/2008 | A | FAIL |
Forrest France
|
|
|
Provide approved hardware at the north exit doors (all three), post signage at the main entry/exit doors, provide missing building address numbers on a contrasting backround as discussed, also reviewed tenant permit life safety items including EM lighting, exit signs, duct detectors, fire extinguishers, etc.
|
FIRE-Final Inspection | 6/10/2008 | 6/10/2008 | 6/10/2008 | P | NR |
Forrest France
|
|
|
Discussed shell building requirements regarding fire life safety issues.
|
Code Occupancy Approval | 6/10/2008 | 6/10/2008 | 6/10/2008 | P | PASS |
Michael Garner
|
|
|
site inspection complete - I found that the complex has been completed according to approved plans/permits - PASS
|
BLD-Final | 6/9/2008 | 6/10/2008 | 6/10/2008 | A | FAIL |
Dave Hannah
|
|
|
Corey Phone #: ###-#### needs other trades to final
|
BLD-Energy code compliance | 6/9/2008 | 6/10/2008 | 6/10/2008 | A | PASS |
Dave Hannah
|
|
|
Corey Phone #: ###-####
|
BLD-Framing/Rough-in | 6/9/2008 | 6/10/2008 | 6/10/2008 | A | PASS |
Dave Hannah
|
|
|
Corey Phone #: ###-####
|
BLD-Framing/Rough-in | 5/21/2008 | 5/21/2008 | 5/22/2008 | P | PART |
Dave Hannah
|
|
|
Corey; Phone #: ###-####, as early p.m. as possible Internet Inspection Request from: Cathy Weisshaupt still needs letter from engineer on connections and shell
|
BLD-Conference | 5/19/2008 | 5/19/2008 | 5/19/2008 | P | PART |
Dave Hannah
|
|
|
cory - after 3:00 please Phone #: ###-#### plans on site ok to start ti but still have issues on shell and core
|
BLD-Framing/Rough-in | 5/6/2008 | 5/7/2008 | 5/7/2008 | A | FAIL |
Jim Storey
|
|
|
cory Phone #: ###-#### - after 10:00 please no aproved plan on site/ need si reports with engineering for changes as well as insp. of bolting.
|
BLD-Conference | 9/4/2007 | 9/4/2007 | 9/5/2007 | P | PASS |
Dave Hannah
|
|
|
Per our conversation this morning-plumbing inspector thinks they may be lacking some inspection???
|
BLD-Foundation | 5/22/2007 | 5/23/2007 | 5/23/2007 | A | PASS |
Dave Hannah
|
|
|
Brian ; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Footing | 5/22/2007 | 5/22/2007 | 5/22/2007 | P | PASS |
Dave Hannah
|
|
|
Brian ; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|