BLD-Final | 1/8/2008 | 1/8/2008 | 1/8/2008 | P | PASS |
Mike Jordan
|
|
|
All issues resolved. Final ok.
|
BLD-Final | 12/19/2007 | 12/20/2007 | 12/20/2007 | A | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 12/19/2007 at 10:01:03 AM. Contact: ###-####. Needs to provide 36x36 counters for checkout stands, nedds to be dispursed.
|
FIRE-Final Inspection | 12/19/2007 | 12/19/2007 | 12/19/2007 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
FIRE-Final Inspection | 12/4/2007 | 12/5/2007 | 12/5/2007 | A | FAIL |
Troy Cobbley
|
|
|
The duct smoke detectors have been installed on the supply side not the return side as required per the IMC. The testing has been stopped.
|
FIRE-Final Inspection | 11/19/2007 | 11/20/2007 | 11/20/2007 | A | FAIL |
Troy Cobbley
|
|
|
Still waiting to final the fire alarm permit then the life safety inspection can be started.
|
FIRE-Final Inspection | 11/16/2007 | 11/19/2007 | 11/19/2007 | A | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm permit finaled.
|
FIRE-Final Inspection | 11/15/2007 | 11/16/2007 | 11/16/2007 | A | FAIL |
Troy Cobbley
|
|
|
The project is not ready for a final yet but the ham hood is ok to use.
|
Code Occupancy Approval | 11/14/2007 | 11/14/2007 | 11/14/2007 | A | PASS |
Scott M.Brown
|
|
|
OK FOR FINAL
|
FIRE-Final Inspection | 11/12/2007 | 11/13/2007 | 11/13/2007 | A | FAIL |
Troy Cobbley
|
|
|
The project is not ready for a final inspection yet. The inspection for today was just for the installation and/or repair of the exit discharge lights. They now work.
|
FIRE-Final Inspection | 11/6/2007 | 11/7/2007 | 11/7/2007 | A | FAIL |
Troy Cobbley
|
|
|
The inspection today was to test the new and existing exit signs and emergency lights. Everything operated ok but exit discharge lights are missing from all of the exits. Exit discharge lights do not need to be added outside of the two exits in the Garden Area due to the interior lighting and two parking lot lights that are powered from the emergency generator that provide adequate lighting.
|
FIRE-Final Inspection | 10/31/2007 | 11/1/2007 | 11/2/2007 | A | FAIL |
Troy Cobbley
|
|
|
This was actually for a conference. I provided a correction notice siting specific code sections for life safety requirements. These code sections were written as follows: (1) Provide a racking permit as per IBC section 2208. Contact Dan Stuart at ###-####. (2) Provide Means of Egress Illumination as per IFC 1006.1 This includes the exit discharge. Emergency power shall be per IFC 1006.3. This is to be in the scope of work and in all paths of exit from the scope of work/remodeled areas. (3) Provide exit signs as per IFC 1011.1. Also see IFC 1011.53 for power source. This is to be in the scope of work and in all paths of exit from the scope of work/remodeled areas. (4) Provide door hardware that complies with IFC 1008.1.8.1 and 1008.1.8.3. (5) Access controlled egress doors, such as in Daycare, must comply with IFC 1008.1.3.4 or receive variance from Dan Stuart ###-####.
|
BLD-Framing/Rough-in | 10/17/2007 | 10/17/2007 | 10/17/2007 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/17/2007 at 9:04:04 AM. Contact: ###-####. ceiling grid ok.
|
FIRE-Conference | 10/17/2007 | 10/17/2007 | 10/17/2007 | P | DONE |
Troy Cobbley
|
|
|
I deferred a fire watch request to dave hanniman and answered general questions about a racking permit.
|
BLD-Wall cover | 10/16/2007 | 10/16/2007 | 10/16/2007 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/16/2007 at 7:27:51 AM. Contact: ###-####. ceiling grid ok, Main restrooms ok.
|
FIRE-Conference | 10/6/2007 | 10/8/2007 | 10/8/2007 | A | DONE |
Troy Cobbley
|
|
|
Conference was for the life safety requirements in the new garden area.
|
BLD-Conference | 10/8/2007 | 10/8/2007 | 10/8/2007 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/8/2007 at 9:50:45 AM. Contact: ###-####. ceiling grid in seafood area ok. pend. fire.
|
BLD-Other | 9/28/2007 | 9/28/2007 | 9/28/2007 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/28/2007 at 7:28:16 AM. Contact: ###-####. soffit at seafood area, ceiling grid, pend. sprinkler.
|
BLD-Other | 9/11/2007 | 9/11/2007 | 9/11/2007 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/11/2007 at 5:45:46 AM. Contact: ###-####. ceiling grid ok, pending fire.
|
FIRE-Final Inspection | 9/6/2007 | 9/7/2007 | 9/7/2007 | A | FAIL |
Troy Cobbley
|
|
|
This was an inspection for the egress corridor near the bakery. I need verification that this corridor has emergency lighting. I also noticed overspaced pendants in the bakery that need addressed prior to a final.
|
BLD-Other | 9/4/2007 | 9/4/2007 | 9/4/2007 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/4/2007 at 9:48:04 AM. Contact: ###-####. Ceiling grid in bakery ok.
|
BLD-Other | 8/31/2007 | 8/31/2007 | 8/31/2007 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/31/2007 at 7:37:14 AM. Contact: ###-####.
|
FIRE-Final Inspection | 8/27/2007 | 8/27/2007 | 8/27/2007 | P | PART |
Troy Cobbley
|
|
|
The remodeled pharmacy area is ok to occupy.
|
BLD-Final | 8/27/2007 | 8/27/2007 | 8/27/2007 | P | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/27/2007 at 8:54:03 AM. Contact: ###-####.
|
BLD-Other | 8/27/2007 | 8/27/2007 | 8/27/2007 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/27/2007 at 8:54:03 AM. Contact: ###-####. Pharmacy ok.
|
BLD-Final | 8/24/2007 | 8/24/2007 | 8/24/2007 | A | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/24/2007 at 6:51:21 AM. Contact: ###-####.
|
BLD-Other | 8/24/2007 | 8/24/2007 | 8/24/2007 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/24/2007 at 6:51:21 AM. Contact: ###-####. Ceiling grid insp. Received RFI # 16 from arcchitect changing grid requirements to 0-2 application.
|
BLD-Other | 8/20/2007 | 8/20/2007 | 8/20/2007 | P | FAIL |
Mike Jordan
|
|
|
Ceiling grid not installed as per plan. c/n issued.
|
FIRE-Final Inspection | 8/17/2007 | 8/17/2007 | 8/17/2007 | P | PART |
Troy Cobbley
|
|
|
This inspection was for the electronics area only. This area is ok to occupy.
|
FIRE-Conference | 8/15/2007 | 8/15/2007 | 8/15/2007 | P | DONE |
Troy Cobbley
|
|
|
This inspection was for the electronics area only. I found six missing sprinkler heads. See the city approved fire sprinkler plans for locations.
|
BLD-Final | 8/15/2007 | 8/15/2007 | 8/15/2007 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/15/2007 at 8:00:02 AM. Contact: ###-####. Not a blg. final. Looking to move in to new electronics area. Needs fire to final. Grid system installed not as per plan. Need RFI from architect prior to signing off grid system.
|
BLD-Conference | 8/15/2007 | 8/15/2007 | 8/15/2007 | P | CANC |
Mike Jordan
|
|
|
Nate; Phone #: ###-#### Internet Inspection Request from: Hattie James Inspection cancelled from web by: Hattie James
|
BLD-Other | 8/13/2007 | 8/14/2007 | 8/14/2007 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/13/2007 at 6:04:03 PM. Contact: ###-####. Received and reviewed paperwork for polycoolite that arrived on site. Paperwork from SGS testing labs indicates that this shipment carries a CC1 rating as required. Will have paperwork scanned in with permit. Allso noted that railing and stairs at docks has been added back in. Plans must be submitted to architect for approval then resubmitted to plan review for approval.
|
BLD-Energy code compliance | 8/13/2007 | 8/13/2007 | 8/13/2007 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/13/2007 at 6:46:25 AM. Contact: ###-####. insul at new pickup demissing wall.
|
BLD-Framing/Rough-in | 8/8/2007 | 8/8/2007 | 8/8/2007 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/8/2007 at 9:16:20 AM. Contact: ###-####. New demissing wall for merchandising/pickup room.
|
FIRE-Alarm Testing | 8/2/2007 | 8/3/2007 | 8/3/2007 | A | DONE |
Troy Cobbley
|
|
|
This inspection actually turned into a conference. I spoke to the superintendant and told him that for the two hood suppression systems all I need is the certification from the hood suppression contractor that states they are ok with the new appliances and setup. I also was shown what was going on in the rest or the store as far as sprinkler work. This work is in progress and has a early start go ahead.
|
BLD-Other | 8/2/2007 | 8/2/2007 | 8/2/2007 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/2/2007 at 10:33:11 AM. Contact: ###-####. Framing for new soffitt at deli area.
|
BLD-Footing | 7/31/2007 | 7/31/2007 | 7/31/2007 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/31/2007 at 8:56:25 AM. Contact: ###-####. wip for footing for new wall at exisiting garden center. Noted special insp. on site.
|
BLD-Footing | 7/27/2007 | 7/30/2007 | 7/30/2007 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 7/27/2007 at 12:27:28 PM. Contact: ###-####. pendig spec insp
|
BLD-Framing/Rough-in | 7/19/2007 | 7/19/2007 | 7/19/2007 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/19/2007 at 6:29:35 AM. Contact: ###-####. Inspected new soffit framing, and exisiting modified soffitts. Will need RFI from architect for framing changes on diamond soffitt in elec\tronics and for change in grid system. Also reviewed plan review report with contractor.
|
BLD-Conference | 6/28/2007 | 6/29/2007 | 6/29/2007 | A | DONE |
Mike Jordan
|
|
|
craig Phone #: ###-####
|