Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD07-00954
StatusFinaled
Name MCALVAIN CONSTRUCTION INC
Site Address 575 S 13TH ST
Project NameBOISE RESCUE MISSION
Customer Number 
ePlanReviewNo
Description
Boise Rescue Mission River of Life - (Addition and Remodel) - Phase 1 - To demolish and remove existing interior partitions, doors and kitchen equipment to delete the existing kitchen, walls separating the small and large dining areas. To remodel these areas to create one large (1740 sq. ft.) dining room. To construct a 1,300 square foot, one story, kitchen addition on the northeast corner of the existing building. The addition is constructed of concrete foundation and slab floor, masonry exterior walls and metal roof joist framing with metal roof deck and single ply membrane roofing system. Phase 2 - To convert the existing Day Shelter into additional showers and restroom. To remove two existing exterior windows and install two new egress doors at the north and west exterior walls of large first floor west men's dormitory room. This permit also includes related site improvements. All construction per the approved plans and attached comment list. This building is being reviewed as nonseparated uses, with the A-2 Occupancy being most restrictive. The sprinkler system is used for story increase.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection10/21/200810/21/200810/21/2008PNR
DetailsForrest France
Pending request for fire alarm permit doc final.
BLD-Final10/17/200810/20/200810/20/2008PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 10/17/2008 at 2:16:00 PM. Contact: ###-####. ok for perm occ
BLD-Final10/16/200810/17/200810/20/2008PPASS
DetailsDave Hannah
Scheduled via mobile device. Phone #: 8711566
FIRE-Final Inspection10/16/200810/17/200810/17/2008APART
DetailsForrest France
Fire life safety completed acceptable, however project cannot be finaled until related fire alarm permit # FIR07-00807 is finaled.
BLD-Conference10/10/200810/10/200810/13/2008PPART
DetailsDave Hannah
John Phone #: ###-#### needs city approved plans and fire life saftey final
BLD-Final11/16/200711/16/200711/16/2007APART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 11/13/2007 at 10:14:58 AM. Contact: ###-####. ok for temp occ one ph one need to complete ph two
FIRE-Final Inspection11/13/200711/16/200711/16/2007APART
DetailsForrest France
Corrections noted for phase one of the project per K. Roule have been completed, fire life safety is acceptable for the portion of permit work as indicated.
BLD-Final11/13/200711/15/200711/16/2007PNR
DetailsDave Hannah
Scheduled by a contractor via Hello! on 11/13/2007 at 10:14:58 AM. Contact: ###-####.
FIRE-Final Inspection11/13/200711/14/200711/14/2007ANR
DetailsForrest France
Need project related fire sprinkler and hood suppression system permits finaled prior to request for a life safety inspection.
BLD-Framing/Rough-in11/9/200711/13/200711/13/2007APART
DetailsDave Hannah
john - ceiling Phone #: ###-#### ok to cover ceiling
BLD-Wall cover10/31/200711/1/200711/1/2007APART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 10/31/2007 at 1:53:55 PM. Contact: ###-####. ceiling grid ok to cover dinning room area
Code Occupancy Approval10/25/200710/25/200710/25/2007PCANC
DetailsMichael Garner
site inspection complete - addition and landscaping completed according to approved plans and DRH conditions - PASS
BLD-Footing6/21/20076/22/20076/25/2007PPASS
DetailsDave Hannah
jose; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang
BLD-Conference6/12/20076/12/20076/13/2007PPASS
DetailsDave Hannah
jose ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith