BLD-Final | 11/15/2007 | 11/16/2007 | 11/16/2007 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/15/2007 at 8:05:12 AM. Contact: ###-####.
|
BLD-Final | 11/7/2007 | 11/9/2007 | 11/9/2007 | A | PART |
Jim Storey
|
|
|
howard Phone #: ###-#### need ada 7-9 tolitet papper/ saftey glazing doors.
|
Code Occupancy Approval | 11/9/2007 | 11/9/2007 | 11/9/2007 | P | PASS |
Scott M.Brown
|
|
|
OK FOR FINAL
|
Code Occupancy Approval | 11/9/2007 | 11/9/2007 | 11/9/2007 | P | CANC |
Scott M.Brown
|
|
|
OK FOR FINAL
|
FIRE-Final Inspection | 11/5/2007 | 11/7/2007 | 11/7/2007 | A | PASS |
Forrest France
|
|
|
Access gates approved per FD, door hardware at the main entry/exit installed while on site, life safety inspection completed acceptable per site visit by K. Roule.
|
FIRE-Conference | 10/30/2007 | 10/31/2007 | 10/31/2007 | A | DONE |
Troy Cobbley
|
|
|
I went over life safety requirements with the builder. He stated that he was going to install two vehicle gates. One on the south side of the building and the other on the north. I told him he needs fire dept approval for this. I told him about none hardened locks and the opticom systems.
|
BLD-Other | 10/30/2007 | 10/31/2007 | 10/31/2007 | A | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/30/2007 at 2:46:02 PM. Contact: ###-####.
|
BLD-Other | 10/29/2007 | 10/30/2007 | 10/30/2007 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/29/2007 at 11:48:04 AM. Contact: ###-####.ceilling ok pending others/ need 4 wall clips/fire stopping.
|
BLD-Wall cover | 10/22/2007 | 10/23/2007 | 10/23/2007 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/22/2007 at 12:39:43 PM. Contact: ###-####. c/n idems ok
|
BLD-Wall cover | 10/18/2007 | 10/18/2007 | 10/18/2007 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/18/2007 at 10:55:18 AM. Contact: ###-####. relocate heater box to exterior wall or reinspect for wall gyp protection/ top of first floor needs fire safing gyp atchment ok can verify at ceilling grid insp/ gas piping pending mech.
|
BLD-Framing/Rough-in | 10/16/2007 | 10/17/2007 | 10/17/2007 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/12/2007 at 2:52:59 PM. Contact: ###-####.engineering and ec report archived.
|
BLD-Framing/Rough-in | 10/15/2007 | 10/16/2007 | 10/16/2007 | P | DEFR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/12/2007 at 2:52:59 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 10/12/2007 | 10/15/2007 | 10/15/2007 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/12/2007 at 2:52:59 PM. Contact: ###-####.
|
BLD-Concrete | 10/4/2007 | 10/5/2007 | 10/8/2007 | P | PART |
Jim Storey
|
|
|
howard rebar - 2nd floor Phone #: ###-#### need engineering for floor change. si on site
|
BLD-Foundation | 8/29/2007 | 8/30/2007 | 8/30/2007 | P | PASS |
Jim Storey
|
|
|
rebar; Ben; Phone #: ###-#### Internet Inspection Request from: Hattie James
|
BLD-Footing | 8/6/2007 | 8/7/2007 | 8/7/2007 | P | PASS |
Jim Storey
|
|
|
ben Phone #: ###-####
|