BLD-Final | 2/6/2008 | 2/7/2008 | 2/7/2008 | P | PASS |
Tony Young
|
|
|
phillip Phone #: ###-#### SWDH called and said full sign off was OK,, ok for perm occ.., also no storage structure is presently on property
|
BLD-Conference | 1/25/2008 | 1/25/2008 | 1/25/2008 | P | PART |
Tony Young
|
|
|
philip Phone #: ###-#### conf on final,, need full ok from health dept,, keep exits clear,, re-call for final when ready,, non permited storage addition has been removed
|
BLD-Final | 8/31/2007 | 9/4/2007 | 9/4/2007 | A | FAIL |
Tony Young
|
|
|
Phillip; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt c/n posted,, ok for temp occ.,, juice bar not ready yet
|
FIRE-Final Inspection | 8/31/2007 | 8/31/2007 | 8/31/2007 | P | PASS |
Forrest France
|
|
|
Fire life safety final inspection passed.
|
FIRE-Final Inspection | 8/22/2007 | 8/23/2007 | 8/23/2007 | A | FAIL |
Troy Cobbley
|
|
|
Need to provide remote annunciator as per the IMC. Shutdown did test ok and the enclosure has been provided. All other items are ok.
|
Code Occupancy Approval | 8/22/2007 | 8/22/2007 | 8/22/2007 | P | PASS |
Michael Garner
|
|
|
site inspection complete - work completed according to approved plans/permits - PASS
|
FIRE-Final Inspection | 8/21/2007 | 8/21/2007 | 8/21/2007 | P | FAIL |
Forrest France
|
|
|
Locking hardware at the door to the shared restroom is not allowed-see approved plan annotations, need to relocate exit sign or provide passage only hardware at this location, need to provide means for testing the duct detector.
|
FIRE-Final Inspection | 8/17/2007 | 8/17/2007 | 8/17/2007 | P | FAIL |
Forrest France
|
|
|
RTU 1 exceeds 2000 cfm per plans, need to install duct smoke detection as required per mechanical code and fire code review notes.
|
BLD-Final | 8/13/2007 | 8/15/2007 | 8/15/2007 | P | CANC |
Tony Young
|
|
|
phill Phone #: ###-####
|
BLD-Conference | 8/10/2007 | 8/13/2007 | 8/13/2007 | A | PART |
Tony Young
|
|
|
phillip Phone #: ###-#### conf on final
|
FIRE-Final Inspection | 8/10/2007 | 8/13/2007 | 8/13/2007 | A | FAIL |
Forrest France
|
|
|
Need to post building address numbers, provide one additional PFE for the mezzanine office area, door hardware is not yet installed at several locations for verification of code compliance, post signage above the main entry/exit door and provide visual indicator, need to test EM lighting and exit signs at next visit.
|
BLD-Final | 8/9/2007 | 8/13/2007 | 8/13/2007 | P | CANC |
Tony Young
|
|
|
Philip ; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
BLD-Framing/Rough-in | 7/16/2007 | 7/16/2007 | 7/16/2007 | P | PASS |
Tony Young
|
|
|
phillip Phone #: ###-####
|
BLD-Framing/Rough-in | 7/12/2007 | 7/13/2007 | 7/13/2007 | P | PASS |
Dave Hannah
|
|
|
PHILLIP Phone #: ###-####
|
BLD-Conference | 6/29/2007 | 7/2/2007 | 7/2/2007 | A | CANC |
Tony Young
|
|
|
phillip; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang same as last week
|
BLD-Conference | 6/29/2007 | 6/29/2007 | 6/29/2007 | P | PART |
Tony Young
|
|
|
Phil,, frame ?s; Phone #: ###-#### general conf,, ok to infill opening w/ masonary in yoga room,, non rated
|
BLD-Conference | 6/28/2007 | 6/29/2007 | 6/29/2007 | A | DEFR |
Tony Young
|
|
|
phillip - framing Phone #: ###-#### re-sched for pm
|
BLD-Framing/Rough-in | 6/27/2007 | 6/28/2007 | 6/28/2007 | A | PART |
Tony Young
|
|
|
phillip Phone #: ###-#### ph conf only phil from Emmett,, need trades 1st
|