BLD-Aging Inspection | 9/23/2009 | 9/23/2009 | 9/24/2009 | | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 9/24/2009 | 9/24/2009 | 9/24/2009 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 8/4/2008 | 8/4/2008 | 8/4/2008 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/4/2008 at 7:46:06 AM. Contact: ###-####.
|
BLD-Final | 7/17/2008 | 7/18/2008 | 7/18/2008 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/17/2008 at 4:06:57 PM. Contact: ###-####. needs to rock under stairs and add one hr door fix ada restroom get other trades to final
|
FIRE-Final Inspection | 7/16/2008 | 7/17/2008 | 7/17/2008 | P | PASS |
Forrest France
|
|
|
Shell fire life safety inspection completed acceptable.
|
Code Occupancy Approval | 7/15/2008 | 7/15/2008 | 7/15/2008 | P | PASS |
Michael Garner
|
|
|
site inspection complete - I found that all work has been completed according to approved plans and permits - PASS
|
FIRE-Alarm Testing | 7/14/2008 | 7/15/2008 | 7/15/2008 | A | CANC |
Forrest France
|
|
|
Duplicate inspection request-"alarm testing" is covered under project related FIR permits.
|
BLD-Other | 6/25/2008 | 6/26/2008 | 6/27/2008 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/25/2008 at 4:59:07 PM. Contact: ###-####.ceiling grid ok to cover halls
|
BLD-Conference | 6/17/2008 | 6/17/2008 | 6/17/2008 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/17/2008 at 7:29:34 AM. Contact: ###-####. fire caulk top of wall conf rm ok to cover
|
BLD-Conference | 6/2/2008 | 6/2/2008 | 6/2/2008 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/2/2008 at 7:55:08 AM. Contact: ###-####. ok to elev mec room lid
|
BLD-Conference | 5/29/2008 | 5/29/2008 | 5/29/2008 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/29/2008 at 6:15:13 AM. Contact: ###-####. doorways into conf room along 2hr wall ok to cover lids
|
BLD-Framing/Rough-in | 5/9/2008 | 5/12/2008 | 5/12/2008 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/9/2008 at 5:05:33 PM. Contact: ###-####.restroom and hall walls ok to cover
|
BLD-Framing/Rough-in | 5/8/2008 | 5/8/2008 | 5/9/2008 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/8/2008 at 8:22:39 AM. Contact: ###-####. ext framing ok to cover ext
|
BLD-Conference | 4/17/2008 | 4/17/2008 | 4/17/2008 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/17/2008 at 9:25:01 AM. Contact: ###-####.
|
BLD-Foundation | 2/7/2008 | 2/8/2008 | 2/8/2008 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 2/7/2008 at 4:50:43 PM. Contact: ###-####.
|
BLD-Footing | 2/1/2008 | 2/4/2008 | 2/4/2008 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/1/2008 at 2:21:42 PM. Contact: ###-####. east side
|
BLD-Concrete | 1/11/2008 | 1/14/2008 | 1/14/2008 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/11/2008 at 1:52:09 PM. Contact: ###-####. Conc. tilt panels, wip. Will receive special insp.
|
BLD-Concrete | 1/10/2008 | 1/11/2008 | 1/11/2008 | P | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 1/10/2008 at 1:57:18 PM. Contact: ###-####.
|
BLD-Concrete | 11/30/2007 | 12/3/2007 | 12/3/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/30/2007 at 10:35:27 AM. Contact: ###-####. they will pour four pannels tomorrow mti will inspect rebar and test concrete
|
BLD-Footing | 10/5/2007 | 10/8/2007 | 10/8/2007 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/5/2007 at 3:32:15 PM. Contact: ###-####.
|
BLD-Footing | 9/28/2007 | 9/28/2007 | 9/28/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 9/28/2007 at 7:04:11 AM. Contact: ###-####.ftgs along south and east side
|
BLD-Footing | 9/25/2007 | 9/26/2007 | 9/26/2007 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 9/25/2007 at 10:20:51 AM. Contact: ###-####. column ftgs
|