Permit Information
Permit NumberBLD07-01654
StatusFinaled
Name CM COMPANY
Site Address 2604 W STATE ST
Project NameST MARY'S CATHOLIC CHURCH ADD.
Customer Number 
ePlanReviewNo
Description
St. Mary's Catholic Church Addition and Remodel - To remodel an existing 4,250 square foot, existing church building and construct a 9,750 square foot church addition on the west end of the existing church building. The addition will have a large nave, a narthex, cry room, sacristy, equipment rooms and two restrooms. The new addition is constructed of masonry and steel stud exterior walls and steel structural frame roof system. The existing church is constructed of masonry exterior walls and wood framing. This permit also includes related site improvements. This building is fully fire sprinkled. The sprinklers are used for area increase. 3/9/09 - Plans modified to include a courtyard garden with masonry screen walls, some wrought iron fence, additional hardscape and landscaping. This courtyard is being constructed on the south side of the church. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/15/20096/16/20096/16/2009APASS
DetailsDave Hannah
jim Phone #: ###-#### ok for perm occ
BLD-Final6/15/20096/15/20096/16/2009PNR
DetailsDave Hannah
jim Phone #: ###-####
FIRE-Final Inspection3/5/20093/9/20093/9/2009APASS
DetailsForrest France
Final fire life safety walkthrough passed.
FIRE-Conference3/5/20093/5/20093/5/2009ADONE
DetailsForrest France
Regarding project related FIR permits and final fire life safety inspection.
BLD-Final3/3/20093/5/20093/5/2009APART
DetailsDave Hannah
jim Phone #: ###-#### ok for temp occ after fire life safty final needs to finish landscaping
BLD-Framing/Rough-in10/8/200810/8/200810/9/2008PPART
DetailsDave Hannah
Jim Phone #: ###-#### ok to cover east half after other trades finish r/is
BLD-Conference6/16/20086/16/20086/16/2008ADONE
DetailsForrest France
Jim Phone #: ###-####
BLD-Final6/4/20086/5/20086/5/2008APART
DetailsDave Hannah
jim - final on phase 1 only Phone #: ###-#### ok to use new nrw area
FIRE-Final Inspection6/3/20086/4/20086/4/2008APART
DetailsForrest France
Preliminary walkthrough of building life safety completed to date for the new addition including the vestibule, narthex, nave, and restrooms, verified EM lighting is functional, fire alarm and sprinkler work for these areas is also complete.
FIRE-Final Inspection6/3/20086/3/20086/4/2008PDEFR
DetailsForrest France
Duplicate inspection request.
FIRE-Final Inspection6/2/20086/2/20086/2/2008PFAIL
DetailsForrest France
Emergency egress lights at all exits to a public way did not function. Can not grant a temporary occupancy until egress lights are working.KR
BLD-Conference5/30/20085/30/20085/30/2008PPASS
DetailsDave Hannah
JIm; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
FIRE-Final Inspection5/30/20085/30/20085/30/2008PCANC
DetailsForrest France
JIm; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt Overbooked
Code Occupancy Approval Temp  5/29/2008 DONE
DetailsWm. Michael Meloy
Temporary occupancy is approved for portion of newly constructed building. Items from church will be moved into this protion. The church will be partially demolsihed and then both building will be joined.
BLD-Other5/15/20085/15/20085/15/2008PPASS
DetailsDave Hannah
rob note: ceiling Phone #: ###-#### ok to cover
BLD-Conference4/30/20084/30/20084/30/2008PPASS
DetailsDave Hannah
jim Phone #: ###-####
FIRE-Conference4/16/20084/17/20084/17/2008ADONE
DetailsForrest France
On site visit regarding fire alarm notification appliances at two locations including the narthex and the storage room areas.
BLD-Framing/Rough-in3/18/20083/18/20083/18/2008PPART
DetailsDave Hannah
jim Phone #: ###-#### dropped hard lids in restrooms and hall ok to cover
BLD-Framing/Rough-in2/26/20082/26/20082/26/2008PPART
DetailsDave Hannah
JIM Phone #: ###-#### ok to cover walls and ceilings
FIRE-Conference2/26/20082/26/20082/26/2008PDONE
DetailsForrest France
On site conference to discuss project phasing affecting fire alarm permit work.
BLD-Framing/Rough-in1/4/20081/4/20081/5/2008PPART
DetailsDave Hannah
jim Phone #: ###-####
BLD-Concrete12/20/200712/20/200712/20/2007PPART
DetailsDave Hannah
jim Phone #: ###-#### grout pour for cmu second 4ft lift mti will be on site for spec inspection
BLD-Concrete12/19/200712/19/200712/20/2007PPART
DetailsDave Hannah
jim Phone #: ###-#### grouting cmu first 4ft lift mti on site for spec insp.
BLD-Concrete12/18/200712/18/200712/19/2007PCANC
DetailsDave Hannah
jim Phone #: ###-####
BLD-Other12/17/200712/17/200712/18/2007PPART
DetailsDave Hannah
JimNote: cmu Phone #: ###-####
BLD-Conference12/17/200712/17/200712/18/2007PPASS
DetailsDave Hannah
JimNote: cmu Phone #: ###-####
BLD-Footing10/2/200710/2/200710/3/2007PPART
DetailsDave Hannah
rob Phone #: ###-#### mti on site crew still working on rebar
BLD-Footing9/21/20079/21/20079/24/2007PPART
DetailsDave Hannah
jim or rob - re-bar - pour at 3:00 Phone #: ###-#### ok to pour ftgs around stairway out of basement ext bldg