Permit Information
Permit NumberBLD07-01932
StatusFinaled
Name THE RUSSELL CORPORATION
Site Address 700 S CLEARWATER LN
Project NameCLEARWATER BLDG
Customer Number 
ePlanReviewNo
Description
(IDAHO INDUSTRIAL COMMISSION - CLEARWATER BLDG) This building IS NOT sprinklered. To remodel the entire 29,125 sq.ft. two story office building for a new office tenant per approved plans. No exterior changes under this permit. Work includes select interior demolition; new non-bearing walls to create offices, support and access / egress paths on both floors; Construct and/or repair a 1-hour fire-rated, tunneled exit corridor system to create / complete a rated exit corridor on both levels; to upgrade interior finishes, ceiling systems, millwork, electrical, mechanical, plumbing and alarm systems to meet tenant needs and to comply with current adopted codes and ordinances. drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/5/20088/5/20088/5/2008PPASS
DetailsDave Hannah
Please verify ok for perm occupancy and let Barb know ok for perm occ
FIRE-Final Inspection7/16/20087/16/20087/16/2008PPASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection6/27/20086/30/20086/30/2008APART
DetailsForrest France
Okay for temporary occupancy with D. Hanneman's permission pending completion of the elevator controls. NOTE: elevator power to be turned off and no use is allowed until work is completed and tested per Temporary Occ. conditions and agreement.
BLD-Final6/26/20086/27/20086/27/2008PPART
DetailsJim Storey
nick Phone #: ###-#### temp occ ok pending aproval of fir dept. over recall of old elavator. all exit system and corridors are complant.
FIRE-Final Inspection6/27/20086/27/20086/27/2008APART
DetailsForrest France
Building fire life safety approval pending project related fire alarm permit final. EM lights and exit signs tested okay with the exception of one light at the 2nd floor to be repaired today per the electrician, some doors at the 1st floor are not yet installed, need to remove the manual thumbturn at one exit door 1st floor SW side.
BLD-Conference6/23/20086/23/20086/23/2008PPASS
DetailsJim Storey
nick Phone #: ###-####
FIRE-Conference6/23/20086/23/20086/23/2008PDONE
DetailsForrest France
Done in conjunction with project related fire alarm testing. Discussed job finish schedule, elevator upgrade completion date, access controled door hardware, noted one fire extinguisher overdue annual certification.
BLD-Conference5/28/20085/29/20085/29/2008APASS
DetailsJim Storey
nick Phone #: ###-####
BLD-Other5/8/20085/8/20085/9/2008PPART
DetailsDave Hannah
Nick, ceiling t-bar; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt ok to cover ground floor ceiling
BLD-Other4/28/20084/28/20084/29/2008PPART
DetailsDave Hannah
nick Note: above ceiling Phone #: ###-#### ok to cover ceiling first floor
BLD-Other4/17/20084/17/20084/17/2008PPART
DetailsJim Storey
T-bar inspection please-nick Phone #: ###-#### ok to instakl boaders
BLD-Other3/6/20083/6/20083/6/2008PPART
DetailsDave Hannah
nick Note: above t bar ceiling Phone #: ###-#### ceiling grid ok but needs to finish draft stopping
FIRE-Conference3/3/20083/3/20083/4/2008PDONE
DetailsForrest France
On site conference regarding questions related to the building fire alarm system specific to manual pull station locations, in duct detectors and plan review annotations.
BLD-Conference2/27/20082/28/20082/28/2008APASS
DetailsDave Hannah
nick Phone #: ###-#### adding two new doors and walked project with nick
BLD-Framing/Rough-in1/23/20081/24/20081/24/2008APART
DetailsJim Storey
nick Phone #: ###-#### need to maintane fire barrior opening protection.
BLD-Framing/Rough-in1/22/20081/22/20081/22/2008PPART
DetailsJim Storey
nick Phone #: ###-#### fire stop above hard lids in restroom/ pad protection at back to back boxes/ ok to start walls.
BLD-Framing/Rough-in12/27/200712/27/200712/28/2007PPART
DetailsDave Hannah
nick - draft stop Phone #: ###-#### first floor ok to cover ceiling
BLD-Framing/Rough-in12/19/200712/19/200712/19/2007PPART
DetailsDave Hannah
nick Note: 2nd floor Phone #: ###-#### ok to cover second floor wall after elec and plumbing r/i are oked
BLD-Framing/Rough-in12/10/200712/10/200712/10/2007PPART
DetailsDave Hannah
nick Phone #: ###-#### draft stops in attic westside ok
BLD-Conference11/27/200711/28/200711/28/2007APASS
DetailsDave Hannah
nick Phone #: ###-#### draft stops