FIRE-Final Inspection | 3/7/2008 | 3/10/2008 | 3/10/2008 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Code Occupancy Approval | 3/10/2008 | 3/10/2008 | 3/10/2008 | P | PASS |
Scott M.Brown
|
|
|
OK FINAL SIGNED OFF
|
BLD-Final | 3/7/2008 | 3/10/2008 | 3/10/2008 | P | PASS |
Mike Jordan
|
|
|
Dutch ###-####. All issues have been corrected. ok for perm occ.
|
FIRE-Final Inspection | 2/28/2008 | 2/29/2008 | 2/29/2008 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given until the second link is installed on the outside fire door. The door will then need to be tested. All other life safety items are ok.
|
BLD-Final | 2/28/2008 | 2/29/2008 | 2/29/2008 | P | PART |
Mike Jordan
|
|
|
Duch Phone #: -208###-####. Temp occ granted. Needs tp provide ADA counter at POS, provide boot under one wash sink in kitchen, repair cleanout in dining room, make membrane penetration.
|
BLD-Framing/Rough-in | 2/25/2008 | 2/26/2008 | 2/26/2008 | A | PASS |
Mike Jordan
|
|
|
bill - fire wall Phone #: ###-####. Reviewed UL data and inspected plumbing through penetration on 2hr. fire barrier wall at canopy section.
|
BLD-Framing/Rough-in | 2/11/2008 | 2/11/2008 | 2/11/2008 | P | PASS |
Mike Jordan
|
|
|
BILL Phone #: ###-####Completion of 2hr fire barrier wall at canopy section. Also reveiwed detail from architect for continuation of 2hr. wall thru store front.
|
BLD-Framing/Rough-in | 1/24/2008 | 1/25/2008 | 1/25/2008 | P | PASS |
Mike Jordan
|
|
|
Bill please call 1/2 hr before going out Phone #: ###-####. 2hr. wall at canopy section
|
BLD-Other | 1/23/2008 | 1/23/2008 | 1/23/2008 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/23/2008 at 7:03:28 AM. Contact: ###-####. ceiling grid ok.
|
BLD-Framing/Rough-in | 1/18/2008 | 1/22/2008 | 1/22/2008 | A | CANC |
Mike Jordan
|
|
|
bill Phone #: ###-####
|
BLD-Framing/Rough-in | 1/16/2008 | 1/17/2008 | 1/17/2008 | A | NR |
Mike Jordan
|
|
|
Bill-Cieling grid inspection please Phone #: ###-####. Needs trades ri insp. first.
|
BLD-Other | 1/8/2008 | 1/8/2008 | 1/8/2008 | P | PASS |
Mike Jordan
|
|
|
bill Note: fire wall Phone #: ###-####
|
BLD-Framing/Rough-in | 1/4/2008 | 1/4/2008 | 1/4/2008 | P | PART |
Mike Jordan
|
|
|
Inner layer of shaft board at 2hr. fire barrier extension to blockout existing door.
|
BLD-Framing/Rough-in | 1/3/2008 | 1/4/2008 | 1/4/2008 | A | PART |
Mike Jordan
|
|
|
dutch Phone #: ###-####. hardlids ok, pend. mech. Interior soffits ok. Contractor to supply UL tech data for membrane and through penetrations at two hr. fire barrier. Also rec eived detail for beam protection at 2hr. firebarrier wall. Bldg. official has approved beam protection detail.
|
BLD-Framing/Rough-in | 12/12/2007 | 12/13/2007 | 12/13/2007 | A | PART |
Mike Jordan
|
|
|
bill Phone #: ###-####. Interior steel stud walls only, no grid or hardlids. Needs to pull mech. permit.
|
BLD-Conference | 12/10/2007 | 12/11/2007 | 12/11/2007 | P | DONE |
Mike Jordan
|
|
|
Met on site with architect conering issues noted on c/n that was issued. All items have been taken care of except for wood beam penetration at 2hr. fire barrier wall. Architect to provide alernate detail and submit to bldg. official for approval.
|
BLD-Footing | 11/9/2007 | 11/13/2007 | 11/13/2007 | A | PART |
Mike Jordan
|
|
|
dennis Phone #: ###-####. footings for ts columns ok. Also wrote contractor c/n for architect to provide UL approved assembly for wood beam penetrations at 2hr fire barrier wall, deatail forcontinuation of 2hr. fire barrier wall thruogh storefront to fire door assembly, provide ul 2hr wall asemmbly, detail for 2hr fire barrier wall at west wall intersection were existing exit door was left.
|