Permit Information
Permit NumberBLD07-02082
StatusFinaled
Name COLSON & COLSON GENERAL CONTRACTOR
Site Address 4892 N CLOVERDALE RD
Project NameBoise Retirement Residence
Customer Number 
ePlanReviewNo
Description
(BOISE RETIREMENT RESIDENCE - BLDG C - WEST SECTION) To construct a new 29 unit 23,254 square foot, three story, I-1, non state licensed, residential care, assisted living facility where all residence will be capable of responding to an emergency situation without physical assistance. This building to be fully fire sprinklered with an NFPA 13-R system as required by the occupancy. This area is separated from the center building (Section A) by a 2-hr. fire wall. Note: This project was reviewed by ICC for energy, structural, nonstructural and accessibility requirements for code compliance. (23 units are less than 800 sq.ft. and 6 units are greater than 800 sq.ft.)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/20/200910/21/200910/20/2009APASS
DetailsJim Sly
bryan Phone #: ###-####
OK for Perm Occ.
FIRE-Final Inspection10/20/200910/20/200910/20/2009PPASS
DetailsTroy Cobbley
Life safety passed.
FIRE-Final Inspection10/5/200910/6/200910/6/2009PFAIL
DetailsTroy Cobbley
The occupant load signs have been mounted and the exit signs, emergency lighting and exit discharge lighting have been verified for functionality. One emergency light and one exit sign need repaired as discussed. See the 10/5/2009 entry for other items needing addressed prior to a final sign off. The relocation of the generator is ok per scott and the fire alarm panel can provide supervision of the primary power at the horizontal sliding doors per Jason Blaise.
FIRE-Final Inspection10/1/200910/5/200910/5/2009PFAIL
DetailsTroy Cobbley
The project related fire sprinkler and fire alarm permits need to be finaled, both of the horizontal sliding doors need to be adjusted so that they easily open manually, the atrium smoke evacuation system needs to be addressed, the exit discharge lighting needs to be removed from control by the photocells and electrical super vision of the horizontal sliding doors needs to be addressed. All of the exit signs, emergency lights and exit discharge lights need to be inspected for placement and tested for functionality after the generator switch over has been repaired. Also need to verify that the relocation of the emergency generator is ok with plan review.
BLD-Final9/16/20099/17/20099/17/2009APART
DetailsJim Sly
Phone #: ###-#### Internet Inspection Request from: Bryan Herb
Checked out all sleeping rooms.....OK, but need all Req signatures for final.
BLD-Other9/10/20099/14/20099/14/2009PPASS
DetailsJim Storey
Drop ceiling grid inspection Phone #: ###-#### Internet Inspection Request from: Bryan Herb
BLD-Other8/24/20098/25/20098/25/2009ANR
DetailsJim Sly
Suspended ceiling Phone #: ###-#### Internet Inspection Request from: Bryan Herb
BLD-Energy code compliance5/26/20095/27/20095/27/2009APART
DetailsJim Sly
1st floor insulation Phone #: ###-#### Internet Inspection Request from: Bryan Herb........OK
BLD-Wall cover5/26/20095/26/20095/26/2009PPASS
DetailsJim Sly
2nd floor sheetrock nailing Phone #: ###-#### Internet Inspection Request from: Bryan Herb
BLD-Wall cover5/20/20095/21/20095/21/2009APASS
DetailsJim Sly
sheetrock nailing 3rd floor hallways 1st layer Phone #: ###-#### Internet Inspection Request from: Bryan Herb
BLD-Energy code compliance5/19/20095/20/20095/20/2009APASS
DetailsJim Sly
2nd floor insulation Phone #: ###-#### Internet Inspection Request from: Bryan Herb
BLD-Energy code compliance5/15/20095/15/20095/15/2009PPASS
DetailsJim Sly
3rd floor insulation Phone #: ###-#### Internet Inspection Request from: Bryan Herb
BLD-Framing/Rough-in5/13/20095/14/20095/14/2009APASS
DetailsJim Sly
1st and 2nd floor fire caulking Phone #: ###-#### Internet Inspection Request from: Bryan Herb
BLD-Wall cover5/11/20095/12/20095/12/2009PPASS
DetailsJim Sly
reinspect draft stop on 3rd floor. Phone #: ###-#### Internet Inspection Request from: Bryan Herb
BLD-Framing/Rough-in5/8/20095/11/20095/11/2009APART
DetailsJim Sly
fire caulking 3rd floor Phone #: ###-#### Internet Inspection Request from: Bryan Herb
BLD-Wall cover4/20/20094/21/20094/21/2009APASS
DetailsJim Sly
1st and 2nd floor hallway fire caulking inspection Phone #: ###-#### Internet Inspection Request from: Bryan Herb
BLD-Framing/Rough-in2/26/20093/2/20093/2/2009PPART
DetailsJim Sly
interior shear inspection Phone #: ###-#### Internet Inspection Request from: Bryan Herb Int Shear C wing OK.
BLD-Framing/Rough-in2/4/20092/5/20092/5/2009APART
DetailsJim Sly
Roof inspection Phone #: ###-#### Internet Inspection Request from: Bryan Herb
Roof Nailing and straps appear OK BLDG C
BLD-Framing/Rough-in1/30/20092/2/20092/2/2009APART
DetailsJim Sly
exterior sheer wall C wing Phone #: ###-#### Internet Inspection Request from: Bryan Herb
Exterior wall shear nailing OK Bldg C
BLD-Conference12/11/200812/12/200812/12/2008ADONE
DetailsJim Sly
discussion of plumbing against 2hr fire wall Phone #: ###-#### Internet Inspection Request from: Bryan Herb
BLD-Concrete11/24/200811/25/200811/25/2008PPART
DetailsJim Sly
MTI scheduled for 2:30 and concrete for 3:00 for interior footings in last wing. Phone #: ###-#### Internet Inspection Request from: Bryan Herb
Interior Footings OK pending MTI insp, tests and approvals.
BLD-Energy code compliance10/13/200810/17/200810/17/2008APASS
DetailsJim Sly
foundation insulation Phone #: ###-#### Internet Inspection Request from: Bryan Herb
BLD-Foundation10/13/200810/14/200810/14/2008APART
DetailsJim Sly
Phone #: ###-#### Internet Inspection Request from: Bryan Herb
Wall at west end OK pending MTI special insp, tests, and approvals.

w
BLD-Footing10/7/200810/8/200810/8/2008PPART
DetailsJim Sly
Phone #: ###-#### Internet Inspection Request from: Bryan Herb
West end. OK


w