BLD-Final | 2/22/2008 | 2/22/2008 | 2/22/2008 | P | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 2/22/2008 | 2/22/2008 | 2/22/2008 | P | PASS |
Mike Jordan
|
|
|
Received letter from special insp. agency. No issues were noted. Letter of compliance was issued for shell and core.
|
BLD-Final | 2/21/2008 | 2/21/2008 | 2/21/2008 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/21/2008 at 7:55:22 AM. Contact: ###-####. Everything ok, Need final letter from special insp. agency prior to issuing letter of compliance for shell and core.
|
BLD-Energy code compliance | 2/21/2008 | 2/21/2008 | 2/21/2008 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/21/2008 at 7:54:40 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/21/2008 | 2/21/2008 | 2/21/2008 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/21/2008 at 7:53:42 AM. Contact: ###-####.
|
BLD-Energy code compliance | 2/20/2008 | 2/20/2008 | 2/20/2008 | P | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/20/2008 at 7:06:41 AM. Contact: ###-####.
|
BLD-Final | 2/20/2008 | 2/20/2008 | 2/20/2008 | P | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/20/2008 at 7:08:13 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/20/2008 | 2/20/2008 | 2/20/2008 | P | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/20/2008 at 7:06:00 AM. Contact: ###-####.
|
FIRE-Final Inspection | 2/18/2008 | 2/19/2008 | 2/19/2008 | A | PASS |
Troy Cobbley
|
|
|
LIfe safety passed. I will verify addresses when the tenant improvements are done since each space has the potential to be a separate street address. The same for door hardware.
|
Code Occupancy Approval | 2/19/2008 | 2/19/2008 | 2/19/2008 | A | PASS |
Scott M.Brown
|
|
|
OK FOR FINAL CARD SIGNED OFF
|
FIRE-Final Inspection | 2/7/2008 | 2/8/2008 | 2/8/2008 | A | FAIL |
Troy Cobbley
|
|
|
The relocated fire hydrant to the southwest of the building does not meet the min. 18" from the ceter of the outlet to the ground requirement in NFPA 24 7.3.3. Also a new fire hydrant has been added roughly 30'-0" to the northeast of the building. This hydrant is not shown on the grading plans.
|
BLD-Framing/Rough-in | 12/4/2007 | 12/5/2007 | 12/5/2007 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 12/4/2007 at 5:25:59 PM. Contact: ###-####. Exterior shear, nailing for roof diaphragm and all hardware.
|
BLD-Foundation | 10/24/2007 | 10/24/2007 | 10/24/2007 | P | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/24/2007 at 7:49:24 AM. Contact: ###-####.
|
BLD-Energy code compliance | 10/24/2007 | 10/24/2007 | 10/24/2007 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/24/2007 at 7:49:24 AM. Contact: ###-####.
|
BLD-Footing | 10/15/2007 | 10/16/2007 | 10/16/2007 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/15/2007 at 10:17:30 AM. Contact: ###-####. footing for trash enclosure.
|
BLD-Footing | 10/10/2007 | 10/10/2007 | 10/10/2007 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/10/2007 at 10:58:30 AM. Contact: ###-####. two interior column pad footings. ok. Also reviewed special insp. reports. ok.
|
BLD-Footing | 10/4/2007 | 10/5/2007 | 10/5/2007 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/4/2007 at 10:26:57 AM. Contact: ###-####. wip on stemwalls, also reviewed special insp. report for footings, ok.
|
BLD-Footing | 10/2/2007 | 10/3/2007 | 10/3/2007 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/2/2007 at 11:59:24 AM. Contact: ###-####.wip, footings will have special insp. Footing subgrade approved by geotech engineer as per contractor. Noted to contractor to have report on site for next insp.
|