Permit Information
Permit NumberBLD07-02405
StatusFinaled
Name JIM KISSLER LLC
Site Address 1907 S BROADWAY AVE
Project NameGarfield Place- SHELL
Customer Number 
ePlanReviewNo
Description
Garfield Place (Office Shell & Core) - to construct a new 10,520 square foot, two story, wood framed, office shell and core building and related site improvements. The finished core areas include two finished stairways, an elevator, elevator machine room, mechanical room and janitor closet. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Other8/11/20088/11/20088/11/2008PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 8/11/2008 at 9:58:23 AM. Contact: ###-####.
DOC - Permit Finaled8/11/20088/11/20088/11/2008PPASS
DetailsJim Storey
BLD-Conference8/8/20088/8/20088/8/2008PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 8/8/2008 at 8:09:20 AM. Contact: ###-####.contractor is going to recall this,, 301 call 415 prior to going out,, ok for TI bld 08-01542 occ.
FIRE-Conference8/6/20088/7/20088/7/2008ADONE
DetailsForrest France
Remainder of building shell life safety issues are finished.
BLD-Conference8/6/20088/6/20088/6/2008PCANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 8/6/2008 at 7:05:48 AM. Contact: ###-####.
BLD-Conference6/30/20087/1/20087/1/2008ADONE
DetailsDave Hannah
Scheduled by a contractor via Hello! on 6/30/2008 at 3:15:11 PM. Contact: ###-####.
BLD-Conference6/19/20086/19/20086/19/2008APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 6/19/2008 at 7:09:47 AM. Contact: ###-####.
BLD-Final6/4/20086/5/20086/5/2008PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 6/4/2008 at 7:13:55 PM. Contact: ###-####. ok for ti occ.
FIRE-Final Inspection6/4/20086/5/20086/5/2008PPASS
DetailsForrest France
Building shell life safety inspection completed acceptable with the exception of missing fire lane signage to be installed today. Remainder of fire life safety issues including the 2nd floor area of refuge and elevator recall to be tested and approved in conjunction with and prior to tenant occupancy permit finals.
Code Occupancy Approval6/2/20086/3/20086/3/2008APASS
DetailsWm. Michael Meloy
pat child Phone #: ###-####
Code Occupancy Approval  6/2/2008 FAIL
DetailsWm. Michael Meloy
Inspection on May 30, 2008, found the rear enclosure not finished, but needing stucco. OK to bond for $1,100.00. for temp occupancy.
BLD-Framing/Rough-in5/29/20085/30/20085/30/2008APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 5/28/2008 at 4:41:54 PM. Contact: ###-####.
BLD-Framing/Rough-in5/28/20085/29/20085/29/2008PCANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 5/28/2008 at 4:41:54 PM. Contact: ###-####. out of time rolled over.
BLD-Framing/Rough-in5/27/20085/28/20085/28/2008PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 5/27/2008 at 4:12:18 PM. Contact: ###-####.ceilling ok pending ele aproval.
FIRE-Conference5/23/20085/23/20085/23/2008PDONE
DetailsForrest France
Discussion with contractor regarding project schedule and building permit shell and tenant permit approvals prior to elevator completion.
BLD-Conference5/21/20085/22/20085/22/2008APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 5/21/2008 at 4:55:17 PM. Contact: ###-####.
BLD-Framing/Rough-in4/23/20084/24/20084/24/2008APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 4/23/2008 at 4:05:53 PM. Contact: ###-####. hard lid framing ok
BLD-Framing/Rough-in4/2/20084/2/20084/2/2008PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 4/2/2008 at 5:58:37 AM. need to fire stop.
BLD-Framing/Rough-in3/27/20083/28/20083/28/2008APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 3/27/2008 at 10:13:35 AM. Contact: ###-####. truss bracing ok
BLD-Framing/Rough-in3/24/20083/24/20083/24/2008PNR
DetailsDave Hannah
Scheduled by a contractor via Hello! on 3/24/2008 at 6:46:46 AM. Contact: ###-####.
BLD-Framing/Rough-in3/20/20083/20/20083/20/2008PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 3/20/2008 at 8:41:33 AM. Contact: ###-####.
BLD-Framing/Rough-in3/17/20083/18/20083/18/2008APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 3/17/2008 at 6:06:52 AM. Contact: ###-####. remove wall heater from p/l wall. misc. framing conections/ fire blk at ceilling line. ok to insulate.
BLD-Framing/Rough-in3/11/20083/12/20083/12/2008APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 3/11/2008 at 2:00:58 PM. Contact: ###-####. first floor framing ok/ bolts and mlb king stud to header/ strap top plates for continous aplaction. fire wall gyp being instaled as per accepted joint aplacation at joist locations in p/l walls and encloser walls back of elvator.
BLD-Footing3/12/20083/13/20083/12/2008ACANC
DetailsJim Storey
Contact: ###-####.
BLD-Framing/Rough-in3/7/20083/10/20083/10/2008APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 3/7/2008 at 5:15:23 PM. Contact: ###-####. exterior stucco ok to cover.
BLD-Framing/Rough-in3/5/20083/6/20083/6/2008APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 3/5/2008 at 11:01:44 AM. Contact: ###-####. ok to start interior cover of p/l wall to create rating and start stair encloser wall on ti side.
BLD-Framing/Rough-in3/3/20083/4/20083/4/2008APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 3/3/2008 at 3:35:16 PM. Contact: ###-####.se and nw brace panel nailling ok under fur out arch. feacher.
BLD-Framing/Rough-in2/27/20082/27/20082/27/2008PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 2/27/2008 at 10:12:06 AM. Contact: ###-####.roof deck straps and naiolling ok/ insulation ok.
BLD-Framing/Rough-in2/25/20082/26/20082/25/2008ACANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 2/25/2008 at 7:14:18 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Feb 25 2008 6:07PM.
BLD-Conference2/19/20082/20/20082/20/2008APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 2/19/2008 at 8:56:47 AM. Contact: ###-####. fire wall at struc. members ok for pre gyp.
BLD-Conference2/12/20082/13/20082/13/2008PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 2/12/2008 at 5:51:25 PM. Contact: ###-####.aproved es report for 1 hour assembly fra-103/ es 1254 and 1318. sent to be archived with aproved docs.
BLD-Conference2/5/20082/6/20082/6/2008APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 2/5/2008 at 4:37:49 PM. Contact: ###-####. enginreering for roof suport to be submited/ floor protection as per aproved submital from plan review.
BLD-Footing12/14/200712/14/200712/14/2007PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 12/14/2007 at 10:17:18 AM. Contact: ###-####. placed with si reports pending
BLD-Foundation12/11/200712/12/200712/12/2007PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 12/11/2007 at 4:47:06 PM. Contact: ###-####.placed with si
BLD-Footing12/6/200712/6/200712/6/2007PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 12/6/2007 at 7:56:27 AM. Contact: ###-####.pwsi
BLD-Footing12/4/200712/5/200712/5/2007APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 12/4/2007 at 8:27:02 AM. Contact: ###-####. si on site ok pending report after sampling and testing of concrete.