BLD-Final | 5/11/2008 | 5/12/2008 | 5/12/2008 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 5/11/2008 at 9:23:41 PM. Contact: ###-####. signed on temp occ.,, but now see that all trades are signed off in comp. system,, final/perm. cof o is ok
|
FIRE-Final Inspection | 5/11/2008 | 5/12/2008 | 5/12/2008 | A | PASS |
Forrest France
|
|
|
Noted corrections have been completed, minor adjustments to duct sample tube orientation done while on site, fire life safety finaled.
|
Code Occupancy Approval | 5/9/2008 | 5/9/2008 | 5/9/2008 | P | PASS |
Michael Garner
|
|
|
Site inspection completed - work has been completed according to approved plans
|
BLD-Final | 5/9/2008 | 5/9/2008 | 5/9/2008 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/9/2008 at 9:37:22 AM. Contact: ###-####. needs fire c/n items completed and finaled
|
FIRE-Final Inspection | 5/9/2008 | 5/9/2008 | 5/9/2008 | A | FAIL |
Troy Cobbley
|
|
|
Provide tags for the three fire extinguishers. Provide remote annunciators as discussed for the duct smoke detectors. The duct smoke detectors are mounted in the 90 degree elbows of the return air ducting. A manometer test will be required or the ducting modified to the 6 to 10 duct widths as per NFPA 72. All other items checked out ok.
|
FIRE-Final Inspection | 5/8/2008 | 5/8/2008 | 5/8/2008 | P | NR |
Forrest France
|
|
|
Not ready at this time per phone call from contractor, to be rescheduled as discussed.
|
FIRE-Conference | 4/14/2008 | 4/14/2008 | 4/14/2008 | P | DONE |
Forrest France
|
|
|
On site conference regarding door hardware, duct detectors and project fire code review notes.
|
BLD-Conference | 4/14/2008 | 4/14/2008 | 4/14/2008 | P | PART |
Tony Young
|
|
|
andy Phone #: ###-#### conf w/ 430 on doors, landings, etc
|
BLD-Framing/Rough-in | 4/10/2008 | 4/10/2008 | 4/10/2008 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 4/10/2008 at 7:08:34 AM. Contact: ###-####. walls ok to cover
|
BLD-Framing/Rough-in | 4/3/2008 | 4/3/2008 | 4/3/2008 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 4/3/2008 at 6:52:06 AM. Contact: ###-####. braces under mech rooftop units
|
BLD-Conference | 3/20/2008 | 3/20/2008 | 3/20/2008 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 3/20/2008 at 5:55:59 AM. Contact: ###-####. draft stop ?s,, can do on existing ponywall framing,, other misc ?s,, ok
|