Permit Information
Permit NumberBLD07-02458
StatusFinaled
Name STOCK CONSTRUCTION MANAGEMENT
Site Address 2854 S FEATHERLY WAY
Project NameSystem Tech INC
Customer Number 
ePlanReviewNo
Description
System Tech - To construct a new 12,035 square foot office and warehouse building with a 1,400 square foot storage mezzanine and related site improvements. This building is constructed of masonry exterior walls with steel structural interior frame and roof system. This permit has been modified to included an automatic fire sprinkler system per Fire Department requirements. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/16/200810/17/200810/17/2008APART
DetailsMike Jordan
Scheduled via mobile device. Phone #: 5737193. ok for temp occ. Will be ok for perm occ. once zoning receives and approves new elevation detail showing additional overhead door.
FIRE-Final Inspection10/16/200810/17/200810/17/2008APASS
DetailsTroy Cobbley
Life safety passed
BLD-Final10/15/200810/16/200810/16/2008PNR
DetailsMike Jordan
eric, please call to make sure he''s there Phone #: ###-####
FIRE-Final Inspection10/15/200810/16/200810/16/2008AFAIL
DetailsTroy Cobbley
See the city approved plans for locations where exit discharge lighting and interior emergency lighting is inoperative. Need the project related fire alarm permit finaled as well. Scott Arleno is ok with the fire dept access through the gate on the north side of the building.
Code Occupancy Approval Temp  10/8/2008 DONE
Staff has issued the applicant a 30 day temporary occupancy. The 30 day period will allow the applicant adequate time to receive a staff level design review approval to add an overhead door and a man door to the east elevation. Once the applicant has submitted the staff level DR application, the applicant is also required to update the building plans to reflect the additional overhead door and the man door that was constructed within the east elevation. ANT 10-8-08
Code Occupancy Approval  9/26/2008 FAIL
Staff arrived at the site and waited for 20 minutes for the applicant to arrive. Staff did briefly look at the site. When staff asked why the pre-finished metal shade coverings over the windows had not been installed, the applicant replied,"those will be installed later." Staff responded by stating that the awnings either had to be installed or bonded for in order for occupancy to be issued. The applicant grabbed the plans and took them into the building. Staff asked the applicant if they wanted staff to go over the entire site to let them know if there were any other chnages necessary to obtain occupancy but the applicant replied by saying that "all of that could be done once the inspection had been rescheduled. A new reinspection will be scheduled once the window shades have been installed. 9-26-08
BLD-Final9/18/20089/18/20089/18/2008PNR
DetailsMike Jordan
Eric- call 30 mins prior to going Phone #: ###-####
BLD-Framing/Rough-in8/15/20088/15/20088/18/2008PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/15/2008 at 9:13:07 AM. Contact: ###-####. Sheet rock for riser room.
BLD-Framing/Rough-in7/31/20087/31/20087/31/2008PPART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 7/31/2008 at 8:45:57 AM. Contact: ###-####.Interior framed walls only. no grid or soffitt.
BLD-Framing/Rough-in7/15/20087/15/20087/16/2008PPART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 7/15/2008 at 10:57:35 AM. Contact: ###-####. Wants to rock from top of wall to ceiling. Needs to contact other trade insp. for approval.
BLD-Foundation3/5/20083/5/20083/5/2008PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 3/5/2008 at 8:43:29 AM. Contact: ###-####. Interior column pad footings.
BLD-Foundation2/14/20082/15/20082/15/2008APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 2/14/2008 at 4:29:38 PM. Contact: ###-####. wip on perimeter stemwall. Need RFI from engineer for fix on vertical steel. Vertical steel placed at 8" oc. Needs to be 2#5 at 24" oc.
BLD-Foundation2/8/20082/11/20082/11/2008APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 2/8/2008 at 3:30:32 PM. Contact: ###-####. perimeter footing.
BLD-Foundation2/5/20082/6/20082/6/2008APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 2/5/2008 at 1:55:50 PM. Contact: ###-####. delay due t weather. wip on installing vert. Steel at perimeter footings. Project will have special insp.