BLD-Final | 5/22/2008 | 5/22/2008 | 5/22/2008 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/22/2008 at 7:58:35 AM. Contact: ###-####.
|
DOC - Permit Finaled | 5/22/2008 | 5/22/2008 | 5/22/2008 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 1/16/2008 | 1/17/2008 | 1/17/2008 | A | PASS |
Mike Jordan
|
|
|
jerry - insulation Phone #: ###-####. All energy code issues resolved. ok to cover.
|
BLD-Framing/Rough-in | 1/14/2008 | 1/15/2008 | 1/15/2008 | A | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/14/2008 at 4:23:10 PM. Contact: ###-####. Framing issues corrected. Needs to complete airseal package at tub downstairs, and all electrical boxes at ceiling. Also needs more baffels for attic ventilation.
|
BLD-Framing/Rough-in | 1/4/2008 | 1/7/2008 | 1/7/2008 | A | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/4/2008 at 12:18:24 PM. Contact: ###-####. Complete nairseal package, provide 1/2" ASTM A307 bolts on scab pice on A03 truss as noted on engineering, Provide 5 rows of nailing on bottom chord of D3 truss as noted on engineering. c/n posted. ok to insul.
|
BLD-Foundation | 11/14/2007 | 11/14/2007 | 11/14/2007 | P | PASS |
Mike Jordan
|
|
|
sebastin Phone #: ###-####. Interior column pad footing in garage ok.
|
BLD-Foundation | 11/13/2007 | 11/13/2007 | 11/13/2007 | P | FAIL |
Mike Jordan
|
|
|
Stem wall; Sebastian at ###-####. column pad footing for garage not as per plan. Needs to be removed and placed as per plan. Will also require reinspection. Jonathan with Welch custom homes was notified.
|
BLD-Footing | 11/8/2007 | 11/9/2007 | 11/9/2007 | P | PART |
Mike Jordan
|
|
|
sabanez Phone #: ###-####
|