FIRE-Final Inspection | 5/27/2008 | 5/27/2008 | 5/27/2008 | P | PASS |
Forrest France
|
|
|
Retested non-functional HVAC unit duct detector for verification of repair, two EM lights at the kitchen and service area okayed, final fire life safety inspection passed.
|
BLD-Final | 5/23/2008 | 5/23/2008 | 5/23/2008 | P | PEND |
Mike Jordan
|
|
|
gary Phone #: ###-####. Will be ok for per or temp once life/safety goes perm or temp.
|
FIRE-Final Inspection | 5/22/2008 | 5/23/2008 | 5/23/2008 | A | FAIL |
Forrest France
|
|
|
Need to repair two non-functional EM lights at the kitchen and service area, one HVAC unit failed to shut down upon smoke detection, one EM light at the entry vestibule repaired while on site, remainder of items previously noted are acceptable.
|
BLD-Final | 5/22/2008 | 5/23/2008 | 5/23/2008 | A | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/22/2008 at 5:05:56 PM. Contact: ###-####.
|
BLD-Final | 5/21/2008 | 5/22/2008 | 5/22/2008 | P | NR |
Jim Sly
|
|
|
gary - around 3:00 if possible please Phone #: ###-#### Need CDHD
|
FIRE-Final Inspection | 5/21/2008 | 5/22/2008 | 5/22/2008 | A | FAIL |
Troy Cobbley
|
|
|
See the city approved notes for items circled in red ink that need addressed. Items include the correct annunciators for the duct smoke detectors, address installed, emergency lighting and exit signs tested....ect. Also a suppression system has been installed and I can find no attached FIR permit for this work. Per the general contractor the installer was General Fire. I contacted Scott in our office about double fees when this permit comes in. Basically not inspection was performed but a conference was held.
|
Code Occupancy Approval | 5/20/2008 | 5/20/2008 | 5/20/2008 | A | PASS |
Scott M.Brown
|
|
|
OK FOR FINAL
|
BLD-Other | 5/16/2008 | 5/16/2008 | 5/16/2008 | P | PART |
Mike Jordan
|
|
|
gary Note: grid Phone #: ###-####
|
BLD-Energy code compliance | 4/8/2008 | 4/9/2008 | 4/9/2008 | A | PASS |
Mike Jordan
|
|
|
gary Phone #: ###-####
|
BLD-Framing/Rough-in | 4/7/2008 | 4/8/2008 | 4/8/2008 | A | PART |
Mike Jordan
|
|
|
gary Phone #: ###-####. Interior steel stud framed walls, furout walls,hardlids and added structural beams for support and hoods. Needs to install three straps atr added supports for new hoods. will check on energy code.
|
BLD-Framing/Rough-in | 3/6/2008 | 3/6/2008 | 3/6/2008 | P | PART |
Mike Jordan
|
|
|
gary Phone #: ###-####
|
BLD-Framing/Rough-in | 3/4/2008 | 3/5/2008 | 3/5/2008 | A | PART |
Mike Jordan
|
|
|
gary Note: if possible 8-9 Phone #: ###-####. Verified H2.5 from studs to new roof deck connection at pop outs. Noted several areas to contractor that requires fireblocking. Also noted that simpson hold straps not yet nailed. contractor to call for additional framing insp. when ri insp. are complete.
|
BLD-Foundation | 2/28/2008 | 2/28/2008 | 2/28/2008 | P | PART |
Mike Jordan
|
|
|
gary Note: if possible early afternoon please Phone #: ###-####. Stemwalls at sw and se ends of existing blldg. wip on installing holdowns as per approved plans.
|
BLD-Footing | 2/26/2008 | 2/27/2008 | 2/27/2008 | A | PART |
Mike Jordan
|
|
|
gary Phone #: ###-####. New exterior footings at sw and se ends of existing bldg.
|
BLD-Footing | 2/25/2008 | 2/26/2008 | 2/26/2008 | A | NR |
Mike Jordan
|
|
|
jerry Phone #: ###-####. No forms or rbar installed. Noted to contractor to reschedule inspection.
|