BLD-Final | 4/28/2008 | 4/28/2008 | 4/29/2008 | P | PASS |
Dave Hannah
|
|
|
pls coordinate with fire final if possible. thank you. Phone #: ###-#### Internet Inspection Request from: John Lodman ok for perm occ
|
FIRE-Final Inspection | 4/28/2008 | 4/28/2008 | 4/28/2008 | P | PASS |
Troy Cobbley
|
|
|
Door hardware changed as per Forrest France notes. KR
|
BLD-Final | 4/21/2008 | 4/22/2008 | 4/23/2008 | P | FAIL |
Dave Hannah
|
|
|
please note that the mec08-00569 permit linked to this permit is not correct, should be on the bonefish grille permit. Phone #: ###-#### Internet Inspection Request from: John Lodman need to install door hardwear
|
BLD-Final | 4/21/2008 | 4/21/2008 | 4/22/2008 | P | CANC |
Dave Hannah
|
|
|
please note that the mec08-00569 permit linked to this permit is not correct, should be on the bonefish grille permit. Phone #: ###-#### Internet Inspection Request from: John Lodman
|
FIRE-Final Inspection | 4/21/2008 | 4/21/2008 | 4/21/2008 | P | FAIL |
Forrest France
|
|
|
Door hardware is not approved as installed.
|
Code Occupancy Approval | 4/21/2008 | 4/21/2008 | 4/21/2008 | P | PASS |
Joe R Venneman
|
|
|
Doors are finally in and meet the BLD plan requirements
|
Code Occupancy Approval | | | 4/21/2008 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 2/28/2008 | 2/29/2008 | 2/29/2008 | P | PASS |
Dave Hannah
|
|
|
pending morning fire sprinkler cover approval. thank you. Phone #: ###-#### Internet Inspection Request from: John Lodman
|
BLD-Framing/Rough-in | 2/22/2008 | 2/22/2008 | 2/22/2008 | P | DONE |
Dave Hannah
|
|
|
Requesting partial cover approval for column wraps only. Plumbing and elect inspections for two hose bibbs and a couple of outlets are this afternoon also. Soffit cover will be requested at a later date. Phone #: ###-#### Internet Inspection Request from: John Lodman
|
BLD-Framing/Rough-in | 2/22/2008 | 2/22/2008 | 2/22/2008 | P | PASS |
Dave Hannah
|
|
|
Requesting partial cover approval for column wraps only. Plumbing and elect inspections for two hose bibbs and a couple of outlets are this afternoon also. Soffit cover will be requested at a later date. Phone #: ###-#### Internet Inspection Request from: John Lodman
|
BLD-Foundation | 2/18/2008 | 2/19/2008 | 2/19/2008 | A | PASS |
Dave Hannah
|
|
|
arch wraps of struct columns. epoxy dowels were inspected by MTI as discussed previously. Pour is 9:00 am today! Phone #: ###-#### Internet Inspection Request from: John Lodman
|
BLD-Other | 2/12/2008 | 2/12/2008 | 2/13/2008 | P | PART |
Dave Hannah
|
|
|
john - deck pour Phone #: ###-#### spec inspection oked steel and deck ok to pour deck
|
BLD-Footing | 2/5/2008 | 2/6/2008 | 2/6/2008 | A | PASS |
Dave Hannah
|
|
|
1st thing am please- approved to start pour by Mike Jordan. Thank you. Phone #: ###-#### Internet Inspection Request from: John Lodman
|
BLD-Footing | 2/4/2008 | 2/5/2008 | 2/5/2008 | P | PART |
Mike Jordan
|
|
|
late afternoon if possible please Phone #: ###-#### Internet Inspection Request from: John Lodman.. colummn pad footings for exterior terrace. footings at exisiting planter not per plan.
|
FIRE-Conference | 2/4/2008 | 2/5/2008 | 2/5/2008 | A | DONE |
Forrest France
|
|
|
Site conference regarding hardware issues for relocated doors, also discussed project related fire alarm and sprinkler permits required.
|
BLD-Footing | 2/4/2008 | 2/4/2008 | 2/4/2008 | P | CANC |
Dave Hannah
|
|
|
John late pm if possible Phone #: ###-####-Cancel per John Lodman on 2/4/08 @ 11:47am BAS
|