Garden Plaza - Office/Retail (shell & core) - To construct a new 21,000 square foot, three story steel frame and masonry retail and office building shell and core and related site improvements. The finished core areas include first floor: entry lobby, restrooms, elevator and elevator machine room, janitor closet, fire riser room and two enclosed stairways; second floor: two restrooms, janitor closet and hallway; third floor: two restrooms and janitor closet. This is a shell and core permit only and no occupancy is allowed under this permit. Separate tenant improvement permits will be required to finish this building for occupancy. 1st Fl. 6,890 sq. ft., 2nd Fl. 6,970 sq. ft., 3rd Fl. 7,140 sq. ft.. This lot is within the floodplain area. An elevation certificate is required to be submitted to and approved by Jim Wyllie, Public Works Dept., prior to calling for a framing inspection. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/14/20095/14/20095/14/2009PPASS
DetailsTony Young
Phone #: ###-#### Internet Inspection Request from: Jessica Noland
final ok
DOC - Permit Finaled5/14/20095/14/20095/14/2009PPASS
DetailsTony Young
BLD-Final5/13/20095/13/20095/13/2009PNR
DetailsTom Arcoraci
Phone #: ###-#### Internet Inspection Request from: Jessica Noland pending zoning
BLD-Conference2/16/20092/17/20092/17/2009APART
DetailsTony Young
hand rail consult Phone #: ###-#### Internet Inspection Request from: Jessica Noland
fire riser access hand rails can turn at bottom to stay out of public way
BLD-Final1/28/20091/29/20091/29/2009PPART
DetailsTony Young
Phone #: ###-#### Internet Inspection Request from: Jessica Noland
temp ok,, need to finish out side access,, ok for temp occ on 3rd floor
FIRE-Final Inspection1/28/20091/29/20091/29/2009APASS
DetailsTroy Cobbley
life safety passed
FIRE-Final Inspection1/27/20091/28/20091/28/2009PCANC
DetailsTroy Cobbley
fire life safety Phone #: ###-#### Internet Inspection Request from: Jessica Noland Inspection cancelled from web by: Jessica Noland
BLD-Final1/27/20091/28/20091/28/2009PCANC
DetailsTony Young
LATE PM PLEASE Phone #: ###-#### Internet Inspection Request from: Jessica Noland Inspection cancelled from web by: Jessica Noland
FIRE-Final Inspection1/26/20091/27/20091/27/2009PCANC
DetailsTroy Cobbley
The life safety can be finaled when the project related fire sprinkler permit is finaled.
FIRE-Final Inspection1/23/20091/26/20091/26/2009PCANC
DetailsTroy Cobbley
Need the project related fire alarm and fire sprinkler permits finaled first. I also ran out of time for the inspection today.
BLD-Conference1/22/20091/23/20091/23/2009PPASS
DetailsTony Young
above ceiling inspection 1st and 2nd floor Phone #: ###-#### Internet Inspection Request from: Jessica Noland
BLD-Framing/Rough-in12/29/200812/30/200812/30/2008ANR
DetailsTony Young
ceiling inspection to cover Phone #: ###-#### Internet Inspection Request from: Jessica Noland
they were wanting a grid inspection on bld08=00594 for T.I.
BLD-Framing/Rough-in12/26/200812/29/200812/29/2008PCANC
DetailsTony Young
ceiling inspection to cover. Phone #: ###-#### Internet Inspection Request from: Jessica Noland Inspection cancelled from web by: Jessica Noland
BLD-Framing/Rough-in12/24/200812/26/200812/26/2008APART
DetailsTony Young
above ceiling inspection for cover Phone #: ###-#### Internet Inspection Request from: Jessica Noland
need mech r/in,, ok to drop perimeter tiles
BLD-Framing/Rough-in12/17/200812/18/200812/18/2008APART
DetailsMike Jordan
shaft wall inspection Phone #: ###-#### Internet Inspection Request from: Jessica Noland. shaft wall, 2nd. floor. ok
BLD-Wall cover12/10/200812/11/200812/11/2008APART
DetailsTony Young
shaft wall Phone #: ###-#### Internet Inspection Request from: Jessica Noland
wip on 2nd and 3rd floor
BLD-Other12/10/200812/10/200812/10/2008PPART
DetailsTony Young
shaft wall Phone #: ###-#### Internet Inspection Request from: Jessica Noland
wip,, 2nd and 3rd floor
BLD-Conference12/9/200812/10/200812/10/2008APART
DetailsTony Young
shaft wall Phone #: ###-#### Internet Inspection Request from: Jessica Noland
wip on 3rd floor shaft
BLD-Conference11/14/200811/17/200811/18/2008PPART
DetailsTony Young
Hour Separation Wall
Phone #: ###-#### ,, with 415
425 and 415 ,, will need fix from architect
DOC - Permit Finaled11/17/200811/17/200811/17/2008PCANC
DetailsTony Young
(This activity was added in error so we have changed the case status back to Issued.)
BLD-Conference11/14/200811/17/200811/17/2008PPART
DetailsDave Hannah
Hour Separation Wall
Phone #: ###-#### Internet Inspection Request from: Jessica Noland
BLD-Conference11/14/200811/14/200811/14/2008PFAIL
DetailsTony Young
Hour Separation Wall
Phone #: ###-#### Internet Inspection Request from: Jessica Noland
need to research and conf again,,
BLD-Framing/Rough-in11/6/200811/7/200811/7/2008PPASS
DetailsTony Young
inspection to cover Phone #: ###-#### Internet Inspection Request from: Jessica Noland
all walls ok to cover pending trades
FIRE-Conference10/31/200811/3/200811/3/2008ADONE
DetailsTroy Cobbley
Conference was for the placement of the electric alarm bell which I defered to the city approved sprinkler plans. I defered the knox box placement to Fire Station 9
BLD-Framing/Rough-in10/17/200810/17/200810/17/2008PPASS
DetailsTony Young
SHEETROCK SCREW INSPECTION NORTH AND WEST SIDES Phone #: ###-#### Internet Inspection Request from: Jessica Noland
BLD-Framing/Rough-in10/15/200810/16/200810/16/2008PFAIL
DetailsTony Young
drywall / screw inspection west side only Phone #: ###-#### Internet Inspection Request from: Jessica Noland
need screwed off per schedule on plans
BLD-Framing/Rough-in10/15/200810/16/200810/15/2008ACANC
DetailsTony Young
sheetrock/screw inspection west side only Phone #: ###-#### Internet Inspection Request from: Jessica Noland Inspection cancelled from web by: Jessica Noland
BLD-Framing/Rough-in10/10/200810/13/200810/13/2008APART
DetailsTony Young
soffit Phone #: ###-#### Internet Inspection Request from: Jessica Noland
south soffits ok to cover
BLD-Framing/Rough-in9/25/20089/26/20089/26/2008PPASS
DetailsTony Young
exterior framing inspection for cover
north, south and east walls Phone #: ###-#### Internet Inspection Request from: Jessica Noland
BLD-Wall cover9/22/20089/23/20089/23/2008APART
DetailsMike Jordan
partial inspection of steel stud framing for west and north walls Phone #: ###-#### Internet Inspection Request from: Jessica Noland.
ok to cover west wall exterior sise only. Additional screws added at headers.
BLD-Conference9/18/20089/22/20089/22/2008APART
DetailsTony Young
partial inspection of steel stud framing for west and north walls Phone #: ###-#### Internet Inspection Request from: Jessica Noland
most ok on exterior,, need more screws on some areas
BLD-Other9/3/20089/4/20089/4/2008APART
DetailsTony Young
roof pan deck inspection; special inspector from MTI will be on site. Phone #: ###-#### Internet Inspection Request from: Jessica Noland
ok pend special inspection report
BLD-Framing/Rough-in8/27/20089/2/20089/2/2008APART
DetailsDave Hannah
Roof Framing Phone #: ###-#### Internet Inspection Request from: Jessica Noland metal trusses on roof ok to cover
BLD-Concrete8/8/20088/11/20088/11/2008PCANC
DetailsTony Young
Phone #: ###-#### Internet Inspection Request from: Jessica Noland
BLD-Other8/8/20088/8/20088/11/2008PPART
DetailsTony Young
structural steel Phone #: ###-#### Internet Inspection Request from: Jessica Noland
pending S. I.
BLD-Concrete8/8/20088/11/20088/8/2008ACANC
DetailsTony Young
pouring 2nd & 3rd floors and stairs Monday a.m. Phone #: ###-#### Internet Inspection Request from: Jessica Noland Inspection cancelled from web by: Jessica Noland
BLD-Conference6/6/20086/9/20086/9/2008APART
DetailsTony Young
masonry rebar and grout pour 7am
special inspector on site Phone #: ###-#### Internet Inspection Request from: Jessica Noland
ok pend s. i. report
BLD-Conference6/3/20086/5/20086/5/2008APART
DetailsTony Young
masonry rebar and grout inspection
special inspector on site at 7 am Phone #: ###-#### Internet Inspection Request from: Jessica Noland
pend s. i. report
BLD-Conference6/3/20086/4/20086/4/2008APART
DetailsTony Young
masonry rebar and grout inspection
special inspector on site at 10 am Phone #: ###-#### Internet Inspection Request from: Jessica Noland
pend s i report
BLD-Concrete6/2/20086/3/20086/3/2008APART
DetailsTony Young
dan- special inspections will be onsite Phone #: ###-####
ok pend S. I. report
BLD-Conference5/15/20085/16/20085/16/2008PPART
DetailsTony Young
rebar placement and grout pour @ Noon 12pm Phone #: ###-#### Internet Inspection Request from: Jessica Noland
1st coarse,, S. I. on site
BLD-Footing4/28/20084/29/20084/29/2008PPART
DetailsTony Young
Phone #: ###-#### Internet Inspection Request from: Jessica Noland
walls ok pending special inspection
BLD-Footing4/25/20084/29/20084/28/2008ACANC
DetailsTony Young
Rebar Inspection Phone #: ###-#### Internet Inspection Request from: Jessica Noland Inspection cancelled from web by: Jessica Noland
BLD-Footing4/16/20084/18/20084/18/2008PPART
DetailsTony Young
REBAR INSPECTION Phone #: ###-#### Internet Inspection Request from: Jessica Noland
wip,, will have special inspection