BLD-Final | 3/21/2008 | 3/21/2008 | 3/21/2008 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/21/2008 at 7:49:34 AM. Contact: ###-####. ok for perm occ
|
FIRE-Final Inspection | 3/21/2008 | 3/21/2008 | 3/21/2008 | P | PASS |
Forrest France
|
|
|
HVAC units are below 2000 cfm per contractor and mechanical sheet, remainder of items completed, fire life safety inspection passed.
|
FIRE-Final Inspection | 3/19/2008 | 3/20/2008 | 3/20/2008 | P | NR |
Forrest France
|
|
|
Missing doors and hardware at some locations, need verification that HVAC units are below 2000 cfm as duct detectors are not installed, remainder of life safety is satisfactory.
|
BLD-Other | 3/5/2008 | 3/6/2008 | 3/6/2008 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/5/2008 at 2:45:04 PM. Contact: ###-####. ok to cover ceiling
|
BLD-Energy code compliance | 2/11/2008 | 2/12/2008 | 2/12/2008 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/11/2008 at 3:37:13 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/8/2008 | 2/8/2008 | 2/8/2008 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 2/8/2008 at 8:17:14 AM. Contact: ###-####.
|