BLD-Aging Inspection | 2/18/2010 | 2/18/2010 | 2/25/2010 | | PASS |
Tony Young
|
|
|
|
DOC - Permit Finaled | 2/25/2010 | 2/25/2010 | 2/25/2010 | A | PASS |
Tony Young
|
|
|
|
BLD-Final | 5/20/2009 | 5/22/2009 | 5/22/2009 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Jessica Noland
|
BLD-Final | 5/20/2009 | 5/20/2009 | 5/20/2009 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Jessica Noland conf on final,, need fire caulking in garage area,, need zoning final
|
FIRE-Final Inspection | 5/20/2009 | 5/20/2009 | 5/20/2009 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. The fire alarm system as shown on the approved drawings has not been installed but it is not required either as per the project scope of work. This was discussed with Scott Arlenno.
|
BLD-Final | 4/30/2009 | 5/1/2009 | 4/30/2009 | A | CANC |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Jessica Noland Inspection cancelled from web by: Jessica Noland
|
BLD-Other | 4/21/2009 | 4/21/2009 | 4/21/2009 | P | PASS |
Tony Young
|
|
|
ceiling grid inspection Phone #: ###-#### Internet Inspection Request from: Jessica Noland
|
BLD-Conference | 3/31/2009 | 3/31/2009 | 3/31/2009 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Jessica Noland
|
BLD-Conference | 3/30/2009 | 3/31/2009 | 3/31/2009 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Jessica Noland ducts from garage to office ok,, 26 gauge,, fire caulk around per code
|
BLD-Conference | 3/30/2009 | 3/30/2009 | 3/30/2009 | P | PEND |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Jessica Noland need to review firewall ?s w// plan review
|
BLD-Energy code compliance | 3/10/2009 | 3/11/2009 | 3/11/2009 | A | PASS |
Tony Young
|
|
|
Phone #: ###-####
|
BLD-Framing/Rough-in | 3/5/2009 | 3/6/2009 | 3/6/2009 | P | PART |
Jim Sly
|
|
|
need ok to insulate and cover Phone #: ###-#### Internet Inspection Request from: Jessica Noland C/N Repair 5/8 rock removed to allow for continuious roof vent at ridge. Call for insp of 5/8 rock membrane on E. 1hr wall. OK to Insulate.
|
BLD-Framing/Rough-in | 3/4/2009 | 3/5/2009 | 3/5/2009 | A | NR |
Jim Sly
|
|
|
Phone #: ###-#### Internet Inspection Request from: Jessica Noland Need to post address.....Need Plm R/I approved....Need approved plans ..... Talked to Bldr.....
|
BLD-Framing/Rough-in | 2/25/2009 | 2/25/2009 | 2/25/2009 | P | NR |
Tony Young
|
|
|
Dan Phone #: ###-#### need trades 1st
|
FIRE-Conference | 2/18/2009 | 2/19/2009 | 2/20/2009 | A | DONE |
Troy Cobbley
|
|
|
This was for a conference covering the sprinkler monitoring. It also included flushing the underground sprinkler supply
|
BLD-Framing/Rough-in | 1/14/2009 | 1/15/2009 | 1/15/2009 | A | CANC |
Tony Young
|
|
|
dan Phone #: ###-#### needs eval sheet from Jim Wylie PW first
|
BLD-Framing/Rough-in | 12/30/2008 | 12/31/2008 | 12/31/2008 | A | PASS |
Tony Young
|
|
|
fire wall inspection Phone #: ###-#### Internet Inspection Request from: Jessica Noland firewall ok in between
|
BLD-Concrete | 10/9/2008 | 10/10/2008 | 10/10/2008 | A | PART |
Tony Young
|
|
|
rebar inspection pour concrete AM Phone #: ###-#### Internet Inspection Request from: Jessica Noland rock placement in courtyard,, concrete under rocks
|
BLD-Concrete | 9/26/2008 | 9/29/2008 | 9/29/2008 | P | PASS |
Tony Young
|
|
|
rebar inspection Phone #: ###-#### Internet Inspection Request from: Jessica Noland footings ok,, corners surveyed in
|