BLD-Final | 2/19/2009 | 2/20/2009 | 2/20/2009 | A | PASS |
Tom Arcoraci
|
|
|
john - mid-morning please Phone #: ###-####
|
FIRE-Final Inspection | 2/19/2009 | 2/20/2009 | 2/20/2009 | A | PASS |
Troy Cobbley
|
|
|
fire life safety passed
|
BLD-Other | 1/29/2009 | 1/29/2009 | 1/29/2009 | P | PASS |
Jim Storey
|
|
|
john Note: sheet rock Phone #: ###-#### sw coner ok for cover.
|
BLD-Energy code compliance | 1/7/2009 | 1/8/2009 | 1/8/2009 | A | PASS |
Mike Jordan
|
|
|
john Phone #: ###-####
|
BLD-Other | 1/2/2009 | 1/2/2009 | 1/2/2009 | P | PART |
Dave Hannah
|
|
|
JOHN - NOTE; COVER Phone #: ###-#### ok to insulate ok to one side contractor will use insulation for fire blocking on hallway walls
|
BLD-Final | 12/8/2008 | 12/8/2008 | 12/8/2008 | P | PASS |
Mike Jordan
|
|
|
john- temporary occupancy Phone #: ###-####. Ok for temp occ.
|
BLD-Final | 12/5/2008 | 12/5/2008 | 12/5/2008 | P | NR |
Mike Jordan
|
|
|
|
BLD-Final | 12/4/2008 | 12/4/2008 | 12/4/2008 | P | NR |
Mike Jordan
|
|
|
john Phone #: ###-####
|
FIRE-Final Inspection | 12/1/2008 | 12/2/2008 | 12/3/2008 | A | PART |
Troy Cobbley
|
|
|
Per Ken Roule and Mark Sentenno the new area can be occupied until the existing areas have been remodeled and the rest of the construction is completed.
|
FIRE-Final Inspection | 11/20/2008 | 11/21/2008 | 11/21/2008 | A | PART |
Troy Cobbley
|
|
|
See redlined notes on city approved plans of area tested and completed. Contractor is looking for a temp occupancy for this area while they remodel the existing building under the same building permit. Contractor will be required tto contact Mark Senteno for temp occupancy. KR
|
BLD-Energy code compliance | 9/17/2008 | 9/18/2008 | 9/18/2008 | A | PASS |
Mike Jordan
|
|
|
John Phone #: ###-####. ok to cover.
|
BLD-Framing/Rough-in | 9/18/2008 | 9/18/2008 | 9/18/2008 | A | PART |
Mike Jordan
|
|
|
John Phone #: ###-####. All framing issues resolved. ok to insul. issued c/n to contractor to have architect supply detalis for 1hr wall and ceiling assemblies for fire riser room.
|
BLD-Framing/Rough-in | 9/8/2008 | 9/8/2008 | 9/8/2008 | P | PART |
Mike Jordan
|
|
|
john Phone #: ###-####. Needs to do airseal, complete nailing of hangars,and girder trusses.
|
BLD-Conference | 8/25/2008 | 8/26/2008 | 8/26/2008 | A | PASS |
Mike Jordan
|
|
|
john Phone #: ###-####. ME twith contractor on site to go over specs for platform lift to stage.
|
BLD-Framing/Rough-in | 8/12/2008 | 8/12/2008 | 8/12/2008 | P | NR |
Mike Jordan
|
|
|
john Phone #: ###-####. Needs ri insp. from other trades first.
|
BLD-Framing/Rough-in | 7/21/2008 | 7/22/2008 | 7/22/2008 | A | PART |
Mike Jordan
|
|
|
John Phone #: ###-####. Nailing for roof diaphragm, hand stack portion of roof framing and roof to cmuwall connections.
|
BLD-Framing/Rough-in | 7/10/2008 | 7/11/2008 | 7/11/2008 | A | PART |
Mike Jordan
|
|
|
john Phone #: ###-####. Shear nailing on exterior walls ok. Also reveiwed special insp. reports on puddle wels and joist to base plate connections for gym roof. ok. Als noted rfi from engineer on conversions for staples.
|
BLD-Framing/Rough-in | 7/7/2008 | 7/8/2008 | 7/8/2008 | A | PART |
Mike Jordan
|
|
|
John Phone #: ###-####. Need RFI from engineer of record for use of staples in leiu of nails for shear wall. Needs to provide straps at double top plate splices and complete install of straps from cmu wall to roof diaphragm.
|
BLD-Concrete | 6/10/2008 | 6/11/2008 | 6/11/2008 | A | DEFR |
Mike Jordan
|
|
|
John Phone #: ###-####. Placement for slab on grade, non structural item. Special insp. on site. Will reveiw reports on next insp.
|
BLD-Other | 6/9/2008 | 6/10/2008 | 6/9/2008 | A | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/9/2008 at 12:12:57 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Jun 9 2008 1:04PM.
|
BLD-Footing | 5/29/2008 | 5/30/2008 | 5/30/2008 | A | DEFR |
Mike Jordan
|
|
|
john Phone #: ###-####. Conc. placed when on site. Noted special insp. on site.
|
BLD-Foundation | 5/23/2008 | 5/23/2008 | 5/23/2008 | P | PART |
Mike Jordan
|
|
|
john Note: pouring concrete at 1:00 pm Phone #: ###-####
|
BLD-Footing | 5/22/2008 | 5/22/2008 | 5/22/2008 | P | PART |
Jim Sly
|
|
|
john - pouring at 2:30 Phone #: ###-#### Footing gridline F 5........Wall Gridline J 6.....OK pending MTI special inspections, tests, and approvals.
|
BLD-Footing | 5/21/2008 | 5/21/2008 | 5/21/2008 | P | PART |
Mike Jordan
|
|
|
John; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt. Stemwall at existing bldg. and north side.
|
BLD-Footing | 5/19/2008 | 5/19/2008 | 5/19/2008 | P | PART |
Mike Jordan
|
|
|
john Note: concrete coming by 1:00 Phone #: ###-####. North footing.
|
BLD-Footing | 5/15/2008 | 5/16/2008 | 5/16/2008 | A | PART |
Mike Jordan
|
|
|
john Phone #: ###-####. wip on perimeter footings. Noted that job wil have special insp. Also reviewed special insp. reports for soils work done to date. Noted to contractor that city approved plans need to be on the job site.
|