BLD-Aging Inspection | 1/9/2009 | 1/9/2009 | 1/9/2009 | | PASS |
Tom Arcoraci
|
|
|
|
DOC - Permit Finaled | 1/9/2009 | 1/9/2009 | 1/9/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Final | 11/2/2008 | 11/3/2008 | 11/3/2008 | P | PASS |
Tom Arcoraci
|
|
|
pending am mech final Phone #: ###-#### Internet Inspection Request from: John Lodman
|
BLD-Final | 10/31/2008 | 10/31/2008 | 10/31/2008 | A | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/31/2008 at 6:27:28 AM. needs mec final
|
FIRE-Final Inspection | 10/21/2008 | 10/22/2008 | 10/22/2008 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
FIRE-Alarm Testing | 10/20/2008 | 10/21/2008 | 10/22/2008 | P | PASS |
Troy Cobbley
|
|
|
testing for duct detectors passed
|
FIRE-Conference | 10/15/2008 | 10/15/2008 | 10/15/2008 | P | DONE |
Troy Cobbley
|
|
|
Per a telephone conversation with the general contractor the existing outside lights, with battery backup, will suffice for the exit discharge lighting.
|
BLD-Energy code compliance | 9/24/2008 | 9/25/2008 | 9/25/2008 | A | PASS |
Mike Jordan
|
|
|
please schedule closer to lunch if possible. thank you. Phone #: ###-#### Internet Inspection Request from: John Lodman
|
BLD-Framing/Rough-in | 9/16/2008 | 9/16/2008 | 9/16/2008 | P | PART |
Jim Sly
|
|
|
approval to insulate please Phone #: ###-#### Internet Inspection Request from: John Lodman Exterior walls OK....MTI reports on epoxy retro holdowns OK. Need insp on TI.....OK to insulate ext walls.
|
BLD-Other | 7/24/2008 | 7/25/2008 | 7/25/2008 | P | PASS |
Tom Arcoraci
|
|
|
Exterior shear panel inspection only. Interior hold down connections not complete, will request inspection prior to inside wall cover. Contact Matt-framing foreman- on-site. Phone #: ###-#### Internet Inspection Request from: John Lodman wip ok ext
|
BLD-Foundation | 6/26/2008 | 6/27/2008 | 6/27/2008 | A | PART |
Mike Jordan
|
|
|
mid morning if possible. thank you. Phone #: ###-#### Internet Inspection Request from: John Lodman. wip. Installing verts for slab dowels. Need paperwork for change in stemwall size from 12 inch to 10 inch from engineer.
|
BLD-Footing | 6/23/2008 | 6/24/2008 | 6/24/2008 | P | PASS |
Tom Arcoraci
|
|
|
subgrade inspected by MTI on 6/23 as requested. early afternoon rebar inspection please. thank you. Phone #: ###-#### Internet Inspection Request from: John Lodman
|
BLD-Footing | 6/20/2008 | 6/20/2008 | 6/21/2008 | P | NR |
Dave Hannah
|
|
|
inspect footing subgrade prior to rebar placement- thank you. Phone #: ###-#### Internet Inspection Request from: John Lodman needs to have a geo tect engineer ok this footing sub grade
|