Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD08-00622
StatusFinaled
Name STEELWOOD ENTERPRISES LLC
Site Address 1901 N WILDWOOD AVE
Project NameSTEELWOOD FLEX CONDOS
Customer Number 
ePlanReviewNo
Description
(MEDIA SPECIALTIES - STEELWOOD FLEX CONDOS - BUILDING #5 - SOUTH END) This building is NOT fire sprinklered. As building shell work, to construct a new 1,943 square foot 2nd story within a new 4,955 square foot building. The building was constructed under permit BLD05-01656. Work is to include concrete footings, steel columns, wood columns, wood ledgers, wood beams, wood floor trusses, shear / bearing walls, floor sheathing, and a stairway within a 1-hr fire-resistance-rated stairway enclosure. In addition, 2 restrooms accessible to the disabled will be constructed. They will be common restrooms available to more than one tenant space. As tenant improvement work, to create a 2,304 square foot tenant space within a new building (1,412 square feet on the 1st story and 892 square feet on the new 2nd story). Work is to include 2 overhead door infills, interior nonbearing walls, interior doors, and interior finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/10/200812/10/200812/10/2008APASS
DetailsJim Sly
OK for Perm Occ.
BLD-Final12/9/200812/10/200812/10/2008ACANC
DetailsJim Sly
Ron Phone #: ###-####
OK for Perm Occ.
BLD-Final12/2/200812/2/200812/2/2008PPART
DetailsJim Sly
ron Phone #: ###-####
OK for Temp........OK for Perm when fire damper installed in cold air Ret.....Ceiling.
FIRE-Final Inspection11/26/200811/28/200811/28/2008APASS
DetailsTroy Cobbley
fire life safety passed
BLD-Final11/26/200811/28/200811/28/2008AFAIL
DetailsJim Sly
ron Phone #: ###-####
Handrails and dampers
BLD-Framing/Rough-in10/14/200810/14/200810/14/2008PPASS
DetailsJim Sly
ron Phone #: ###-####
BLD-Framing/Rough-in10/13/200810/14/200810/14/2008ACANC
DetailsJim Sly
ron Phone #: ###-####
BLD-Framing/Rough-in10/10/200810/13/200810/13/2008APART
DetailsJim Sly
ron Phone #: ###-####
OK to insulate....advised Contr....fire dampers at floor/ceiling assembly.
BLD-Conference10/7/200810/8/200810/8/2008ADONE
DetailsJim Sly
kevin - please call 1/2 hr prior to inspection Phone #: ###-####
FIRE-Conference9/16/20089/16/20089/16/2008PCANC
DetailsTroy Cobbley
The conference was not required on site and was taken care of over the phone.
BLD-Conference9/15/20089/15/20089/15/2008PDONE
DetailsJim Sly
Ron Phone #: ###-####
BLD-Other8/19/20088/19/20088/19/2008PCANC
DetailsJim Sly
ron - please call for access Phone #: ###-####
BLD-Other8/19/20088/19/20088/19/2008PPASS
DetailsJim Sly
ron - grout - please call for access Phone #: ###-####
Non shrink grout under columns....OK
BLD-Other8/14/20088/15/20088/15/2008ANR
DetailsJim Sly
Ron- welding- call for access Phone #: ###-####
Need to inspect non shrink grout under steel columns prior to placing concrete.
BLD-Framing/Rough-in8/14/20088/14/20088/14/2008PPART
DetailsMike Jordan
Ron Phone #: ###-####.. verified anchor bolts in ts column base plates. Told Ron to place non shrink grout unser baseplates prior to placing remaining conc.
BLD-Foundation8/7/20088/8/20088/8/2008APART
DetailsMike Jordan
Ian Phone #: ###-####wip. Special insp. to verify reinforcement for interior column pad footings, also will do epoxy insp.