BLD-Final | 8/7/2008 | 8/8/2008 | 8/8/2008 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 8/7/2008 at 3:09:13 PM. Contact: ###-####. ok for cof o
|
FIRE-Final Inspection | 8/7/2008 | 8/8/2008 | 8/8/2008 | A | PASS |
Forrest France
|
|
|
Corrections verified for compliance, shell permit finaled, duct detectors deleted due to cfm below 2000, life safety inspection passed.
|
FIRE-Final Inspection | 8/5/2008 | 8/6/2008 | 8/6/2008 | A | FAIL |
Troy Cobbley
|
|
|
The shell building permit needs finaled prior to this permit being finaled. Per Sam Rogers we do not need to reverify the elevator recall since it has been approved by the State of Idaho elevator inspector but the Area of Refuge still needs inspected. Those two items are required for the shell. Items found wrong on the tenant improvement include: Suite number needs to be provided, repair all of the exit signs and emergency lights as marked on sheet E1.0 and either install the duct dectors as discussed or remove them since they are not shown on the drawings and both units are less than 2,000 cfm and mount the fire extinguisher.
|
BLD-Other | 7/15/2008 | 7/16/2008 | 7/16/2008 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 7/15/2008 at 11:38:42 AM. Contact: ###-####.ceilling ok for cover.
|
BLD-Framing/Rough-in | 6/23/2008 | 6/23/2008 | 6/23/2008 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/23/2008 at 9:54:56 AM. Contact: ###-####.
|