DOC - Permit Finaled | | | 11/13/2008 | | DONE |
|
|
|
Letter of completion issued
|
BLD-Final | 11/7/2008 | 11/10/2008 | 11/10/2008 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 11/7/2008 at 9:08:36 AM. Contact: ###-####.
|
BLD-Final | 8/21/2008 | 8/22/2008 | 8/22/2008 | P | PART |
Tony Young
|
|
|
rob Phone #: ###-####
|
FIRE-Final Inspection | 8/21/2008 | 8/22/2008 | 8/22/2008 | P | PASS |
Forrest France
|
|
|
Corrections finished, fire life safety passed.
|
FIRE-Final Inspection | 8/13/2008 | 8/15/2008 | 8/15/2008 | P | PART |
Forrest France
|
|
|
Final pending ceiling work at the basement level computer lab and ceiling/fire sprinkler work at the new fabrication room. EM lights and exit signs tested okay, project related FA is finished, remiander of life safety per the scope of work is acceptable.
|
BLD-Other | 8/11/2008 | 8/11/2008 | 8/11/2008 | P | PART |
Tony Young
|
|
|
Rob- ceiling Phone #: ###-####
|
BLD-Other | 8/9/2008 | 8/11/2008 | 8/11/2008 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 8/9/2008 at 2:52:10 PM. Contact: ###-####. ceiling ok pending trades
|
BLD-Other | 7/28/2008 | 7/29/2008 | 7/29/2008 | A | PASS |
Tony Young
|
|
|
Rod Note: ceiling cover Phone #: ###-#### 1st floor and basement I. T rooms ok on ceiling grid
|
BLD-Framing/Rough-in | 7/23/2008 | 7/23/2008 | 7/23/2008 | P | PART |
Tony Young
|
|
|
rob Phone #: ###-#### attic ties , ok pending s. i. reports
|
BLD-Framing/Rough-in | 7/22/2008 | 7/23/2008 | 7/23/2008 | A | PART |
Tony Young
|
|
|
rob Phone #: ###-#### seismic hold downs in attic,, and beam through ties
|
BLD-Framing/Rough-in | 7/14/2008 | 7/14/2008 | 7/14/2008 | P | PART |
Dave Hannah
|
|
|
rob Phone #: ###-#### see marked up plans second floor strapind ok to cover
|
BLD-Framing/Rough-in | 7/9/2008 | 7/10/2008 | 7/10/2008 | P | PART |
Dave Hannah
|
|
|
Rob Phone #: ###-#### see marked up areas on plans looked at framing and floor to wall straping on second fl and replacement of sheet rock lid in basement hallway all ok to cover
|
BLD-Framing/Rough-in | 7/7/2008 | 7/8/2008 | 7/8/2008 | P | PART |
Jim Sly
|
|
|
Rob Phone #: ###-#### Rock installed...lids Rooms 306 300 403 408 1st floor ....OK to cover walls 2nd floor area E on plan.
|
BLD-Framing/Rough-in | 7/2/2008 | 7/2/2008 | 7/2/2008 | P | PART |
Tony Young
|
|
|
Rob Phone #: ###-#### basement hall way drag struts,, pending ok from S I and structural engineer on as built
|
BLD-Framing/Rough-in | 7/1/2008 | 7/1/2008 | 7/1/2008 | P | PART |
Tony Young
|
|
|
Rob Phone #: ###-#### wall and straps as noted on plans
|
BLD-Other | 6/26/2008 | 6/27/2008 | 6/27/2008 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/26/2008 at 5:12:02 PM. Contact: ###-####. straps in room 302,, ceilings ok in 303 and 305 ok
|
BLD-Framing/Rough-in | 6/26/2008 | 6/26/2008 | 6/26/2008 | P | PART |
Tony Young
|
|
|
Rob- ele insp also in the PM Phone #: ###-#### ok anop
|
BLD-Framing/Rough-in | 6/17/2008 | 6/18/2008 | 6/18/2008 | P | PART |
Tony Young
|
|
|
rob - basement - east wing seismic Phone #: ###-#### seismic straps ok as noted on plans,, pending S. I. report on pull tests
|
BLD-Framing/Rough-in | 6/17/2008 | 6/18/2008 | 6/18/2008 | A | PART |
Tony Young
|
|
|
rob - basement classroom and storage Phone #: ###-#### - after 9:30 please walls ok to cover as noted on plans (anop)
|
BLD-Framing/Rough-in | 6/13/2008 | 6/13/2008 | 6/13/2008 | P | PASS |
Jim Storey
|
|
|
rob Phone #: ###-#### wall sec basement stair #3 ok for cover.
|
FIRE-Conference | 6/10/2008 | 6/11/2008 | 6/11/2008 | A | DONE |
Forrest France
|
|
|
On site conference regarding exit signage at the new wall and exit door located in the basement level northeast side.
|
FIRE-Conference | 6/9/2008 | 6/10/2008 | 6/10/2008 | A | DONE |
Forrest France
|
|
|
Rob- fire life saftey Phone #: ###-####
|