BLD-Final | 8/26/2008 | 8/27/2008 | 8/27/2008 | A | PASS |
Mike Jordan
|
|
|
Mike Please call 1/2 hr before going out ( ele final is also in for the am) Phone #: ###-####. ok for perm occ.
|
BLD-Final | 8/25/2008 | 8/25/2008 | 8/25/2008 | A | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/25/2008 at 7:17:50 AM. Contact: ###-####. Still needs elec. and plumbing to sign perm occ.
|
FIRE-Final Inspection | 8/21/2008 | 8/21/2008 | 8/21/2008 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 8/13/2008 | 8/14/2008 | 8/14/2008 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/13/2008 at 3:53:14 PM. Contact: ###-####. ok for temp occ. Needs other trades to sign perm. Also needs to install boots under sinks, install missing safety glazing and finsh transitions on carpet to tile/congoliuem at floor elevation changes.
|
FIRE-Final Inspection | 8/13/2008 | 8/14/2008 | 8/14/2008 | A | PART |
Troy Cobbley
|
|
|
A temporary was given with Sam Rogers permission until the fire alarm permit can be finaled. See the project related fire alarm permit for details. The two exit signs from the previous correction notice have been repaired.
|
FIRE-Final Inspection | 8/12/2008 | 8/13/2008 | 8/13/2008 | A | FAIL |
Troy Cobbley
|
|
|
The project related fire alarm permit needs to be finaled. Also the very west most second floor corridor exit sign needs repaired and another needs to be added at the second floor elevator corridor/main corridor junction as shown on the city approved drawings. All other items are ok.
|
BLD-Final | 8/12/2008 | 8/13/2008 | 8/13/2008 | P | NR |
Mike Jordan
|
|
|
Mike ###-####. Needs plumbing final, fire/life/safety.
|
BLD-Framing/Rough-in | 8/5/2008 | 8/6/2008 | 8/6/2008 | A | PASS |
Mike Jordan
|
|
|
Terry- ceiling grid Phone #: ###-####. Remaining rooms on 2nd floor ok.
|
BLD-Framing/Rough-in | 7/30/2008 | 7/31/2008 | 7/31/2008 | A | PART |
Mike Jordan
|
|
|
mike - ceiling grid - please call 1/2 hr prior to inspection Phone #: ###-####. ceiling grid 2nd floor. ok except for the four rooms were elec. ri has not passed.
|
BLD-Framing/Rough-in | 7/29/2008 | 7/30/2008 | 7/30/2008 | A | CANC |
Mike Jordan
|
|
|
Mike- call before going Phone #: ###-####
|
BLD-Framing/Rough-in | 7/24/2008 | 7/24/2008 | 7/24/2008 | P | PASS |
Mike Jordan
|
|
|
mike - hard lid inspection Phone #: ###-####. hardlids for restrooms on 2nd. floor, remaining interior steel stud walls on 2nd floor were edward jones was occuping.
|
BLD-Framing/Rough-in | 7/21/2008 | 7/21/2008 | 7/21/2008 | P | PASS |
Mike Jordan
|
|
|
Mike- ceiling grid Phone #: ###-####
|
BLD-Energy code compliance | 6/27/2008 | 6/27/2008 | 6/27/2008 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 6/26/2008 | 6/27/2008 | 6/27/2008 | P | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Verified backing for ADA hardware in restroom at 2nd. floor.
|
BLD-Framing/Rough-in | 6/25/2008 | 6/26/2008 | 6/26/2008 | P | PART |
Mike Jordan
|
|
|
mike Note: please call 1/2 before inspection Phone #: ###-####. Interior steel stud walls at 2nd. floor. Need to verify backing for ADA harware in restroom @ 2nd. floor. Als pend. plumbing ri insp. on 2nd. floor.
|
BLD-Framing/Rough-in | 6/25/2008 | 6/25/2008 | 6/25/2008 | P | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/25/2008 at 6:42:33 AM. Contact: ###-####. Inspection cancelled from web by: Alexandra Rahn
|
BLD-Energy code compliance | 6/16/2008 | 6/17/2008 | 6/17/2008 | P | PART |
Jim Sly
|
|
|
mike Phone #: ###-#### 1st floor........OK
|
BLD-Framing/Rough-in | 6/13/2008 | 6/16/2008 | 6/16/2008 | P | PART |
Jim Sly
|
|
|
Mike- call prior to going Phone #: ###-#### 1st floor OK
|